1
Q

A project is over budget if the CV is…

A

Negative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A project is on schedule if the SV is…

A

Equal to 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It is feasible to complete the project within the revised budget if the TCPI is…

A

Greater than 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly