Contracts Flashcards

1
Q

What is AIA B101?

A

Owner-Architect contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AIA B101 - Article 1: Initial Information

A

program
physical characteristics
owner’s budget for cost of work, delivery method, milestone dates
owner’s & arch’s representative
owner’s consultants & contractors (geo tech)
architect’s consultants & contractors for basic services (structural, mechanical, electrical)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AIA B101- Article 2: Architect’s Responsibilities

A

arch must be licensed in local jurisdiction
provide services in accordance with standard of care
arch to carry insurance policies: general liability, automobile, worker’s comp, employer’s liability, professional liability (errors + omissions)
arch can request reimburse for addle insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AIA B101 - Article 3 Scope of Architect’s Basic Services

A

coordinate with owner & owner’s consultants
submit schedule of services (owner provides date for commencement of construction and date of substantial completion)
contact govt authorities for approval and filing of construction docs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Architect’s Basic Services?

A

Schematic Design
Design Development
Construction Document
Procurement Phase (Competitive bidding vs. negotiated proposals)
Construction Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

AIA B101- Article 4: Supplemental Services

A

Supplemental Services: activities beyond Basic Services (BIM management, cost estimates, landscape design etc)
Additional Services: services added after the contract is signed (digital models, public presentations, out of sequence submittal review, substitutions from owner/gc that require cd changes)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

AIA B101 - Article 5: Owner’s Responsibilities

A

owner to:
provide budget w/ contingency
provide survey, borings, site remediation
coordinate work of their consultants with architect’s work
notify architect if any issues with arch’s dwgs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

AIA B101 - Article 6: Cost of Work

A

arch to evaluate cost of work
if lowest bid is above cost of work, arch to provide budget reconciliation services at no cost
if procurement phase does not start within 90 days of completion of CD’s, owner’s cost of work to be adjusted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Cost of Work?

A

total cost to owner to construct all elements of project designed or specified by the architect
includes: contractor’s general conditions, overhead, and profit
discludes: architect’s fee, cost of land, contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

AIA B101 - Article 7: Copyrights and Licenses

A

architect grants non-exclusive license to instruments of service to owner for purpose of constructing and maintaining project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

AIA B101 - Article 8: Claims and Disputes

A

if claim or dispute happens - follow steps of conflict resolution: negotiation, mediation, arbitration, litigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

AIA B101 - Article 9: Termination or Suspension

A

if owner suspends project or architect’s services, architect is compensated for services to that point. When project resumes, architect is compensated for project related expenses during interruption
owner can terminate services without cause
owner pays architect a termination fee and licensing fee if they want to continue using instruments of service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

AIA B101 - Article 11: Compensation

A

Typical proportion of fee:
SD 15%
DD 20%
CD 45%
BID 5%
CA 15%
Reimbursable expenses: out of town travel, permitting, printing, renderings, site office expenses, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is AIA A201?

A

General Conditions (does not describe a contractural relationship)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

AIA A201 - Article 2: Owner

A
  • the owner is required to pay for approvals, easements, assessments, and all charges required for construction.
  • the owner must retain an architect licensed in the jurisdiction of the project
  • the owner has the right to stop work if it is nonconforming
  • the owner has the right to correct work if the contractor neglects to carry out work, and fails to correct it after 10 days notice
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

AIA A201 - Article 1: General Provisions

A

the architect and their consultants have sole ownership over the instruments of service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

AIA 201 - Article 3: Contractor?

A
  • the contractor must carefully study the cd’s and promptly report any inconsistencies or omissions
  • the contractor is NOT required to determine if the cd’s conform to laws, rules, or regulations
  • the contractor is solely responsible for construction means, methods, techniques, sequences, and procedures
  • the contractor must provide and pay for labor, materials, equipment, tools, water, heat, facilities, etc
  • the contractor secures and pays for the building permit and other permits required by govt agencies
  • contractor must report concealed or unknown conditions to the architect & owner within 14 days of observance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

AIA 201 - Article 3: Contractor (cont)

A
  • after contract is awarded, the contractor submits a construction schedule, with project commencement, milestones, substantial completion, submittal schedule
  • shop dwgs, product data, and samples are NOT contract documents, but proof of conformance provided by contractor
  • architect is responsible for approving submittals, samples, and project data for conformance with design docs but contractor is still ultimately responsible for their compliance
  • contractor indemnifies and holds harmless the architect & owner from claims resulting from performance of the work if the contractor’s negligence or omissions caused the damage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

AIA 201 - Article 4: Architect

A
  • architect serves as owners rep during construction unless another party is specified
  • architect prepares change orders & construction change directives
  • architect determines if the contractor’s work is in accordance with cd’s and reports nonconforming work to the owner
  • architect provides certificates of payment for the contractor at stipulated intervals
  • architect must approve dates of substantial completion and final completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

AIA A201 - Article 5: Subcontractors

A

contractor takes liability for the subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

AIA A201- Article 6: Construction by Owner or by Separate Contractors

A

the owner is responsible for coordinating their own contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

AIA A201 - Article 7: Changes in the work

A

-change order - signed by owner, contractor, and architect. describes a change in work with an agreed upon price and schedule impact
-construction change directive: signed by owner & architect, but NOT contractor. a change in the work without an agreed upon price & schedule impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

AIA A201 - Article 8: Time

A

contract time is binding but may be extended to accommodate: faults of architect, owner, or separate contractor. fire. adverse weather. changes to the work.
contract time is ‘of the essence’ - work must be completed by specified dates or they are in breach of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

AIA A201 - Article 9: Payments and Completion

A
  • contractor provides a schedule of values (either stipulated sum or GMP) to arch. this is used by arch to review contractor’s applications for payment
  • contractor submits an itemized application for payment
  • within 7 days of receipt of application for payment, arch issues a certificate of payment to the owner. could be entire sum or partial amount they think is owed
  • Certificate of payment: certifies that work has progressed to the point indicated by the contractor
  • Arch can withhold C of P if - work is nonconforming, contractor cannot pay their subcontractors, work cannot be completed for the contract sum or time
  • Substantial completion: when owner can occupy and utilize project
  • final completion: arch issues last certificate for payment, work is complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

AIA A201 - Article 10: Protection of persons and property

A
  • contractor is responsible for safety on job site
  • contractor designates a site safety personnel
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

AIA A201 - Article 11: Insurance and bonds

A
  • contractor is responsible for purchasing commercial general liability insurance
  • owner is responsible for purchasing property insurance
  • if there is a fire, all rights are waived and losses are covered by property insurance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

AIA A201 - Article 12: uncovering and correction of work

A
  • cost of correcting work and resulting arch services required is at contractor’s expense
  • if it’s conforming, contractor can ask for compensation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

AIA A201 - Article 13: Miscellaneous Provisions

A
  • ## contractor must inform the arch of tests and inspections so that they may be present
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

AIA A201 - Article 14: termination or suspension of contract

A

contractor can terminate contract within 7 days notice if work is topped through no fault of contractor for: 30 consecutive days, 120 days in a 365 day period
- owner may terminate contract for cause or convenience
- if contractor fails to do work, ignores relevant laws, or fails to pay their subcontractors, the owner can terminate the contract with 7 days notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

AIA A201 - Article 15: Claims and disputes

A
  • claims and disputes amongst parties must be within 10 years of sub completion
  • contractor and owner waive claims against each other for consequential damages arising out of this contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is A101?

A

Owner-Contractor agreement (stipulated sum)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

AIA A101 - Article 1: The Contract Documents

A
  • contract documents include the drawings, specifications, and addenda
  • these are a binding component of the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

AIA A101 - Article 2: The Work

A
  • the work is described the contract documents
34
Q

AIA A101 - Article 3: date of Commencement and substantial completion

A
  • dates are listed as binding and used to asses the contract time
  • if contractor fails to achieve substantial completion date listed, through no fault of other parties, damages may be assessed
35
Q

AIA A101 - Article 4: Contract Sum

A
  • the contract sum is a stipulated sum, which means a fixed fee subject to the following modifications: alternates, allowances, unit prices, liquidated damages
  • if not stipulated sum, then it could be ‘cost-plus-fixed fee’ with or without a GMP (covered in diff AIA Contracts)
36
Q

AIA A101 - Article 5: Payments

A
  • apps for payment to be submitted to arch each month. amounts to be based on schedule of values
  • schedule of values: allocates contract sum among various portions of work
  • retainage: for each progress payment, the owner may withhold a designated amount, to be awarded at sub completion
  • final payment: entire unpaid balance owed to contractor. must be paid within 30 days of arch’s issuance of final certificate of payment
37
Q

AIA A101 - Article 6: dispute resolution

A
  • arch will serve as initial decision maker
  • following negotiation and mediation, litigation is the default dispute resolution process unless arbitration is selected
38
Q

AIA A101 - Article 7: termination or suspension

A

-contractor can terminate contract within 7 days notice if work is topped through no fault of contractor for: 30 consecutive days, 120 days in a 365 day period
- owner may terminate contract for cause or convenience
-

39
Q

AIA A101 -Article 8: miscellaneous provisions

A
  • identify owner’s rep & contractor’s rep
  • insurance and bonds to be purchased and maintained alongside this contract
40
Q

What is AIA C401?

A

Architect-Consultant agreement

41
Q

AIA C401 - Article 1: General provisions

A

-consultant is independent contractor and is responsible for own means and methods.
- not an employee of the arch
- arch assumes toward consultant all obligations that owner assumes toward arch

42
Q

AIA C401 - Article 2: consultant’s responsibilities

A
  • consultant to uphold standard of care
  • consultant to maintain following insurance: commercial general liability, automobile liability, workers comp, employers liability, prof liability
43
Q

AIA C401 - Article 3: scope of consultants services

A

listed in this section: scope of services, phasing of services, number of site visits, any other commitments

44
Q

AIA C401 - Article 4: additional services

A

consultant will not proceed to provide addlt services until arch’s written authorization

45
Q

AIA C401 - Article 5: architects responsibilities

A

-provide available info in a timely manner to consultant
- furnish updated estimates of cost of work to consultant
- provide notice to consultant if any errors or omissions in consultant’s work

46
Q

AIA C401 - Article 6: cost of work

A

consultant shall prepare estimates of cost of work for the relevant portion of the project
consultant to participate in VE process

47
Q

AIA C401 - Article 7: copyright and licenses

A

consultant grants to arch a license to use consultant’s instruments of service

48
Q

AIA C401 - Article 8: claims and disputes

A
  • consultant indemnifies and holds arch harmless from damages arising from third party claims, to the extent that the damages are caused by negligent acts or omissions of the consultatn
49
Q

What are the A Series of contracts?

A

Owner-Contractor Agreements

50
Q

What are some important A Series contracts?

A

AIA A101-2017: Owner-Contractor. Design-Bid-Build
AIA A133-2009: Owner-Construction Manager, Contractor. Cost of Work plus fixed fee
AIA A195-2008: Owner-Contractor. IPD
AIA A201-2017: General Conditions for contract of construction
AIA A295-2008: General Conditions for the contract of construction (IPD)
AIA A701-2018: Instructions to bidders
AIA A305: Contractor’s qualification statemtn

51
Q

What are the B-Series contracts?

A

Owner-Architect Agreements

52
Q

What are some important B-series contracts?

A

AIA B101- Standard form of agreement between owner & arch
AIA B102: owner-arch, without predefined scope
AIA B103: owner-arch, complex projects
AIA B104: owner-arch, mid-size projects
AIA B105: owner-arch, standard short form (residential or small commercial)
AIA B106: owner-arch, pro bono
AIA B121: owner-arch, for services provided under multi[le service orders
aia b195: owner-arch, IPD
AIA B214: standard form of architect’s services, LEED certification

53
Q

What are the C-Series of contracts?

A

Other agreements

54
Q

What are some important C-Series contracts?

A

AIA C101 - Joint revenue agreement for professional services
AIA C103 - standard form of agreement between owner & consultant, without predefined scope
AIA C104 - arch-consultant agreement
AIA C191 - multi-party agreement for IPD
AIA C195 - single purpose entity for IPD projects

55
Q

What are D-Series agreements?

A

Miscellaneous documents/guides

56
Q

What is D200?

A

Project checklist, to serve as a record of owner/arch/contractor decisions

57
Q

What are E series agreements?

A

Exhibitis

58
Q

What are some important E series agreements?

A

E203 - bim and digital data exhibit
E204 - Sustainable projects exhibit

59
Q

What are G series agreements?

A

AIA G701 - change order (owner, arch, contractor sign)
AIA G702 - application and certificate for payment (contractor applies, arch signs)
AIA G704 - certificate of substantial completion
AIA G711 - punchlist document

60
Q

AIA A101 - Article 9 Contract Documents

A

includes all relevant drawings, specifications, addenda, and supplementary documents

61
Q

AIA A101

A

O-C

62
Q

AIA A133

A

O-CMc

63
Q

AIA A195

A

O-C IPD

64
Q

AIA A201

A

Gen conditions for the contract of construction

65
Q

AIA A295

A

Gen conditions for contract of construction IPD

66
Q

AIA A701

A

Instructions to bidders

67
Q

AIA 305

A

Contractor’s qualification statement

68
Q

B101

A

O-A

69
Q

B102

A

O-A w/out predefined scope

70
Q

B103

A

O-A complex projects

71
Q

B104

A

O-A mid sized projects

72
Q

B105

A

O-A standard short form (res or small comercial)

73
Q

B106

A

O-A pro bono services

74
Q

B121

A

O-A services provided under multiple services orders

75
Q

B195

A

O-A IPD

76
Q

B214

A

LEED certification

77
Q

G701

A

Change order

78
Q

G702

A

application and certificate for payment

79
Q

G704

A

Certificate of substantial completion

80
Q

G711

A

punchlist document