Contract Administration Flashcards

1
Q

TENDERING

Tell me about the process

A
  1. JCT Practice note 6 to be followed
  2. Tenders should be received either at the CA’s or clients Address prior to the given time.
  3. Sealed within a pre-written/addressed envelope
  4. Must be whiteness by another when opened
  5. Tender summary form should be completed and signed by the person that opened them and witness
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

TENDERING

How nay tenders would you go out to and why ?

A

Depends on the scope of works. Majority of schemes I have dealt with it has been 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

TENDERING

What would you include in a tender package ?

A
  • Prelims
  • Preamble
  • SoW
  • H&S Plan
  • Tender Summary
  • Drawings
  • Return Envelope
  • Separate pricing sheets
  • Letter indicating timescales
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

TENDERING

In what instances would you accept a tender other than the lowest ?

A
  1. Contractor with greater specialist knowledge
  2. Capacity to carryout works, possible mistakes made or general uncertainty about a particular contractor

NOTE: Should be mentioned in the invitation to tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens at PC ?

A
  • No LD’s
  • Documents given: H&S File, O&M (operation and Maintenance) Manuals, Record Drawings
  • Start of Rectification Period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

JCT- Why was IC selected for this project ?

A
  • The works were simple in nature (could if used MW contract too)
  • Loss and Expense expressly provided for (not on MV)
  • Section completion
  • No relevant events in MW Contract
  • Where provisions are required to cover named specialises
  • No need for IC (with contractor design) the works were simple and clear
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

JCT- What was the length of the rectification period and why was this length chosen?

A
  • 6 months

- Retention at 5% at interim payments and 2.5% at final payment (after Rectification Period)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

JCT- How did you determine that the rain was ‘exceptionally adverse’

A
  • Can be hard, must be worse that average
  • MET Office average weather records
  • Site photos
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is 6.5.1 Insurance ?

This insurance enables claims for non-negligent injury or damage to the property. so insurance in joint and issued to both names.

Three options (a), (c), & (c) ?

A

Option A- which is where the Contractor takes out and maintains joint names all risk insurance of the works.

Option B- Which is where the Employer take out and maintains the joint names all risks insurance of the works

Option C- Which is the only option referring to renovations and involving existing structure. This is where the Employer takes out and maintains a join name all risk insurance of the works and the policy also insures the existing structure and contents against specified perils’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Tell me about Section 7: Performance Bonds, Guarantees, Collateral Warranties and Third Party Rights ?

A

Performance Bonds and Warranties (from the a bank or parent company) - used as surety should contractor go bust. Must be requested in the contractual particulars.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Tell me about Section 7: Performance Bonds, Guarantees, Collateral Warranties and Third Party Rights ?

A

Performance Bonds and Warranties (from the a bank or parent company) - used as surety should contractor go bust. Must be requested in the contractual particulars.

Collateral Warranties is a separate contract formed in order to create a contractual liability that would not exist otherwise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly