Construction cost definition

A

Total cost of the work to the client:
-result of coordination by architect,
-construction management fees
-all other fees for procurement + coordination of services
-all applicable taxes (except value added taxes)

*construction cost excludes the fee of architect, consultants, land cost, land dev charges, other professional fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Direct costs to construction:

A

-Materials
-labor
-equipment
-contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Indirect costs;

A

-general conditions
-administration + profit of contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Professional costs;

A

-studies
-professional services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Divers costs:

A

-taxes
-inflation
-other contingencies
-construction contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

General fees are determined by?

A

00-procurement and contracting requirements
01-general conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

3 categories of general conditions

A
  1. Costs related to construction cost
    -insurance
    -permits
    -fines
    -Financing costs
  2. Length of the projects
    -superintendent
    -PM
    -winter conditions
    -security
    -fence
    -crane
    -heating
    -cleaning + garbage
  3. Punctual costs
    -professional fees
    -protection of existing buildings
    -permits + fines
    -signs
    -inspections
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4 types of estimation

A

-elemental : uniformat 2 : most popular
-progressive
-parametric
-volume
-unitary
-surface

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Progressive estimation; advantages + inconveniences

A

Adavantages;
-reliable when done well

Inconveniences:
-Lots of time
-requires high degree of specialization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Elemental cost

A

Advantages ;
Most popular
Divides building in large elements
-easy to change elements ; value engineering
-used old + new buildings

disadvantages;
-doesn’t use same divisions as trades
-very oversimplified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Surface

A

-used in real estate
-arch’s have lots of data
-a good very general view;

-doesn’t account for unique aspects of a project
-oversimplified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Units

A

-very general
-very fast
-must be adapted