Contracts Flashcards
1
Q
What happens after punchlist is completed per A201?
A
final certificate for payment is issued
2
Q
who issues certificate of occupancy?
A
AHJ
3
Q
which delivery method allows a shared savings clause
A
cost plus and GMP. incentive for contractor to utilize savings.
4
Q
G701
A
change orders
5
Q
G702/3
A
application for payment. breaks the contract sum into portions of the work in accordance with the schedule of values.
6
Q
A305
A
Contractors qualification statement