Contracts Flashcards

1
Q

Direct Damages

A

Money lost directly because of a delay or problem - like the cost of paying to fix a wall that falls or the cost of additional time to complete a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Consequential Damages

A

Indirect consequence of a delay or problem - like the loss of revenue on a rentable space or the loss of fee that an architect could have got if they were able to work on another project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A101

A

Owner-Contractor (design-bid-build)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A 133

A

Owner-Construction Manager, Contractor (Cost of work plus fixed fee)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A 195

A

Owner-Contractor, Integrated Project Delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A 201

A

General Conditions for the Contract of Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A 295

A

IPD, General conditions of the contract of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A 701

A

Instructions to Bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A 305

A

Contractor’s Qualification Statemenr

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

B 101

A

Owner-Architect agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

B 102

A

Owner-Architect, without a pre-defines scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

B 103

A

Owner-Architect, complex projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

B 104

A

Owner-Architect, mid-size projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

B 105

A

Owner-Architect, standard short form (residential or small commercial)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

B 106

A

Owner-Architect, pro-Bono services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

B 121

A

Owner-Architect, for services provided under multiple service orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

B 195

A

Owner-Architect, IPD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

B 214

A

Standard form of Architect’s Services: LEED Certification

19
Q

C 101

A

Joint Revenue Agreement for Professional Services

20
Q

C 103

A

Standard Form of Agreement between Owner and Consultant, without a predefined scope of consultant services

21
Q

C 191

A

Standard Form of the Multi-Party Agreement for IPD Projects

22
Q

C 132

A

Owner and Construction Manager as Advisor

23
Q

C 195

A

Standard Form of the Single Purpose Entity Agreement for IPD Projects

24
Q

D 200

A

Project Checklist, to serve as a record of Owner/Architect/Contractor decisions

25
E 203
BIM and Digital Data Exhibit
26
E 204
Sustainable Projects Exhibit
27
G 701
Change Order (Owner, Architect, and Contractor sign)
28
G 702
Application and Certificate for Payment (contractor applies, architect signs)
29
G 704
Certificate of Substantial Completion
30
G 711
Punchlist Document
31
Cost of Work
Construction cost, including contractor profit Does NOT include design fee, cost of land, contingencies
32
Supplemental Services
- services beyond the Basic Services - should be agreed upon before completion by the architect - could include: site programming, BIM Management, detailed cost estimates, as-built drawings, interior design, landscape design, etc
33
Additional Services
Services added after the contract is signed for work that is not covered initially under the Basic or Supplemental services OR to supplement changes to the project schedule of budget. Examples: if other parties mess up like owner of owner’s consultants, substantial claims, public meetings, etc
34
Insurance required under B101:
- General Liability - automobile liability - worker’s compensation insurance - Employer’s liability insurance - Professional liability insurance (errors & omissions)
35
Contract Documents include / don’t include:
- owner-contractor agreement - general conditions of the contract - drawings - specifications - addenda issued prior to the execution of the contract - modifications issued after the contract is signed (such as: change orders, change directives, minor changes in the Work issued by the architect) Not included: - anything related to bidding process - shop drawings - product data - product samples/submittals
36
Under what circumstance can the contractor request financial info from owner after work starts?
1. Owner misses payments that were required by the contract 2. If contractor is legitimately concerned about owners ability to make payments 3. A change in work that significantly affects contract sum
37
C141
Contract between A/E entity and Owner for bridging design-build
38
Certificate of Payment
Certifies that, to the best of that Architect’s knowledge, the Work has progressed to the point indicated by the Contractor, in accordance with the Construction Documents.
39
Substantial Completion
Project fit for its intended use and purpose. Architect certifies when the work has reached this milestone. Next step is punch list.
40
Schedule of Values
Allocated the Contract Sum among the various portions of the work
41
When is retainage awarded?
substantial completion
42
Final Payment
The entire unpaid balance owed to the Contractor. Must be paid within 30 days of the Architect’s issuance of the final Certificate for Paymen
43
Contract Time (A201)
Start date (or other established start date) to SUBSTANTIAL COMPLETION
44
“Day” means
All calendar days unless otherwise specified (yes, weekends count)