Construction technology and environmental services Flashcards
What RIBA Stage is on-site construction?
RIBA Stage 5 - Manufacturing and Construction
What is buildability?
- Buildability can be defined as the extent to which the design of a building facilitates the ease of construction.
- To help improve buildability, early contractor involvement should be considered to benefit from their experience and expertise.
What are the benefits of off-site construction over in-situ?
- Safety - Hazards such as falls from height are more likely to occur on site that in a factory.
- Efficiency and quality - Construction takes place in a controlled environment.
- Sustainability - Reduction in waste produced
- Speed - Work in the factory can be scheduled to begin at the same time as other activities on site, resulting in a shorter build programme.
What are temporary works?
Temporary works are the parts of a construction project that are needed to enable the permanent works to be built, they are usually required for safety or access reasons. Examples are:
- Propping.
- Scaffolding.
- Formwork.
- Excavation support.
- Access and task lighting.
What are hoists?
Designed for the vertical transportation of materials and/or people.
What is shoring?
Form of temporary support given to existing buildings and excavations. The purpose is to prevent collapse or excessive movement.
What is a substructure?
- Substructure is the lower portion of the building (in the ground) which supports the superstructure.
- Transmits the loads of the building to the ground.
- Includes foundations, basements and retaining walls.
What is a ground heave?
- Ground heave is usually associated with clay soil which swells when wet, causing the upward movement of the ground.
- As the soil generally cannot expand downwards of sideways, the result is that the exposed upper surface of the soil rises up.
What are some of the techniques available for ground improvement?
- Vibro compaction.
- Vibro stone columns.
- Vertical drains and vacuum consolidation.
- Soil mixing.
- Dynamic compaction.
- Dynamic replacement.
What are the different forms of excavation?
- Site clearance operations (removing vegetation and rubble).
- Stripping topsoil.
- Reduced level dig (to reach formation level).
- Cut and fill.
- Excavations for foundations.
What are the key factors the contractor should consider when excavating?
- Nature of the soil and moisture content of the ground.
- Method of excavation.
- If ground support systems are required.
- Proximity of existing buildings.
- Depth of excavation.
- Underground services and drainage.
Can you explain some of the techniques to waterproof a basement?
- Tanking - Materials such as asphalt, polythene sheeting, bitumen, are applied internally or externally to provide a continuous membrane to the base slab and walls.
- Drained Cavity - This method accepts a small amount of water seepage will occur. Cavity walls are formed, the water seepage is collected in the cavity and drained or pumped away.
Have you come across the term SUDS?
- Sustainable Urban Drainage Systems are designed to manage storm water locally (as close its source as possible), to mimic natural drainage and encourage its infiltration and/or attenuation. and even perspiration.
- SUDS help to reduce the reliance on existing drainage infrastructure.
- On Zurich we had
Permeable paving
swales
attenuation tanks
Can you detail a typical road build up please?
- Compacted and rolled type-1 subbase (100-250mm).
- Base course (70-150mm)
- Binder course (50-100mm)
- Wearing/surface course (20-40mm)
What is the purpose of a foundation?
- Foundations provide support for structures, transferring their load to the ground to avoid excessive settlement.
- Foundations should bear the loads of the superstructure
What are the typical considerations when selecting the type and size of foundations?
- The total loads of the building.
- Nature and load bearing capacity of the ground.
- Type of structure
- Cost
- Construction constraints (for example, their proximity to adjacent buildings/structures)
What are the different types of foundation?
- Strip foundations
- Pad foundations
- Raft foundations
- Piled foundations
What is a raft foundation?
A raft foundation is essentially a continuous slab that extends over the entire footprint of the building. The raft spreads the load of the building over a larger area that other foundations, the stress acting on the ground below is reduced.
What are pad foundations?
- Pad foundations are typically used to support individual or multiple columns, spreading the load to the ground below.
- They are usually square or rectangular on plan and can be reinforced or non-reinforced.
What are strip foundations?
As the name suggests, the formation is in a strip of linear structure that ultimately serves to spread the weight across the total area of the ground, typically used to support masonry.
What are pile foundations?
- A pile is a column (usually concrete) that extends deep into the ground.
- Where the bearing capacity of the soil is poor or imposed loads are very heavy, pile foundations may be required.
There are two main types of pile:
- End bearing piles
- Friction piles - shear stress
There are two main construction methods:
- Bored piles
- Driven concrete piles
In what scenarios might a piled foundation be the best solution for the project?
- Where the structure is heavy and the underlying soil is weak.
- In areas where settlement issued are common.
- Where the sub-soil water table is high.
- Where the load distribution of the structure is not uniform.
- Presence of horizontal forces.
Can you explain how end bearing and friction piles transfer the load of the building?
End bearing piles - The bottom of the pile rests on a layer of strong soil or rock, the load of the building is transferred through the pile onto the strong layer.
Friction piles - Friction piles work on a different principle, friction piles develop most of the pile bearing capacity by shear stresses along the sides of the pile. In other words, the surface of the pile works to transfer the forces to the soil.
What are the differences between bored piles and driven piles?
The fundamental difference lies in their point of manufacture. A driven pile is formed off site under factory-controlled conditions and a bored pile is manufactured on site.
What are the key advantages and disadvantages of driven piles?
Advantages
- Piles can be precast to the required specification
- Piles of any size, length and shape can be made in advance.
- A pile driven into granular soil compacts the adjacent soil mass, the bearing capacity of the pile may increase as a result.
- Fast, neat and clean installation.
Disadvantages
- Required heavy equipment for handling and delivery.
- Increased noise and vibrations generated by driving the piles.
- Can be costly if piles are too short
What are the advantages and disadvantages of bored piles?
Advantages
- Any size or shape of pile can be formed on site.
- No risk of damage during delivery and handling
- Reduced vibrations and noise
Disadvantages
- Significant spoils are generate that need to be handled
- Reliance and coordination on multiple trades (reinforcement crew, piling crew and concrete supplier)
- Unlike driven piles, bored piles do not improve the bearing capacity of the ground.
What are decant pile walls?
- A wall is formed by installing interlocking piles which create a solid barrier free of gaps.
- Typically used to form a retaining wall.
What is underpinning and why might it be required?
Underpinning is a method for repair and strengthening the foundations.
- Stabilising foundations undergoing settlement
- Stabilising foundations that have moved because of landslip or unstable slopes.
- Stabilising foundations affected by erosion, subsidence, or heave.
- Stabilising foundations affected by vibration damage.
- To increase the load capacity of the existing foundations.
- To accommodate a new adjoining building, new basement, or deep sewer.
What is the superstructure if a building?
- The structural components of a building constructed above ground level (usually everything above damp-proof course).
- The basic components of a buildings superstructure are columns, beams, slabs, walls.
What is the envelope of a building?
- A building envelope is the boundary between the interior and exterior of a building.
- The materials and components that form the external shell of a building such as brickwork, cladding, curtain walls.
Can you briefly explain what a retained façade is?
- The façade of the building is preserved whilst the rest of the structure is remodelled, or a new structure is built behind it.
- Façade retention is often used when restoring listed buildings
What are the key considerations when designing external walls?
- Weather protection.
- Fire resistance.
- Acoustic requirements.
- Thermal performance.
- Structural performance.
- Appearance/aesthetics
- Expected lifespan
- Future maintenance
What are standard brick dimensions in the UK?
Standard bricks are 215mm x 102.5mm x 65mm
How many UK standard size bricks are required per m2?
60 bricks per m2
How many UK standard size blocks are required per m2?
10 blocks per m2
What are weep holes?
- Small openings in the outer skin of masonry construction.
- Weep holes provide ventilation to the cavity and allow moisture to drain away.