cost planning estimation tutorial Flashcards

1
Q

What is the objective of a cost planning exercise

A

to define as accurately as possible the minimum realistic cost of executing an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the various purposes of undertaking a cost planning exercise

A

comparing technical solutions

identifying financial commitment

as a basis for tendering

as a yardstick against which performance can be measured

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

which parties undertake a cost planning exercise and why

A

All parties, particularly promoter and contractor

contractor = to provide a tender

the promoter = to establish the likely final cost of project and thus to secure funds for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the main elements of an estimate? (give subcategories)

A

Personnel - labour (various skillsets of labour required, management)

Plant (or equipment) - mechanical, non mechanical

Materials - consumables, steel, pipes, bricks, tiles, cladding, steelwork

Subcontractors

Specialist services

overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are main forms of cost data

A

period based - hourly, daily or weekly costs

fixed costs -

unit output costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Raw cost data are pretty much useless on their own, why?

A

costs data particularly for labour and plant are period based

this doesn’t indicate cost for an amount of work, which needs to be known for estimating purpose

it can be converted to a unit output if knowledge of the resources productivity is known

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

suggest items which would come under ‘overheads’ cost element

A

staff

accommodation (offices)

small tools and plant

welfare and first aid

transport

insurance

security

storage

workshops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what influences the accuracy of a cost estimate

A

accuracy of cost model

accuracy of data fed into it

number of items it contains

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is the main advantage and disadvantage of BoQ model

A

Main advantage - allows comparison of different estimates / tenders

main disadvantage - time consuming to prepare, does not allow direct entry of overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimation of duration of activities requires 3 types of data, list these and how data is obtained?

A

Quantity of each item - (MTO) Material take off from drawings, or from BoQ

Resources required - usually from experience of managing these resources

unit output - most difficult
1- from experience or historical production records
2 - using published ‘standard’ outputs
3- from work study, although only used with repetitive processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How can PM ensure critical activity does not affect the overall duration of a project

A

ensure activities preceeding finish on time

ensuring duration of activity is monitored and controlled so it does not increase

ensuring adequate sufficient resources are available

ensuring finish time as planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly