Contract Administration Flashcards

1
Q

What is your understanding of latent defects and what
contractual issues are associated with them?

A
  • Latent defects are defects which only come to fruition some time after building completion and may take many years to become
    identifiable.
  • A claim in contract can only be brought about within the limitation period of the contract, 6 or 12 years depending on whether the contract was executed as a deed or underhand.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the contractor deemed to have allowed on the
inclusion of a defined provisional sum?

A
  • They are deemed to have made proper allowances for carrying out the work in their programme and preliminaries.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the contractor deemed to have allowed for with undefined provisional sums?

A
  • Expenditure of the undefined provisional sum may carry additional costs for programme or preliminaries as a result of carrying out the works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How are provisional sums dealt with in the final account?

A
  • The provisional sums included in the contract are deducted and the actual amount substituted.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does NEC stand for?

A
  • New Engineering Contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main parts of the JCT contracts?

A

 Recitals.
 Articles.
 Contract Particulars.
 Attestation.
 Conditions divided into 9 sections
 Schedules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a bespoke contract?

A
  • Contract conditions that are drafted specifically for a particular project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What the advantages of standard forms of contract?

A
  • They are written by legal experts.
  • Parties should be familiar with the provisions in the form providing greater consistency.
  • Rights and obligations of each party are clearly set out
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What the disadvantages of standard forms of contract?

A
  • They may not be appropriate to the needs of a particular project or client.
  • Using an inappropriate standard form for the project will cancel out any advantages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When would use a bespoke contract rather than a standard form?

A
  • They should generally be used for major projects with novel obligations.
  • When specialist advisors can undertake the amendments as this requires great skill and knowledge.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the types of dispute resolution in JCT contracts?

A

Negotiation: Parties engage in informal discussions and negotiations to reach a mutual resolution without involving a third party.

Mediation: A neutral third party, called a mediator, helps facilitate discussions and assists the parties in finding a mutually agreeable solution.

Adjudication: A statutory process that provides a quick and interim resolution to disputes. An adjudicator, usually an industry expert, makes a binding decision on the dispute.

Arbitration: A formal process where an independent arbitrator or panel hears the dispute and issues a binding and enforceable decision known as an award.

Litigation: If all other methods fail, parties can take the dispute to court, where a judge or jury issues a judgment. Litigation is a formal and public process, often more time-consuming and expensive than alternative methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly