Contract Documents Flashcards
What Contract documentation would you expect to see on a JCT Standard Building Project?
- The Articles of Agreement and Conditions of Contract
- Contract Particulars
- Drawings
- Specifications
- Schedule of Works (list of works)
- Pricing Doc - *Bills of Quantities – if it is with Quantities, Contract Sum Analysis or Schedule of Rates
- *Activity Schedule if CSA or SR used
- *Employer’s Requirements & Contractor Proposals – if there is a Contractor Design Portion
What Contract documentation would you expect to see on a JCT D&B Project?
- Articles of Agreement & Conditions of Contract
- Contract Particulars
- Drawings
- Specifications
- Works Schedule
- Employer’s Requirements
- Contractor Proposals
- Pricing Doc - Contract Sum Analysis
What is the ranking of Contractual Documents in JCT?
For JCT - Articles of Agreement and Conditions of Contract (override all other documents, including Framework Agreements)
What are the articles of agreement?
The ‘articles of agreement’ set out the core obligations of the parties involved. They consist of five sections:
1. Agreement
o Date of the agreement, the employer and contractors name and registered office
2. Recitals
o Factual explanation for the basis of the contract, describes what, how, how much?
3. Articles
o Sets out what is agreed between the parties. Obligation of Contractor and Employer. Identifies CA, QS, PD, PC. Right to adjudication / arbitration
4. Contract Particulars
o A schedule of the variables in the agreement and conditions
5. Attestation
o Confirming that the contract is correct and genuine. Contract executed either under hand or under seal (deed).
What is included in the Articles?
- Article 1 – Contractor’s obligations
- Article 2 – Contract Sum
- Article 3 – Architect/ CA
- Article 4 – QS
- Article 5 – Principal Designer
- Article 6 – Principal Contractor
- Article 7 – Adjudication
- Article 8 – Arbitration
- Article 9 – Legal Proceedings
What are Contract Particulars?
- The Contract Particulars set out the agreement and conditions of the contract that are specific for the project.
- They are a schedule of variables that detail the options that will be used from within the contract conditions, but without altering the overall intention of the contract clauses.
What are the contract conditions?
• Contract conditions set out the principal legal relationship between the parties to a construction project, determining allocation of risk and responsibilities.
• Conditions of contract must be read in conjunction with contract specifications, drawings, bills of quantities, activity schedules and special conditions.
• 9 sections of the conditions of the contract:
1. Definition and Interpretation
2. Carrying out of Works
3. Control of the Works
4. Payment
5. Variations (Changes D&B)
6. Injury, damage and Property Damage
7. Assignment, Performance Bonds and Guarantees, Third Party Rights and Collateral Warranties
8. Termination
9. Settlement of Dispute
What are the contract schedules?
They come after the main contract conditions, they provide supplementary information on conditions within the contract such as processes, options or timelines.
What schedules are in JCT SBC?
- Schedule 1 – Design Submission Procedure
- Schedule 2 – Variation and Acceleration Quotation Procedure (In D&B Sch 2 = Supplemental Provisions)
- Schedule 3 – Insurance Options
- Schedule 4 – Code of Practice
- Schedule 5 – Third Party Rights
- Schedule 6 – Forms of Bonds
- Schedule 7 – JCT Fluctuations Option A
- Schedule 8 – Supplemental Provisions
What are drawings and specifications?
- Working drawings include architectural, structural, civil, mechanical, electrical, public health and interior drawings, provide a visual representation of the works to be carried out.
- Usually executed electronically in CAD and are a graphical representation of the design. Can also be in 3D models.
- Specifications describe the products, materials and work required for a project.
- They DO NOT include cost, quantity or drawn information
- MUST be read alongside other information such as quantities, schedules and drawings.
- EXAMPLE: Performance specification describe the materials and workmanship required for a development
What is a performance specification and prescriptive specification?
• A performance specification is one where the designer (architect / engineer) sets the criteria for the contractor to deliver a package of work within a set of parameters. This allows the contractor to consider several ways of providing the required package to achieve a cost-effective solution as per the design intent drawings.
• EXAMPLE: Windows- minimum u-value, waterproofing ect.
• Details:
o Standards
o Description of materials to be used
o Execution, lay out, testing, installation.
- A prescriptive specification (full) identifies each and every item, right down to the spacing and number of screws required to fix plasterboard for example, as well as the size, type and material of the screw.
- Gives the client more certainty when the work is tendered and priced by the contractor.
What is National Building Specification (NBS) and what are the benefits of its use?
NBS is a master specification system. It describes the material, standards and workmanship of products for construction projects. NBS helped inform one of my projects on NatWest as to how many toilets needed to be installed within the building in line with the capacity of people using it
• Improves efficiency, reduces errors
• Aids in decision making, minimises repetitive works
• Avoids delay, helps develop drawings and designs
• Widely recognised, consistent terminology and understanding in the industry
What is a schedule of works?
- Schedule of works provide a list of the works required on a project.
- An alternative to bill of quantities and usually used on SBC without quants
- The Schedule references the requirements included in the specifications and contract drawings plus any additional ‘builders work’ or ‘fixing schedule’ type items, this is commonly referred to as a specified schedule of work.
- Typically they are used for small building projects or alterations work
What is a Bills of Quantities?
- A bill of quantities is prepared by the employers cost consultant (QS) and provides project specific measured quantities of the items of work identified in the specifications and drawings in the tender docs.
- Quantities are measures in number, length, area, volume, weight or time
- Issued to tenderers for them to provide a price for carrying out the works. Ensures all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
What are the benefits of a BOQ?
- Competitive tender- tenderers price the same quantities
- Fair and accurate system for tendering
- Makes it easier to quantify the work as a basis for the valuation of variations, the preparation of interim payments, and the final account.
- Informs the project budget
- Ensures the correct amount of materials are procured