Contractual Documents Flashcards
Design-Award-Build (DAB) Or Design-Bid-Build (DBB)
An owner develops contract documents with an architect or engineer consisting of a set of blueprints and a detailed specification. Bids are solicited from contractors based on these documents; a contract is then awarded to the lowest responsive and responsible bidder.
Design-Build (DB)
An owner contracts with only one entity to provide both design and construction services. Cons: 1. owner does not have much control over design once the contract is signed. 2. easily run into disputes. 3. owner needs to know specific performance requirements. This method is typically used when owner has building experience.
common methods of project delivery includes
- Design-Award-Build 2. Fast Track 3. Design-Build or Bridging (DB with AE/PM) 4. Integrated Project Delivery
Integrated Project Delivery (IPD)
Completing a project in which all the participants collaborate closely from conceptual phase. Highly collaborative, depends heavily on technology, communication, and having an integrated building information model (BIM) that everyone on the team has access to.
Fast Track Or DBB with Construction Management (DBB with CM)
With partially completed contract documents, an owner will hire a construction manager to act as an agent. As substantial portions of the documents are completed, the construction manager will solicit bids from suitable subcontractors. This allows construction to proceed more quickly and allows the owner to share some of the risk inherent in the project with the construction manager.
Agency vs. Vendor
Agency involve 3 parties: the principal, the agent and the third party. Architect (agent) acts on behalf of the owner and has the authority to perform certain duties. Contractor is considered as a vendor, only supplies product or service and primarily acts in his or her own interests.
Single-Prime Contract vs. Multi-Prime Contract
Single prime only has one general contractor. The owner has one single source of responsibility. It’s easier for architect to do construction administration. Multiple prime has individual contracts with General Construction, HVAC, Plumbing, Electrical contractors. Difficult for scheduling, coordination, and manage. The most frequent use of multiple prime contracts is for phased construction, in which contracts are awarded sequentially for each phase . This type of construction is also referred to as the “fast-track” method.
3 common compensation methods for contractor
- stipulated sum / lump sum 2. guaranteed maximum price (GMP) 3. cost-plus-fee
3 common compensation methods for architect
- stipulated sum / lump sum / fixed fee 2. cost plus fee 3. percentage of construction cost
Lien
A mechanic’s lien is a claim by one party against the property of another party for the satisfaction of a debt and a common method for an architect, contractor or material supplier to gain payment.
Liquidated Damage
damages whose amount the parties designate during the formation of a contract for the injured party to collect as compensation upon a specific breach (e.g., late performance).
can be found in Owner-Contractor agreements
Surety Bond or Bond
an agreement by which the surety (the bonding company) agrees to be responsible to the obligee (the owner) for the default or debts of the principal (the contractor). A protection for the owner against debt and defaults. Contractor pays. Default: failure to meet the legal obligations in contract
Completion Bond
The project will be complete free of liens. Completion bonds are surety bonds which a contractor submits to a bank or other creditor that has disbursed a loan to finance a project.
Bid Bond
The bidder, if awarded a contract, will enter into the contract within a specified time, and in accordance with the bidding documents.
Performance Bond
To protect the interest of the owner, and ensure that the work will be completed in accordance with the contract documents.