Contract Practice Flashcards
What is included within the contract documents for a project?
- Building Contract, Articles of Agreement
- Schedule of Amendments
- Design / Drawings
- Employer’s Requirements / Contractor’s Proposals (if relevant – D&B/CDP)
- Contract Sum Analysis
Who are the key parties involved in construction contracts?
Employer
Contractor
Contract Administrator (Standard Building Contract)
- Expected to maintain impartiality whilst administering
- Contractor must comply with their instructions
Employer’s Agent (Design and Build Contract)
- Contractor must comply with their instructions
Quantity Surveyor
- SBC: Party to the contract
- DB: Not party to the contract but expected to maintain impartiality if involved in administering/
What is the role of the QS in construction contracts?
- Value variations
- Ascertain loss and/or expense
- Carry out interim valuations
- Prepare the final account
What is the Contractor’s obligations in construction contracts?
The contractors obligations are identified in clause 2.2 of the JCT SBC and clause 2.1 of the JCT DB contract.
- Complete and carry out the works in a proper and workmanlike manner
- All materials and goods are of the standard described in the specification / Employer’s Requirements.
- Give all notices required by the Statutory Requirements and comply.
What is the clients obligations in construction contracts?
- Payment of the contractor on time
- Do not disturb the contractor from working with reasonable skill and care.
What are the five key elements for contract formation?
- Offer
- Acceptance
- Consideration
- Capacity & Competence
- Intention to Create Legal Relations
How are construction contracts executed and what are the main differences?
- A contract can be executed as a deed or under hand.
- The principle difference is the party’s liability period for breach of contract.
- 12 years if executed as a deed, 6 years if executed under hand.
What is a standard form of contract?
- Set of formal, pre-determined arrangements and mechanisms that form the basis of agreement between parties.
What are the typical amendments made to standard forms of contract?
- Transfer risk to the contractor by reducing the list of relevant events / matters
- Final date for payment due to contractor lengthened, from 14 to 28.
- Rectification Period extended from 6 months to 12 months
What are the types of contract under traditional procurement?
- Lump sum contract, where contractors agree to execute the work for a fixed total sum of money.
- Re-measurement contract, Where the contract sum is not finalised until after completion but is assessed on re-measurement to a previously agreed basis.
- Cost Reimbursement Contract, Where the sum is arrived at on the basis of prime costs of labour, plant and materials to which there is an added amount of OHP.
What are the types of contract under design & build procurement?
- Turnkey Contract, Where the Client settles on a complete package (ready to move in) to a specification of a commercial firm.
- Design & build contract, Employer’s requirements will be written stating the Contractor’s design obligations for the whole of the works.
What is the difference between JCT and NEC contracts?
- NEC references compensation events as events which may entitle a Contractor to claim both additional time and additional costs, whereas JCT differentiates Relevant Events and Relevant Matters.
- JCT contains provisional sums whilst the NEC does not.
- The activity schedule is a key contractual document of the NEC and is to be updated regularly.
When is the JCT SBC used and who is responsible for administrating the contract?
- Designed for use when traditional procurement route has been chosen.
- CA and QS administer the performance of the contractual obligations.
What are the types of contract under the SBC?
Standard Building Contract with Quantities
- Fixed price lump sum contracts with monthly interim payments.
Standard Building Contract without Quantities
- Contract Sum Analysis completed by Contractor defines the work.
Standard Building Contract with Approximate Quantities
- Re-measurement contracts are used in situations where the design/type of works can be described in reasonable detail but the amount cannot be given
What is a SBC with contractors design portion?
- Option that allows the employer to require the contractor to design discrete parts of the works but not whole majority (otherwise DB might be more appropriate).
When is the JCT Minor Works contract used and who is responsible for administrating the contract?
- Designed for use when traditional procurement route has been chosen.
- Used on smaller, lower value, more basic, shorter programme construction projects.
- Architect/CA and QS administer the performance of the contractual obligations.
What are the types of contract under the the Minor Works Contract?
Minor Works Building Contract
- Fixed price lump sum contract with interim monthly payments
- Employer must provide a pricing document, drawings and specifications to specify the quantity and quality of work
Minor Works Building Contract with Contractor’s Design
- Employer must detail the requirements for the parts of work that contractor is responsible for designing.
When is the JCT Design & Build contract used and who is responsible for administrating the contract?
- Designed for use when design and build procurement route has been chosen.
- DB projects can vary in scale but are generally suitable where detailed provisions are needed.
- The EA administers the performance of the contractual obligations.
What are the Employer’s Requirements in a DB contract?
- Details what the employer requires from the completed project and the required level of design responsibility from the contractor.
- Scale of design work can vary: contractor may be required to complete the design produced by a design team or they might be required to carry out all of it.
What are the Contractor’s Proposals in a DB contract?
- Design prepared in response to employer’s requirements.
- Set out their proposals for designing and constructing the project, along with their price.
What is Novation?
- Parties may agree that the design team initially engaged by the employer should be transferred from the employer to contractor to complete the design
- DB contract will require amendments as the standard contract does not provide provisions for novation.
What are the key differences between standard building contracts and DB contracts?
- Full design at tender stage with a SBC, whereas a DB could range from simple set of ER’s to full design.
- Client retains control over design in SBC so quality is perceived to be higher.
- CA in a SBC and EA in DB.
What are the Recitals under JCT contract suites?
- Recitals contextualise the agreement, giving factual explanations for the basis of the contract.
- The Recitals include:
What are the Articles under JCT contract suites?
- The Articles set out what is agreed between the parties.
- The Articles include: