Cost estimation methods Flashcards
Expert judgement
Expert judgment is also used in other methods as Reserve, group decision-makin techniques and analogous cos estimation.
Expert judgment is basically someone that provides valuable insight.
The gut feeling/intuition of someone who is experienced.
Analogous estimating
Also called top-down estimating
This method uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project.
Analogous cost estimating uses historical information and expert judgment.
Generally less costly and less time consuming than other techniques, but also less accurate.
The downside of using this techniques is that it estimates based on only one historical point, which may not be representive of the problem being addressed.
Parametric estimating
Uses a statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work.
Bottom-Up Estimating
WBS
Three-Point Estimating
Reserve Analysis
Cost of Quality
Don’t need this fucker
Project Management Software
Don’t need this fucker
Vendor Bid Analysis
Don’t need this fucker
Group Decision-Making Techniques
Don’t need this fucker
What is the Analogous cost estimation equation?
Cost of new project = (Cost driver new project/cost driver old project) * Cost of old project
y_2 = (x_2/x_1)*y_1