Contract Administration Flashcards

1
Q

What is your understanding of latent defects and what
contractual issues are associated with them?

A
  • Latent defects are defects which only come to fruition some time after building completion and may take many years to become
    identifiable.
  • A claim in contract can only be brought about within the limitation period of the contract, 6 or 12 years depending on whether the contract was executed as a deed or underhand.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the contractor deemed to have allowed on the
inclusion of a defined provisional sum?

A
  • They are deemed to have made proper allowances for carrying out the work in their programme and preliminaries.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the contractor deemed to have allowed for with undefined provisional sums?

A
  • Expenditure of the undefined provisional sum may carry additional costs for programme or preliminaries as a result of carrying out the works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How are provisional sums dealt with in the final account?

A
  • The provisional sums included in the contract are omitted and the actual amount added.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does NEC stand for?

A
  • New Engineering Contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main parts of the JCT contracts?

A
  1. Recitals.
  2. Articles.
  3. Contract Particulars.
  4. Attestation.
  5. Conditions divided into 9 sections
  6. Schedules.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a bespoke contract?

A
  • Contract conditions that are drafted specifically for a particular project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the advantages of standard forms of contract?

A
  • Experts - They are written by legal experts.
  • Familiarity - Parties should be familiar with the provisions in the form providing greater consistency.
  • Rights and obligations - Clearly set out for each party.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What the disadvantages of standard forms of contract?

A
  • They may not be appropriate to the needs of a particular project or client.
  • Using an inappropriate standard form for the project will cancel out any advantages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When would use a bespoke contract rather than a standard form?

A
  • They should generally be used for major projects with novel obligations.
  • When specialist advisors can undertake the amendments as this requires great skill and knowledge.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the types of dispute resolution in JCT contracts?

A

Negotiation: Parties engage in informal discussions and negotiations to reach a mutual resolution without involving a third party.

Adjudication: A statutory process that provides a quick and interim resolution to disputes. An adjudicator, usually an industry expert, makes a binding decision on the dispute.

Mediation: A neutral third party, called a mediator, helps facilitate discussions and assists the parties in finding a mutually agreeable solution.

Arbitration: A formal process where an independent arbitrator or panel hears the dispute and issues a binding and enforceable decision known as an award.

Litigation: If all other methods fail, parties can take the dispute to court, where a judge or jury issues a judgment. Litigation is a formal and public process, often more time-consuming and expensive than alternative methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the change control procedure under the standard building contract?

A
  1. Identification of Change
  2. Notification
  3. Assessment
  4. Cost and Time Implications
  5. Approval
  6. Implementation

IN.A.CAI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Management of variations to the works - Can you instruct a variations without a formal CAI?

A

Key Points of SBC Clause 3.12
Definition of Variations: This clause defines what constitutes a variation, including changes to the quality, quantity, or nature of the works.

Instructions for Variations: It outlines that the contractor must carry out variations when instructed by the Contract Administrator (CA).

Valuation of Variations: The clause specifies how variations will be valued. This may involve assessing the impact on cost and time.

Notification: The contractor must notify the CA of any circumstances affecting the variation, ensuring proper communication.

Time Implications: It includes provisions for assessing how variations may affect the completion date of the project.

Documentation: All variations must be documented to maintain a clear record for both parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly