Contract practice Flashcards

1
Q

What is a contract?

A
  • A contract is a legally binding promise (written or oral) by one party to fulfil an obligation to another party in return for consideration
  • A basic binding contract should comprise four key elements: offer, acceptance, consideration and intent to create legal relations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Please define ‘express terms’?

A
  • Express terms are the terms of the agreement which are expressly agreed between the parties
  • Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Please define ‘implied terms’?

A

A contractual term that has not been expressly agreed between the parties but has been implied into the contract either by common law or by statute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is tort?

A
  • A tort is a civil wrong
  • Part of the civil law
  • A claim in tort is concerned with loss or harm
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do statutory provisions and contract provisions differ?

A
  • Statutory provisions are set out by law & must be complied with regardless.
  • Contract provisions relate to the contract in question & therefore only apply to a specific project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is your opinion of oral contracts?

A
  • Whilst they are legally binding, the difficulty lies in proving the specific terms and conditions of the agreement.
  • Having a written contract is always the preferred opinion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a breach of contract?

A

A breach of contract occurs when one party in a binding agreement fails to deliver according to the terms of the agreement. A breach of contract can happen in both a written and an oral contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the Local Democracy, Economic Development and Construction Act 2009?

A
  • October 2011 - the Local Democracy, Economic Development and Construction Act 2009 (the 2009 Act) came into force in England and Wales
  • The Act amended the House Grands Construction and Regeneration Act 1996 (the Construction Act)
  • The Act changed the way construction contracts are entered into and in particular, introduced an amended regime for payment and adjudication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the key provisions under the Act?

A

Contracts
- The LDEDC Act repeals the requirement for construction contracts to be in writing therefore, contracts that are partly in writing or wholly oral are now covered. This will allow parties to go to adjudication, even if their involvement is not formally recognised in writing

Payment

  • Under the HGCR Act a construction contract must have an ‘adequate mechanism’ for determining what payments are due and when they become payable
  • Pay when certified clauses can no longer be used to prevent paying a subcontractor on the basis that a certificate in the main contract is yet to be issued

Payment notices: contractual requirements

  • The construction contract must specify that either the payer or payee (but not both) will issue the payment notice
  • This must be issued not later than 5 days after the payment due date and paid before the final date for payment identified by the construction contract (the parties being free to agree how long the period is between the date the sum becomes due and the final date for payment
  • The payment notice must specify the sum the payer/payee considers to be due at the payment due date and the basis on which that sum was calculated. A payment notice must be issued, even if the amount of the payment notice is nil.

Payment notices: payee’s notice in default of payer’s notice

  • The the payer is required by contract to issue a payment notice and fails to serve that notice in the required form or in the set timeframe, the payee is entitled to issue a default payment notice.
  • A default payment notice obliges the payer to pay the amount due and allows the payee their statutory right to suspend performance for non-payment

Payless notice

  • Paying parties are required to either pay the notified sum specified in either the payment notice or default payment notice, by the final date for payment or serve an effective pay less notice. This allows the payer to amend the sum due if it is later discovered the work covered, or the amount notified within the payment notice turns out to be unsound
  • To be effective a pay less notice must specify the sum that the paying party considers to be due on the date the notice is served, the basis on which that sum is calculated and be served no later that the prescribed period prior to the final date for payment

Suspension of performance for non-payment

  • The LDEDC Act clarifies the contractor’s right to suspend carrying out the work in the event of non-payment
  • to validly suspend performance of its obligations by reason of non-payment, a default payment notice must be issued and there must have been failure to pay. The party in default (the party who has not paid) is liable to pay the payee (contractor stopping work) a reasonable amount by way of costs and expenses incurred by exercising the suspension of all or part of the work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a letter of intent?

A
  • Typically used to describe a letter from an employer to a contractor (or from a main contractor to a subcontractor) indicating the employer’s intention to enter into a formal written contract for works described
  • The letter of intent typically asks the contractor to begin those works before the formal contract is executed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What information is typically included in a letter of intent?

A
  • Detailed description of the work to be completed
  • Contract sum (if agreed)
  • Date for possession
  • Date for completion
  • Insurance provisions required
  • Method of payment
  • Expiry date of letter
  • Typically states employers’ right not to award the main contract for whatever reason.
  • ADR method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of a letter of intent?

A

Allows work to commence before the main contract is agreed/signed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages?

A
  • May lead to complacency and disincentivise both parties from signing the main contract
  • Contractually less robust than the main contract
  • The employer loses incentive in negotiations of the main contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In what circumstances might a letter of intent be used?

A
  • Where the employer needs to commence works before a certain date
  • Where materials have long lead in times and early procurement would aid the programme
  • Starting construction works might trigger early founding
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who issues the letter of intent?

A

The employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who signs it?

A

Both the employer and the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What would you say if the client asked you to draft a letter of intent?

A

It is a legally binding agreement like a contract; therefore, we would NOT draft those

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the different types of letters of intent?

A

Comfort letter
A comfort letter is a letter expressing a party’s intention to act in a particular way at some point in the future, or at the time of issuing the letter

Instruction to proceed with consent to spend
A letter with instructions to proceed and consent to spend is sometimes referred as an “if” contract. This type of letter allows work to proceed up to a certain value while the contract itself is being finalised

Recognition of contract
This type of letter is also referred to as a letter of acceptance and is used by some forms of contract (such as FIDIC) to formally execute the contract itself. Generally, such a letter will be issued on once the contract has been substantially agreed and usually marks the completion of negotiations between the parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Are you aware of any case law relating to letters of intent?

A

Ampleforth Abbey Trust v Turner and Townsend

The defendant project managers were retained by the Trust in relation to a project to build new accommodation at a school. The defendant’s retainer included obligations ‘facilitating, assisting and being involved in the procurement of the building contractor and the building contract’. The contractor never signed the building contract and the whole of the works (which were completed late) were procured using letters of intent. The effect of this was that the Trust was not able to claim liquidated damages under the building contract for the later completion of the works.
HHJ Keyser QC help that the defendant had been negligent in failing to take the steps reasonably required of a competent project manager for the purpose of finalising the building contract between the Trust and the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is a parent company guarantee?

A

A parent company guarantee (PCG) is a form of security that may be required by clients to protect them in the even of default on a contract by a contractor that is controlled by a parent company (or holding company). Typically, such a default might be caused by the insolvency of the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

In what circumstance may a PCG be required?

A

Parent company guarantees can be particularly useful where a small contractor is part of a large financially stable group of companies. The guarantee is given by the parent company to the client and in the event the contractor defaults on their obligations, the parent company is required to remedy the breach, meeting all the contractor’s obligations under the contract (and / or covering loss and expense incurred by the client)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Are there any Acts which govern third party rights?

A

Contract (Rights of Third Parties) Act 1999

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the overarching purpose of the Act?

A
  • The Act allows third parties to enforce terms of contracts that they are not a party to, but which benefit them in some way, or which the contract allows them to enforce
  • It also gives parties access to various remedies if those contract terms are breached
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the advantages of third-party rights?

A

Time and cost
Since no separate document (i.e. a collateral warranty) is being entered into, using the Act cuts down on the time and cost associated with warranties being drawn up, signed and circulated

Certainty Once the rights to be conferred on third parties are negotiated and agreed by all parties, there is limited room to revisit the working when protection is required as is often the case when new collateral warranties are circulated for signature

Subcontractors
The third-party rights process can also be extended in subcontracts, so that (provided the relevant building contract and subcontract are drafted accordingly) an employer can confer third party rights in relation to work done by subcontractors unilaterally. This avoids the need to chase large numbers of individual warranties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the disadvantages of third-party rights?

A

Lack of flexibility
Once the schedule of third-party rights being conferred has been agreed, there is limited room for negotiation. While this can be an advantages as it will help to keep costs down, in some circumstances the inflexibility could cause a problem if a specific provision is required for a particular party, such as an incoming tenant or purchaser.

Need for careful drafting
Recent cases have been shown the importance of drafting provisions relating to the enforcement of third-party rights very clearly to ensure that all the necessary rights are conferred on the third party, for example the right to commence adjudication proceedings if this is required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Why might third-party rights be used instead of collateral warranties?

A
  • If a lot of collateral warranties are required, it can involve a lot of administration and cost
  • Third-party rights are easier to get in place because there is no separate document required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is a collateral warranty?

A

A collateral warranty is a formal contractual agreement which runs alongside another contractual agreement - its purpose is to create a contractual relationship between two parties (e.g. companies; individuals) where one would not otherwise exist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Can you provide a working example of of how a collateral warranty could be used?

A

The employer places a contract with a contractor, the contractor then places several subcontracts with its suppliers to actually do the works, the employer has a direct contractual relationship with the contractor, but he has not contractual relationship with any of the subcontractors (this is known as ‘privity of contract’)

In these circumstances the employer may wish to have a direct contractual relationship with the subcontractor so that is can enforce the obligations that the subcontract owes directly, or to create other obligations and rights between them. This might be considered as a security measure if the contractor should become insolvent or if its employment were to be terminated for any reason.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Who might want a collateral warranty?

A
  • Any third party with a financial or inherent interest in the project but is not party to the main contract. e.g. funding institution, future tenants, purchasers
  • The employer may want a collateral warranty with key subcontractors or suppliers, if the contractor were to go into liquidation, otherwise they would have no contractual link with them for redress in case of defective workmanship
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is the difference between a bond and collateral warranty?

A
  • A bond is usually a financial commitment backed up by a third party, a collateral warranty passes on contractual obligations
  • Bonds are contained within the contract
  • Collateral warranties are a side agreement to the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Are there any alternatives to collateral warranties?

A

An alternative method to confer such rights is provided by the Contracts (Rights of Third Parties) Act 1999 which allows third parties to obtain the benefits from contracts, which are entered into by others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are the three ways that benefits can be transferred under a building contract?

A
  • Collateral warranties
  • Third party rights
  • Assignment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

There is a high probability that collateral warranties will be needed under a D&B contract, can you explain why?

A

The design team typically sit below the contractor under D&B contract; therefore, the employer will need to retain a contractual link with the design team (using a collateral warranty)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Are you aware of any case law relating to collateral warranties?

A

Parkwood Leisure v Laing O’Rourke

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What happened in the case of ‘Parkwood Leisure v Laing O’Rourke’?

A

In light of the particular wording used in the collateral warranty, there was no doubt that is should be treated as a construction contract under section 104 of the Housing Grants, Construction and Regeneration Act 1996

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is assignment?

A

Assignment is the process whereby the benefit of a contract is transferred from one party to another, but the burden of the contract remains with with the original party to the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Can you provide a working example to explain how assignment might be applied?

A
  • Assignment can arise where a party to a construction contract, collateral warranty or consultant’s appointment wants to assign the benefit under that contract to a third party, such as a purchaser or tenant of a building.
  • Banks and other funders will also frequently take an assignment of the benefit of a suite of construction documents in respect of a development, as an additional part of the security package for their loan to finance the development. A bank will want to acquire the benefits of such documents to be able to assume the position of the employer under them in the event of the employer defaulting on its financial obligations during the works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What are some of the typical clauses of assignment?

A
  • It is standard to allow assignment of rights twice without consent
  • The assignment should be notified in writing to the other party
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What is a bond?

A
  • Construction bonds are protection for the owner against non-payment, lack of performance, company default and warranty issues.
  • An arrangement where a contractual duty owed by one party to another is backed up by a third party
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Can you list 5 different bonds which might be used on a project?

A
  • Performance bond
  • Retention bond
  • Off-site materials bond
  • Advance payment bond
  • Tender bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What is a performance bond?

A
  • A Performance Bond is a form of security provided by a contractor to a developer of employer
  • It consists of an undertaking by a bank or insurance company to make a payment to the employer in circumstances where the contractor has defaulted under the contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

When might the employer want a performance bond?

A
  • If the contractor is new or unapproved
  • If there is concern over the contractor’s finances/commercial standing
  • The economy might be heading into recession
  • The employer simply wants to protect their commercial exposure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What is the difference between on-demand and conditional performance bond?

A

On-demand bonds - Money set out in the bond is immediately available on demand without needing to satisfy any preconditions whatsoever (including establishing the contractor’s liability) unless the demand is fraudulent

Conditional bonds - Requires the employer to provide evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss consequently

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What is the typical value of a performance bond?

A

Usually 10% of the contract sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What is the typical cost of a performance bond?

A

The cost largely depends on the financial stability of the contractor and the number of previous claims (if any).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What is the risk of not having a performance bond?

A
  • In the event a contractor goes into insolvency and there is no bond in place, the employer will be liable to pay all costs to deal with the insolvency
  • Costs include sourcing a new contractor to complete the works and any premium that will attract
  • The employer will not be able to pursue the contractor as the company will be in the process of liquidation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Are there any alternatives to a performance bond?

A
  • If the contractor is part of a group of companies, then the employer may wish to consider a Parent Company Guarantee (PCG)
  • If the smaller common breaches the contract, the parent company is obligated to step in and remedy the breach
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

What is a tender bond?

A
  • Requested by the employer when inviting contractors to tender for a contract
  • A tender bond provides security against the risk of the successful bidder failing to enter the contract
  • It should help to prevent idle tendering
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

What is an off-site materials bond?

A

Covers an employer against the risk of paying the contractor for materials being manufactured off-site. If the contractor or subcontractor becomes insolvent, the employer can claim on the bond for goods paid for (in the event they are not delivered to site)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What is a retention bond?

A
  • Typically, an employer could hold up to 5% of the contract value for a period of up to 12 months. The main contractor or subcontractor then must wait for the funds to be returned at the end of the making good defect period, this can affect business cash-flow
  • A retention bond will provide the employer with the same level of comfort as the retention, but the contractor / subcontractor has the real benefit of retaining the cash in their account
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What are the disadvantages of a retention bond?

A
  • The employer will ultimately have to pay the premium for taking out the bond (usually through the contract sum)
  • May reduce the contractor’s incentive to complete the works promptly and to the desired standard
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Why might a retention bond be used?

A
  • An advances payment bond is required to protect and support payments to contractors by the employer in advance of works being done.
  • Some contracts require the purchase of materials in advance of a contract commencing, there is always a risk to the employer in advancing money to a contractor who may not be well known to them to allow the purchase of goods to enable the contract to commence
  • an advanced payment bond protects the payment being advanced in exchange for a bond underpinned by a suitable guarantor to give peach of mind to both parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What are antiquities?

A

Items as:

  • Historical artefacts, pottery and coins
  • Bones or fossils
  • Something of historical interest of value
  • Archaeology
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What should the contractor do if they discover such objects?

A
  • Use best endeavours to avoid disturbing
  • Cease work if it would endanger the object
  • Take necessary measures to preserve in existing location and condition
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

When objects of interest are discovered, who is liable for the delay and expense incurred?

A
  • Usually the employer

- Significant delays and costs can arise - can be a serious event for the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

What are defects?

A
  • Broadly defined as a defect in workmanship, design, materials, or systems used. The result is a failure of the building project or structure that causes damages to people or property. This, in turn, leads to financial losses or harm to the owner

The NEC contract defines a defect as:

  • A part of the works which is not in accordance with the works information or,
  • A part of the works designed by the contractor which is not in accordance with the applicable law or the contractor’s design which the project manager has accepted.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What are patent defects?

A
  • Patent defects are those which can be discovered by reasonable inspection
  • Patent defects would include wall cracks, sagging gutters, broken windows, missing tiles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

What are latent defects?

A

Latent defects are those which cannot be discovered by reasonable inspection, for example problems with foundations which may not become apparent for several years after completion when settlement causes cracking in the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Why is the defect rectification period typically 12 months?

A

12 months will allow the building to go through all seasons of the year; therefore, most defects (with exception to latent defects) will become apparent within this period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

What is novation?

A
  • Under a design & build contract, novation normally refers to the process by which design consultants are initially contracted to the client, but are then ‘novated’ to the contractor
  • The contractor will then go on to manage the remaining design process with the existing design team, rather than bring their own consultants onboard
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Are novation agreements required under traditionally procured projects?

A

Not usually, this is because the designers are typically retained by the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

What are some of the advantages of novation?

A
  • Reduced learning curve - working with the client at an early stage, the design team can gain a strong understanding of the project requirements. If the design team are not novated, this learning is potentially lost and parts of the process will ned to be replicated with a new design team
  • Reduced contractual risk for the employer - the process of novation and the transfer of responsibility to the contractor means the employer assumes minimum risk contractually
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What are some of the disadvantages of novation?

A
  • Following novation of consultants, the employer will generally require collateral warranties.
  • The client may need to employ a shadow team for compliance purposes
  • There is potential for conflict of interest, particularly in relation to services that remain to be performed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

What is retention?

A

A percentage of the sums certified for payment under the construction contract (typically 3-5%) is held by the employer during the construction phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

What is the purpose of retention?

A

It is used as an assurance of project completion and is intended as a safeguard against subsequent defects that the contractor may fail to remedy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

What can the employer use retention monies for?

A
  • If the contractor does not return to correct the defects, then the retention held may be used to fund the payment of others to correct the defects
  • The project manager / contract administrator will need to check the contract on the ability to do this and the relevant notices that should be given to the contractor prior to appointing others to undertake the works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

How is retention released to the contractor?

A

Typically, retention monies are released in 2 stages:

  • At the time of issuing the completion/practical completion certificate, the first half of retention monies will be certified and released
  • The second half of retention monies will be certified and released upon the expiry of the defect period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Who typically benefits from interest accruing on the retention money?

A

Usually, the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Are there any alternatives to holding retention?

A

It is possible to procure a retention bond to cover retention that would otherwise have been deducted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

What is professional negligence?

A

Professional negligence is when a professional fails to perform their responsibilities to the required standard or breaches a duty of care. This poor conduct subsequently results in a financial loss, physical damage or injury of their client or customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

How can the employer / client recover a loss if the consultant or contractor is professionally negligent?

A

Make a claim on their professional indemnity insurance (PII)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

What is product liability insurance?

A
  • Manufacturers and/or suppliers of products incorporated in construction works are at risk of claims being made against them for damages if defects in those products result in damage or injury.
  • Product liability insurance protects the policy holder against liability resulting from these defects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

What is public liability insurance?

A
  • Public liability insurance protects against liabilities for injury to third parties (non-employees) or their property
  • For example, a member of the public could make a claim if a fallen brick damaged their car, or if a supplier trips over an unsecured cable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

What is employer liability insurance?

A

Employers’ liability insurance can pay the compensation amount and legal costs if an employee claims compensation for a work related illness or injury

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

What is Contractor Designed Portion (CDP)?

A

Typically used on traditionally procured projects, design responsibility for specific elements of the building is transferred to the contractor

76
Q

What is the difference between traditional procurement with CDP and design & build?

A
  • Traditional procurement with CDP - the design responsibility lies with the employer except for certain elements that are transferred under CDP
  • Design & build - all responsibility for the design rests with the contractor
77
Q

How are CDP elements executed?

A

A performance specification is provided at tender stage which the contractor provides the design proposals in response. These proposals are then reviewed by the design team and either accepted, commented upon or rejected

78
Q

Can you list typical CDP elements which the employer may wish to transfer?

A
  • Steelwork connections
  • Cladding
  • Roofing
  • Temporary works
  • MEP elements
79
Q

What are domestic subcontractors?

A
  • Domestic subcontractors are chosen by the contractor to execute a package of works
  • The employer’s consultants (e.g. architect, PM, QS) not the employer themselves influence the appointment or the conditions
80
Q

What are named subcontractors?

A
  • The employer provides a list of named subcontractors which are pre-approved
  • The contractor selects one from the list through the tendering process
  • Once appointed by the contractor, they then become a domestic subcontractor
81
Q

What are the advantages of naming subcontractors?

A

Naming a subcontractor provides the employer with more control to the selection of a subcontractor by the contractor, while still leaving them with the element of choice and the responsibility of monitoring their performance

82
Q

What are nominated subcontractors?

A
  • A nominated subcontractor is selected by the employer to carry out an element of the works (still employed by the contractor
  • Nominated subcontractors are usually imposed upon the contractor
83
Q

What are the disadvantages of nominated subcontractors?

A
  • As the subcontractor is being imposed on the contractor, the contractor will generally be allowed the right to object under certain conditions (safety reasons for example)
  • The contractor and subcontractor may have conflicting procedures, ethics, attitudes
84
Q

What are the advantages of nominated subcontractors?

A

On the basis the employer has nominated them in the first instance, their work should be of high quality and acceptable to the employer

85
Q

What is insolvency?

A

Insolvency is concerned with the inability to pay debts

86
Q

What can be done at tender stage to identify potential contractor insolvency?

A
  • Through check financial accounts for stability
  • Check for front loading of the tender submission
  • Bank references
  • Use credit checking agencies (Dun and Bradstreet report)
  • Previous references (from consultants and employers)
  • Request a bond and / or parent company guarantee - this will not prevent insolvency but will give the employer comfort in the event of default
87
Q

What is termination?

A

When a contract is terminated, the parties to the contract are no longer obliged to perform their obligations under the contract

88
Q

Can the contractor suspend works for non-payment?

A
  • If the notified sum is not paid by the final date for payment, the Construction Act 2009 puts the payee in a stronger position than before. It can now suspend performance of any or all its obligations, not just the work
  • The contractor can stop insuring the works, postpone applying for a necessary consent or refuse to implement a variation instruction
  • The payee will be entitled to a “reasonable amount” for its re-mobilisation costs, as well as an extension of time
89
Q

What are delay damages / LDs?

A

A genuine pre-estimate of loss suffered by the employer because of late completion of the works.
The damages are inserted into the contract prior to signing by the contracting parties

Key points

  • LDs should not be a penalty
  • Quick remedy to avoid having to prove actual loss due to the breach
  • The contractor knows their liability
  • The employer should the calculate the figure (consultants should not do this on their behalf)
90
Q

What sort of expenses/costs can an employer include in the damage calculation?

A
  • Loss or rent or other income
  • Additional professional fees
  • Expected costs incurred by other parties
  • Cost of not having facility (storage, rent, abortive costs)
  • Capital salaries
  • Associated legal costs

The figure should not be construed as a penalty; thus the employer needs to be realistic when identifying potential costs

91
Q

What if your client tells you the damages are £100,000 per week?

A
  • Exercise due diligence - check they do believe £100,000 per week is genuine pre-estimate of likely loss
  • If there is a concern - explain the dangers that the damages might be construed to be a penalty (they may not be enforceable)
92
Q

Under a JCT contract, what contractual documents must be in place before damages can be deducted?

A
  • A non-completion notice/certificate is in place
  • The contractor is notified that the employer may require the payment of; or may withhold or deduct LDs
  • A payless notice is served
93
Q

What is a LD holiday or LD free period?

A
  • This is essentially just a grace period during which the contractor has no commercial liability for delay
  • For example, if the contractor has a two-week LADs holiday, LADs will only begin accruing after the delay has continued for two weeks
94
Q

What is the implication of inserting ‘nil’ or £0 in the section against the damage clause?

A

The consequence of this can be that the contractor’s liability for damages for delay is zero

95
Q

What is the difference between liquidated and unliquidated damages?

A
  • Contracting parties might agree to pay a certain amount on breach on contract. When such provisions are created in the contract, they are known as liquidated damage
  • Unliquidated damages are granted by the courts based on an assessment of the loss or injury caused to the party suffering such breach of contract
96
Q

If an extension of time is issued, what affect would this have on delay damages?

A

Damages cannot be deducted from the original date; damages are levied from the revised practical completion / completion date

97
Q

What is a pre-construction services agreement (PCSA)?

A
  • A contract between the employer and contractor for pre-construction services
  • The PCSA documents the services that the contractor is to perform before signing the building contract and identifies the terms and conditions under which these services are to be performed
98
Q

When might a PCSA be used?

A

In a two-stage tender approach to facilitate early contractor involvement

99
Q

How can a PCSA benefit a project?

A

Early involvement of the contractor should improve the buildability and cost-certainty of the design as well as creating a better integrated project team and reducing the likelihood of disputes

100
Q

What sort of activities can a PCSA be used for?

A
  • Contribute to the design process
  • Advise on buildability, sequencing and construction risk
  • Advise on the selection of specialist subcontractors
  • Help develop the method of construction
  • Prepare a site layout plan for the construction stage
  • Assist with any planning application matters or other approvals
101
Q

What should be considered when drafting a PCSA?

A
  • Arrangements do not commit the employer to enter into the building contract. It is important that the employer have means of securing an alternative bid if second-stage negotiations fail
  • The scope of service for the contractor is clearly defined and unambiguous
  • Usual programme and delay damage clauses are carefully drafted by the legal team
102
Q

What are the main forms of building contract?

A
  • JCT (Joint Contracts Tribunal)
  • NEC (New Engineering Contract)
  • FIDIC (International Federation of Consulting Engineers)
  • Bespoke contracts are also used
103
Q

What are some of the considerations when selecting the appropriate construction contract?

A
  • Nature of the client
  • Priorities - cost, time, quality and risk allocation
  • Procurement choice
  • Value of work
  • Type/nature of work
  • Public or private employer
  • Complexity of work
  • Size and location of work
104
Q

What is a bespoke contract?

A
  • Bespoke contracts are contracts that are tailored to fit the specific requirements of a project
  • Bespoke contracts are often used when standard forms are not suitable
105
Q

What are the advantages of standard forms over bespoke contracts?

A
  • Written by legal experts
  • Rights and obligations of each party are clearly set out to the required level of detail
  • Parties should be familiar with the provisions in the form - greater consistently in application and fewer unforeseen anomalies
106
Q

What are the disadvantages of bespoke contracts?

A
  • Familiarity is decreased as they are rarely used
  • Expensive to draft (legal fees)
  • May be poorly drafted and lead to ambiguity
  • not familiar to the party administering the contract
  • Clauses / provisions might be untested in court
  • This type of contract could be unappealing to the contractor
107
Q

When would a bespoke contract be appropriate to use (rather than a standard form)?

A

When amending a standard contract will not do, the most efficient means of achieving a client’s requirements might be to create a bespoke contract

108
Q

Have you amended a standard contract? Can you explain exactly how you did this?

A
  • As consultants, we do not have legal training, so we do not amend the contract ourselves
  • All amendments should be drafted by the legal team
109
Q

What are some risks associated with amending a standard contract?

A
  • Amendments can spoil the delicate balance of risk allocation
  • Can create legal uncertainty
  • Can attract a cost premium to tenders
  • Amendments must be reasonable and comply with legislation
  • Courts can strike out amendments if contrary to good faith
110
Q

What does JCT stand for?

A

Joint Contracts Tribunal

111
Q

What are some of the contracts in the JCT family?

A
  • Standard Building Contract
  • Intermediate Building Contract
  • Minor Works Building Contract
  • Major Project Construction Contract
  • Design & Build Contract
  • Management Building Contract
  • Construction Management Contract
  • JCT Constructing Excellence Contract
  • Measured Term Contract
  • Prime Cost Building Contract
  • Repair & Maintenance Contract
  • Homeowner Contract
112
Q

What are key project characteristics which influence which JCT contract is used?

A
  • Size, value and type of project
  • Need for contractor design
  • Certainty on final cost
  • appetite for risk ownership and risk transfer
  • Employer experience
  • Programme requirements
113
Q

When would you use the JCT Minor Works Contract?

A

The contract is designed for smaller, basic construction projects where the work is of a simple nature. Minor Works Building Contracts are suitable for projects procured via the traditional method

114
Q

What are the key features of the JCT Minor Works Contract?

A
  • The employer is responsible for the design. The employer (through its advisers) will need to provide drawings, a specification, or work schedule to specify the quantity and quality of work at tender stage
  • If the appointed contractor is to be responsible for designing specific parts of the works, then a Minor Works Building Contract with contractor’s design must be used
  • The Minor Works Building Contract is not suitable where the project is complex enough to require bills of quantities, detailed control procedures, or provisions to govern work carried out by named specialists
  • Minor Works Building Contracts are normally administered by the architect or a contract administrator
115
Q

When would you use the JCT Intermediate Contract?

A
  • The contract is designed for construction projects involving all the recognised trades and skills of the industry, where fairly detailed contract provisions are needed, but without complex building service installations or other specialist work
  • Intermediate Building Contracts are suitable for project procured via the traditional method
116
Q

When would you use the JCT Building Standard Building Contract?

A
  • Designed for large or complex construction projects where detailed contract provisions are needed, suitable for projects procured via the traditional method
  • The employer is responsible for the design. However, Standard Building Contracts also have option provision for a ‘Contractor’s Designed Portion’ if the appointed contractor is to be responsible for the design of specific parts of the works
  • Works can be carried out in sections
117
Q

When would you use the JCT Major Project Construction Contract?

A
  • Designed for large-scale construction projects where major works are involved
  • It is used by employers who regularly procure large-scale construction work and the work is carried out by contractors with the experience and ability to take greater risk that would arise under the JCT contracts
  • Major Project Construction Contracts are suitable for projects procured via the design & build method
118
Q

What are the key features of the JCT Major Project Construction Contract?

A
  • Often in Major Projects, a ‘novation’ agreement is put in place so that the architect or designer who initially worked with the employer continues to complete the design under the responsibility of the contractor
  • The employer usually employs a representative to exercise their powers and functions under the contract
  • Project can be carried out in sections
  • The employer and contractor have their own detailed in-house procedures, so only limited procedures need to be set out in the contract conditions
  • The contractor is responsible for the design, as well as completing the works. The scale of design work to be carried out by the contractor can vary
119
Q

What would you use the JCT Design & Build Contract?

A

The JCT Design & Build Contract is designed for construction projects where the contractor carries out both the design and the construction work. Design & build projects can vary in scale, but the Design & Build Contract is generally suitable where detailed provisions are needed

120
Q

What are the key features of the JCT Design & Build Contract?

A
  • The scale of design work needed to be carried out by the contractor can vary greatly on design & build projects
  • Contractor will complete design based on a concept provided through the employer’s advisers of will be responsible for producing and completing the design right from the outset
  • The design requirements and responsibility of the contractor in design & build projects go beyond that covered in a traditional contract with a contractor’s designed portion
  • The employer normally uses an agent to administer the contract
  • Works can be carried out in sections
121
Q

When would you use the JCT Prime Cost Contract?

A
  • Design for projects that require an early start on site, often alterations or urgent repair work (such as fire damage)
  • Usually the exact nature and extent of the work is not known until the project is underway, so full design documents are not completed until work has commenced
  • Suitable for projects procured via the traditional method, using a cost reimbursement or cost plus payment structure
122
Q

When would you use the JCT Measured Term Contract?

A
  • Designed for use by employers who have regular flow of maintenance, minor works and improvements projects that they would like to be carried out by a single contractor over a specified period.
  • Measured Term Contracts are suitable for projects procured via the traditional method, using a measurement payment structure
123
Q

When would you use the JCT Construction Management Contract?

A
  • For use on construction projects where the employer appoints separate trade contracts to carry out the works and a construction manager to oversee the completion of the works for a fee
  • Construction management contracts are suitable for projects procured via the management method
124
Q

What are the key features of the JCT Construction Management Contract?

A
  • Works can be carried out in sections
  • The contract is used where separate contractual responsibility for design, management and construction of the project is desired
  • The employer provides the design and enters into direct separate trade contracts with suppliers to carry out the construction of the works
  • The construction manager is appointed by the employer to manage the project and act as an agent on the employer’s behalf. The construction manager also administers the conditions of the trade contract
125
Q

When would you use the JCT Management Building Contract?

A
  • Management Building Contracts are suitable for large, complex projects, where flexibility and an early start on site is required
  • Construction is completed under a series of separate works contracts, which the management contractor appoints and manages for a fee
  • The management contractor employs works contractors to carry out the construction and the works contractors are directly contractually accountable to the management contractor
  • Works can be completed in sections
  • the employer is responsible for the design and this is usually supplied to the management contractor by the architect or design team working on the employer’s behalf
126
Q

What are relevant events?

A
  • A relevant event is an event on or off site that causes a delay to the completion date of the works
  • For example, a relevant event could be something that happens during the design and manufacture process to delay things, or a site event that prolongs the installation works
127
Q

Can you provide examples of relevant events in the contract?

A
  • Variations and instructions
  • deferment of possession of the site
  • Suspension by the contractor for non-payment
  • The carrying out of work by statutory undertakers
  • Impediment, prevention, or default by the employer
  • Loss or damages occasioned by a Specified Peril (fire, flood)
  • Exceptionally adverse weather conditions
  • Strike or lockout
  • Civil commotion or terrorism
  • The exercise of any statutory power after the base date by the UK Government or Local or Public Authority
  • Force Majeure
128
Q

What is force majeure?

A

Force majeure events are usually defined as certain acts, events or circumstances beyond the control of the parties, for example, natural disasters or the outbreak of hostilities

129
Q

can you provide some examples of force majeure event?

A
  • War, hostilities, invasion, act of foreign enemies
  • Rebellion, revolution, insurrection, civil war
  • Contamination by radioactivity
  • Riot, commotion, strikes, go slows, locks outs or disorder
  • Acts or threats of terrorism
130
Q

What happens when a relevant event occurs?

A
  • Upon it becoming reasonably apparent that a delay will occur, the contractor notifies the contract administrator in writing, stating the particulars and extent
  • The contractor must state one of the relevant events and detail of how and why the delay is occurring or likely to occur
  • The contractor should give an estimate of delay in his notice so that the contract administrator can form his/her own opinion
  • The contract administrator responds within 12 weeks stating whether a relevant event has or has not occurred
  • If the event has occurred, the contractor administrator assesses the delay
  • A new completion date is then fixed (extension of time)
131
Q

Assuming the relevant event has occurred and is accepted by the contract administrator, is the contractor entitled to loss and expense?

A
  • Relevant events entitle the contractor to claim an extension of time only
  • The contractor will need to demonstrate a relevant matter has occurred to claim loss and expense
132
Q

What are relevant matters?

A
  • A matter for which the employer is responsible that materially effects the progress of the works
  • This may enable the contractor to claim direct loss and / or expense that has been incurred
133
Q

Can you give some examples of relevant matters?

A
  • Failure to give the contractor possession of the site
  • Failure to give the contractor access to and from the site
  • Delays in receiving instructions
  • Failure by the employer to supply goods and/or materials
  • Disruption caused by work carried out by the employer
134
Q

What is the difference between a relevant event and relevant matter?

A
  • Relevant events entitle the contractor to claim additional time
  • Relevant matters entitle the contractor to claim additional costs (loss and expanse)
135
Q

What is a loss and expense claim?

A

Loss and expense claims are often associated with delays but can be for any event where the Contractor incurs loss due to the failure of the employer (relevant matter)

136
Q

What is the key thing to remember when assessing loss and expense claims?

A
  • It should be actual loss incurred by the contractor
  • The prices in the contract bill of quantities, contract schedule of rates or preliminaries should not be used (actual costs may be more or less than these)
137
Q

Do you need an extension of time for a loss and expense claim?

A

No, loss and expense can be due without an extension of time

138
Q

What are the common heads of claim in loss and expense?

A
  • Prolongation (extra site overheads i.e. preliminaries)
  • Thickening of preliminaries (extra site supervision)
  • Disruption (causing plant and labour to be underutilised / unproductive)
  • Increase in labour and material costs during the period of delay
  • Finances charges (i.e. interest)
139
Q

What are prolongation costs?

A
  • Prolongation costs are a type of financial claim made by contractors in respect of late running projects
  • They typically include claims for the cost of time related resources such as site management, site accommodation and key items of plant and machinery
140
Q

What is partial possession?

A
  • A building contract may allow the employer to take partial possession of part of the works, before they have been formally completed
  • Partial possession often requires the agreement of the contractor but allows the employer to use part of the works for its intended purpose (prior to completion of the whole of the works)
141
Q

What are the key points of partial possession?

A
  • Not agreed in advance (prior to signing the building contract)
  • Usually, completion is deemed to have occurred for that section
  • A voluntary agreement between employer and contractor
  • Contractor must give consent
142
Q

Can the contractor refuse to give partial possession?

A
  • Partial possession can only be taken with the consent of the contractor, but that consent may no be unreasonably withheld
  • The contractor would be entitled to withhold if occupation of completed areas would hinder their ability to complete the remaining areas
143
Q

What are the typical implications of partial possession?

A
  • Half retention is released (proportionate to the area of possession)
  • The contractor’ responsibility for insuring the works (if applicable) ends.
  • The contractor’s liability for liquidated damages ends (proportionate to the area of possession)
  • The employer becomes responsible for any damages to the works
  • The defect period commences
144
Q

What is sectional completion under a JCT contract?

A
  • Sectional completion refers to a provision within the building contract which allows different completion dates to be set for different sections of the works
  • Once it is in the contract, the contractor has an obligation to achieve the sectional completion date. Liquidated damages are agreed up front should the section be delivered late
145
Q

What is the difference between sectional completion and partial possession?

A
  • Sectional completion leaves less to chance, because the parties the parties have agreed many of the practical consequences of that completion in advance
  • If something does go wrong (a delay to practical completion for example), it is easier for the contract administrator to deal with delays, changes or even acceleration with sections in place
146
Q

What are the main options for insuring the works under a JCT contract?

A
  • Option A - The contractor takes out and maintains joint names all risks insurance of the works for new buildings
  • Option B - The employer takes out and maintains the joint names all risks insurance of the works for new buildings
  • Option C - The only option referring to renovations and involving existing structures. This is where the employer takes out and maintains a joint name all risks insurance of the works and the policy also insures the existing structure and contents against ‘specified perils’
147
Q

What is contractor’s ‘all risk’ insurance?

A
  • The essence of the contractor’s ‘all risk’ cover is protection against the physical loss or damage to the works being undertaken
  • Sometimes referred to as ‘CAR insurance’
  • The policy will pay for repair or replacement of the insured works following damage caused by an insured event
148
Q

What are specified perils?

A

Specified perils tend to be significant events that would cause very significant damage to the works, including but no limited to:

  • Fire
  • Explosions
  • Earthquakes
  • Flooding
149
Q

What is subrogation?

A
  • Subrogation is a concept that allows an insurance company that has paid a loss to step into the shoes od its insured to then sue a party that may be responsible for causing the loss.

Working example

If a contractor’s crane drops a steel beam (causing damage), the owner’s builder’s risk insurer pays the loss, the owner’s insurer can step into the shoes of the owner and sue the contractor for the loss it caused

150
Q

What is a joint names insurance policy?

A
  • Policy in the names of two or more parties (i.e. contractor and employer)
  • Under a joint names policy, the insurer will have no right of subrogation against on of the insurer parties, even where an insured party has caused the loss for which the insurer has had to pay out
151
Q

What does NEC stand for?

A

New Engineering Contract

152
Q

What does ECC stand for?

A

Engineering and Construction Contract

153
Q

Please can you give me an overview of NEC ECC contract?

A
  • Suitable for any construction-based contract between an employer and a contractor
  • It is intended to be suitable for any sector of the industry, including civil, building, nuclear, oil & gas
  • There are six main options to choose from

Key points

  • No reference to the QS in the contract
  • PM assumes full authority on behalf of the employer
  • PM controls time and cost as an administrative function
  • PM updates the risk register and issues instructions
  • It is widely accepted that the contract generates a large volume or paperwork / administration
  • Programme is a contract document
  • Requirement for parties to give early warnings
154
Q

What are some of the perceived advantages of using the NEC ECC contract?

A
  • The contract is based on mutual trust and co-operation
  • Focuses on pro-active risk management rather than on what happens when things go wrong
  • Encourages all parties to resolve cost and programme issues ‘up front’ rather than waiting until the final account
  • The contract is written is plain English
155
Q

What are the 6 main options (NEC3 ECC)

A
  • Option A: Priced contract with activity schedule
  • Option B: Priced contract with bill of quantities
  • Option C: Target contract with activity schedule
  • Option D: Target contract with bill of quantities
  • Option E: Cost-reimbursable contract
  • Option F: Management contract
156
Q

Can you provide an overview of Option A please?

A
  • Option A is a priced contract with an activity schedule where the risk of carrying out the work at the agreed prices is largely borne by the contractor
  • The advantage of using an activity schedule is that it simplifies the administration of the interim payment process. With subsequent interim payments being made against the completion of each activity - so no partial payments

Key points

  • Lump sum contract
  • Project is usually well defined at tender
  • Payment on completion of defined activities
  • Suitable for traditional and design & build
157
Q

Can you provide an overview of Option B please?

A
  • Option B is a priced contract with a bill of quantities (BoQ) where the risk of carrying out the work at the agreed prices being borne by the contractor

Unlike option A where specific elements of work within an activity schedule are certified for payment upon full completion, when using Option B the contractor is entitled to be paid interim payments based on a percentage of each BoQ item in line with the contract payment schedule

158
Q

Can you provide an overview of Option C please?

A
  • Option C is a target cost contract with an activity schedule where the out-turn financial risks are shared between the client and the contractor in an agreed portion
  • The Option C contract allows the financial risks to be shared between the parties (employer and the contractor) which motivates the contractor to deliver the works in the most cost-efficient way
  • The target cost is agreed between the parties which is made up of the contractor’s estimate of the ‘Defined Costs’ plus a fee which is to cover the contractor’s costs, overheads and profit

Key points

  • The target cost is set by the activity schedule
  • The target moves with compensation events
  • The contract uses the paid & gain mechanism for sharing risk
159
Q

Can you provide an overview of Option D please?

A
  • Option D is a target cost contract with a bill of quantities where the out-turn financial risk are shared between the client and contractor in an agreed proportion
  • The contract operates in a similar way to Option C; however, a BoQ is used instead of an activity schedule

Key points

  • Target cost set by the bill of quantities
  • Target moves with compensation events
  • The contract uses the pain & gain mechanism for sharing risk
160
Q

Can you provide an overview of Option E please?

A
  • Option E is a cost reimbursable contract, often referred to as “cost plus”.
  • Under this option, the employer will largely take on the financial risk, the contractor is reimbursed for all their actual costs plus a pre-agreed overhead and profit percentage
  • Option E might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, such as emergency work (urgent alteration or repair work)
161
Q

Can you provide an overview of an Option F please?

A
  • Option F is a cost reimbursable management contract
  • The works are designed and/or constructed by multiple subcontractors who are contracted to a management contractor
  • The management contractor is responsible for the work and is paid a fee (the cost that it pays the works contractors plus an additional fee), while the financial risk is largely take by the client
162
Q

Which NEC ECC main option carries the least financial risk for the employer?

A

Option A, this is because it is a fix price contract

163
Q

Which NEC ECC main option carries the most financial risk for the employer?

A
  • Option E, this is because the contractor is reimbursed and the actual costs they incur in carrying out the works, plus an additional fee
  • The below table shows how commercial risk is apportioned for each of the 6 contracts
164
Q

What are Secondary Options under NEC3 ECC?

A

Dispute resolution

  • W1
  • W2

X Clauses

  • X1 - Price adjustment for inflation
  • X2 - Changes in the law
  • X3 - Multiple currencies
  • X4 - Parent Company Guarantee
  • X5 - Sectional Completion
  • X6 - Bonus for early completion
  • X7 - Delay damages
  • X8 to X11 - Not used in ECC
  • X12 - Partnering
  • X13 - Performance bond
  • X14 - Advanced payment to the contractor
  • X15 - Limitation of the contractor’s liability for his design to reasonable skill & care
  • X16 - Retention
  • X17 - Low performance damages
  • X18 - Limitation of liability
  • X20 - Key Performance Indicators

Options dealing with national legislation

  • Y(UK)2 - The Housing Grants, Construction and Regeneration Act 1996
  • Y(UK)3 - The Contracts (Rights of Third Parties) Act 1999

Additional conditions
- Z clauses

165
Q

What are Z Clauses?

A

Z clauses are used to amend standard form NEC contracts. They can be inserted into NEC contracts as a means of adding conditions or amending wording

166
Q

What problems can potentially arise when drafting Z clauses into the contract?

A
  • Poorly drafted Z clause can be problematic if it does not work effectively with the core clauses in the standard contract. For example, a Z clause which amends one part of the core clauses may impact upon other core clauses as there may already be a complex interaction between many of the terms
  • Z clauses should therefore only be drafted by individuals with a good knowledge of NEC contracts and who understand both the intention of the parties and how the clauses will affect the rest of the contract
167
Q

With reference to the contractor’s programme, how does NEC differ from JCT?

A
  • The programme is not a contract document under JCT, under NEC it is
  • The programme plays a significant role in the NEC contract, one of its key functions to assist with the compensation event assessment process
168
Q

What are the different types of float on an NEC programme?

A
  • Total float
  • Time risk allowance
  • Terminal float
169
Q

Can you explain what total float is please?

A
  • The time an activity can be delayed from its early start date without delaying the planned completion
  • Available either to the employer or the contract (on a first come first served basis)
  • In the case below, total flow is 3 weeks, activity F could be delayed by 3 weeks prior to effecting the planned completion
170
Q

Can you explain what time risk allowance is please?

A
  • This is the duration allows in each activity by the contractor to account for the risk in not completing that activity in the minimum possible period
  • It is ‘owned’ by the contractor and cannot be used to mitigate the effect of a compensation event
  • For example, an activity might take 3 weeks 2 days to complete assuming normally circumstances and conditions. However, downtime and poor weather might result in the activity actually taking 4 weeks to complete (time risk allowance is therefore 3 days)
171
Q

Can you explain what terminal float is please?

A
  • The duration between planned completion and the current contract completion date
  • This is also ‘owned’ by the contractor and cannot be used to mitigate the effect of a compensation event
  • If planned completion moves forward due to unused risk allowance and the gap between the planned completion and contract completion becomes greater, this can be “banked” as terminal float
172
Q

How can the completion date be changed?

A

By a compensation vent or acceleration

173
Q

How can the planned completion date be changed?

A
  • Anything can change it
  • For example, the contractor could be delayed in completing activities or works could be going faster than originally anticipated
174
Q

What are key responsibilities or the project manager under the contract?

A
  • The NEC contract has no contract administrator, clerk of works or architect (named in the contract). As such, the project manager is the focal point. It is the project manager’s duty to manage the contract on behalf of the employer
  • The project manager will administer the contract on behalf of the employer and is designated authority to issue all instructions, notifications and other communication required under the contract
  • The project manager is the only person who can change the works information using his/her expertise
  • The project manager should be on site regularly and be aware of progress, including any changes to price, defects and compensation events
  • Monitors the execution of the project and ensures all parties adhere to conditions of contract
175
Q

What are the key responsibilities of the supervisor under the contract?

A
  • Defined as an individual or a team responsible for the contractor’s compliance with the works information (basically to check for defects an is independent to the project manager)
  • The traditional clerk of works role (JCT contracts) is the closest comparison; however, the supervisor is much more involved and has significant authority under the NEC contract
  • The supervisor raises defects notices for works not in accordance and can issue instructions to search for a defect
176
Q

What are key responsibilities of the employer under the contract?

A
  • Give site access
  • Ensure any transfer of authority over and above what is normal within the contract is communicated to the contractors
  • Make payments in accordance with the contract
  • Take out any necessary insurance provisions
  • The employer is defined as an organisation and not an individual. This is common practice and avoids issues when individuals move on within an organisation the liability is kept within the organisation as it is the organisation’s ultimate responsibility
177
Q

What is key requirements for the contractor under the contract?

A
  • The contractor’s responsibilities are outlined in Clause 2 of the contract. The key / overarching responsibility is to provide works in accordance with the works information
178
Q

What is the works information (WI)?

A
  • Works information specifies and describes the works the contractor is to provide and sets out any constraints to how the contractor provides the works
  • Good quality works information is vital to achieving better outcomes for projects and reducing misunderstandings and disputes. Works information should be prepared with individual project requirements and the operation of the ECC in mind
  • If works information is not precise, there is a risk that the contractor will interpret it differently from the employer’s intention

Key points

  • Specifies and describes the works
  • States any constraints on how the contractor provides the works
  • Works information provided by the employer includes:
  • Technical information
  • Specification and drawings
  • Constraints (for example specific safety requirements)
  • Employer’s requirements for work to be designed by the contractor
179
Q

How can you make the NEC3 ECC a design & build contract?

A

You would specify in the works information that the contractor is responsible for carrying out all aspects of the design

180
Q

What are compensation events?

A
  • Compensation events are events which are usually not the fault of the contractor and change the cost of the work or the time needed to complete it
  • As a result, the prices, key dates or the completion date may be reassessed and in many cases the contractor will be entitled to more time or money
181
Q

Does the NEC contract have relevant events and relevant matters like JCT?

A
  • No, NEC contracts deal with issues under the single heading - compensation events
  • Compensation events deal with both time and money
182
Q

Where are compensation events detailed in the contract and can you provide examples?

A
  • Compensation events are dealt with under clause 601

Examples

  • The PM gives instruction changing the works information
  • The employer does not allow access to and use of part of the site
  • The project manager gives an instruction to stop or not start any work or to change a key date
  • A test or inspection done by the supervisor causes unnecessary delay
  • The project manager or the supervisor changes a decision which he has previously communicated to the contractor
183
Q

What happens if the contractor notifies a compensation event 12 weeks after becoming aware of the event?

A
  • The contractor is not entitled to a change in the prices, the completion date, or a key date. Clause 61.3 requires the contractor to notify a compensation event within eight weeks of becoming aware of the event
  • There are exceptions to this - If the event arises from the project manager or the supervisor giving an instruction, issuing a certificate, changing an earlier decision, or correcting an assumption (the 8-week rule does not apply).
184
Q

What are early warning notices?

A

The early warning process is a mechanism for both parties to identify potential problems to the project. The contract emphasises that both parties are obliged to notify the other as soon as they become aware of a matter that cold affect time, cost or quality

Clause 16.1
The contractor and the project manager give an early warning by notifying the other as soon as either becomes aware of any matter which could:

  • Increase the total of the prices
  • Delay completion
  • Delay meeting a key date
  • Impair the performance of the works in use
185
Q

What are the key updates in NEC3 to NEC4?

A
  • NEC4 has introduced two new contracts into its suite of contracts:
  • Design and Build and Operate (DBO) Contract - The DBO contract combines the functions of design, construction, operation and/or maintenance to enable it to be procured from a single supplier
  • Alliance Contract (ALC) - This is for clients who wish to enter a single contract with several participants to deliver a project or programme of work. The focus of the contract will be on collaborative working encouraging all parties to work together in achieving client objectives
  • The ‘Risk Register’ has been re-named ‘Early Warning Register’ to distinguish it from the project risk register often used for wider project management purposes
  • ‘Employer’ becomes ‘Client’ and ‘Works Information’ becomes ‘Scope’
  • A 4 week period for escalation and negotiation of a dispute has been introduced, which takes place prior to commencing any formal proceedings. This requires nominated senior representatives of each party to meet and try to reach a negotiated solution
  • In secondary option X12, ‘Partnering’ has been changed to ‘Collaboration’ better to reflect the intent
  • There is now only one fee percentage, with no separate fee percentage for subcontracted works
  • Payments - Contractors must submit applications for payments, rather than the project manager being obliged to assess if they fail to do so
  • Language - All contracts are written gender neutral (no more he/his)
186
Q

What are the key differences between NEC and JCT construction contracts?

A
  • NEC is drafted in plain English. NEC attempts to eliminate the use of legal terms and instead provides for simpler language and gives words their natural meaning
  • NEC operates an ‘early warning’ process where both the project manager and contractor are required to notify each other of any matter which could affect time, cost, or quality
  • JCT splits up the components of time and cost, dealing with them and their subparts independently at various stages after a change arises. NEC deals with the effects of time and cost together
  • JCT: variations - NEC: compensation events
  • Each has an allotted person to act on behalf of the employer (contract administrator in JCT, project manager in NEC)
  • NEC uses 6 main options and secondary options, JCT uses separate contracts (for example Minor Works, Standard Building Contact, Design & Build)
  • The QS is not mentioned in NEC, only project manager
  • NEC is considered a more collaborative approach to working. Parties are required to work in the spirit of ‘mutual trust and cooperation’
  • Under NEC, the programme is a contract document, 25% of monies due can be withheld if the contractor does not submit an accepted programme
  • NEC has ‘periods of reply’ (incentivises the parties to respond to each other in a timely manner); however, the contract is heavy on administration
  • JCT contains provisional sums, NEC does not.