Contract Administration Flashcards
TENDERING
Tell me about the process
- JCT Practice note 6 to be followed
- Tenders should be received either at the CA’s or clients Address prior to the given time.
- Sealed within a pre-written/addressed envelope
- Must be whiteness by another when opened
- Tender summary form should be completed and signed by the person that opened them and witness
TENDERING
How nay tenders would you go out to and why ?
Depends on the scope of works. Majority of schemes I have dealt with it has been 4
TENDERING
What would you include in a tender package ?
- Prelims
- Preamble
- SoW
- H&S Plan
- Tender Summary
- Drawings
- Return Envelope
- Separate pricing sheets
- Letter indicating timescales
TENDERING
In what instances would you accept a tender other than the lowest ?
- Contractor with greater specialist knowledge
- Capacity to carryout works, possible mistakes made or general uncertainty about a particular contractor
NOTE: Should be mentioned in the invitation to tender
What happens at PC ?
- No LD’s
- Documents given: H&S File, O&M (operation and Maintenance) Manuals, Record Drawings
- Start of Rectification Period
JCT- Why was IC selected for this project ?
- The works were simple in nature (could if used MW contract too)
- Loss and Expense expressly provided for (not on MV)
- Section completion
- No relevant events in MW Contract
- Where provisions are required to cover named specialises
- No need for IC (with contractor design) the works were simple and clear
JCT- What was the length of the rectification period and why was this length chosen?
- 6 months
- Retention at 5% at interim payments and 2.5% at final payment (after Rectification Period)
JCT- How did you determine that the rain was ‘exceptionally adverse’
- Can be hard, must be worse that average
- MET Office average weather records
- Site photos
What is 6.5.1 Insurance ?
This insurance enables claims for non-negligent injury or damage to the property. so insurance in joint and issued to both names.
Three options (a), (c), & (c) ?
Option A- which is where the Contractor takes out and maintains joint names all risk insurance of the works.
Option B- Which is where the Employer take out and maintains the joint names all risks insurance of the works
Option C- Which is the only option referring to renovations and involving existing structure. This is where the Employer takes out and maintains a join name all risk insurance of the works and the policy also insures the existing structure and contents against specified perils’
Tell me about Section 7: Performance Bonds, Guarantees, Collateral Warranties and Third Party Rights ?
Performance Bonds and Warranties (from the a bank or parent company) - used as surety should contractor go bust. Must be requested in the contractual particulars.
Tell me about Section 7: Performance Bonds, Guarantees, Collateral Warranties and Third Party Rights ?
Performance Bonds and Warranties (from the a bank or parent company) - used as surety should contractor go bust. Must be requested in the contractual particulars.
Collateral Warranties is a separate contract formed in order to create a contractual liability that would not exist otherwise.