Change / Variations Flashcards
What is a Change/Variation?
The term Variation means the alteration or modification of the design, quality or quantity of works.
A change order is work that is added to or deleted from the original scope of work of a contract, which alters the original contract amount and/or completion date.
When should a change/variation mechanism be established?
At the beginning of the project during the feasibility stage to understand how change will be controlled and managed.
What would you define in a change control procedure for your project?
- Governance procedure. Different levels of sign off
- Document the process (change control logs). Monitor and log changes.
- Change control forms
- Set regular meetings for reviewing and agreeing change
- Report cost impact with regards to changes. Work with QS
What is a change control log?
- Change identity no.
- Date raised
- Description
- Cost and Time impact
- Owner
- Accepted / Closed
What is a change control log? What does it capture?
It is a document that records all changes made on the project. it records: • Change identity no. • Date raised • Description • Cost and Time impact • Owner • Accepted / Closed
What is change control?
Change control is a process that ensures potential changes to the deliverables of a project or the sequence of work in a project, are recorded, evaluated, authorised and managed
How can change be funded within a project?
- fund the change from the construction/project risk allowance (contingency).
- fund the change by budget transfers within the project; or
- fund the change from a third party.
Who can instruct a change?
JCT – A/CA and EA
NEC - PM
How is change dealt with differently between JCT and NEC?
JCT contracts deals with time and cost change separately through relevant events and relevant matters whereas NEC deals with it combined in compensation events.
What effects the way change is valued?
The way the contract is priced. lump price cost agreed upfront, re-measurement at the end
How is a variation defined in the JCT?
The term Variation means the alteration or modification of the design, quality or quantity of works including:
• Additions, omissions or substitutions of any work
• The alteration of the kind or standard of any material or goods to be used in the work
• The removal from the site any work executed or site materials other than work materials or goods which are not in accordance with the contract.
The imposition by the employer of any [additional] obligations or restrictions, or the addition to or alteration or omission of any obligations or restrictions. These obligations or restrictions refer specifically to:
• access to the site, or specific parts of the site,
• limitations on working space or working hours
• Carrying out of work in a specified order
What section can of the contract is variations noted?
Section 5 – Variations
How are Variations Valued?
Employer and the Contractor shall agree the value of a Variation. (Common practice in the industry for the parties to exchange information and calculations pertaining to the value of a Variation and reach an agreement, which forms part of a rolling final account)
Additionally, the contractor could be asked to submit a quotation for agreement prior to an instruction being issued by the A/CA
Where agreement has not been reached, the QS is obliged to carry out a valuation of the variations in accordance with the Valuation Rules.
How is it priced differently with JCT SBC with Quants?
It is not they use the same 3 processes for valuing change as JCT SBC XQ
What is the Priced Document referred to in the contract?
They are documents within the contract that are used as a basis for valuing variations. Within JCT SBC XQ these include:
• Work Schedule
• Contract Sum Analysis
• Schedule of Rates
What is a variation quotation? (JCT SBC)
If the A/CA in his instruction for a Valuations states that the Contractor is to provide a quotation in accordance with Schedule 2 (Variation Quotation) the Contractor shall (subject to sufficient information) provide a quotation, unless within 7 days of his receipt of that instruction (or longer if agreed) he notifies the A/CA that he disagrees with the application of the procedure to that instruction.
What happens if the Contractor notifies the Contractor that he disagrees with the variation? (JCT SBC)
If the Contractor notified that they disagree with the variation within the (7 days or more if agreed) time period, he shall not be obtained to provide that quotation and the Variation shall not be carried out unless and until the A/CA gives a further instruction that the Variation is to be carried out and is to be valued by a Valuation.
What happens if the CA instructs a variation on an accepted Variation Quotation? (JCT SBC)
Where the Contractor has produced a Variation for the works and a Confirmed Acceptance issued, THEN if the A/CA subsequently issues an instruction requiring a Variation of that work, the Valuation of that Variation shall be made on a fair and reasonable basis. The valuation shall acknowledge the content of that quotation and that Variation shall include the direct loss/expense, if any incurred by the Contractor because the regular process of the works or of any part of them is materially affect by compliance with the instruction. The Variation Rules shall apply only to the extent that they are consistent with those requirements.
What right does the Contractor have to be present at measurement? (JCT SBC)
Where it is necessary to measure works for the purpose of the Valuation, the QS shall give the Contractor the opportunity to be present at the time of measurement and to take notes / measurements as required.