What is included in a payment certificate?

A

1) Date of certificate
2) Contract date
3) Key payment timelines (due date, assessment date, final date for payment etc)
4) Site address & project number
5) Contract sum
6) Certificate reference number
7) Gross value
8) Retention
9) Cumulative of previous payments
10) Amount due
11) Director / Contract Admin signature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the difference between a Contract Administrator and Employer’s Agent?

A

Employers Agent works on D&B whereas CA works on SBC.

CA is more impartial between Contractor and Client whereas EA acts on behalf of the Employer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who does this role on an NEC contract?

A

Project Manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a relevant event vs relevant matter?

A

Relevant Event is an extension of time. Relevant matter entitles the Contractor to EOT and loss and expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you assess a relevant event or matter?

A

Well, the Contractor is required to identify “if and when it is reasonably apparent that they are in delay” and give notice to the EA/CA.

I would review this notice and check the Contract and Contract Amendments to review which Relevant Events/ Matters caused the Contractor to be in delay.

I would review the programme and see if the matter affecting the Contractors progress had impacted their critical path, reviewing all relevant substantiation.

If deemed acceptable, then I would instruct the fixing of the Completion date. Otherwise, I would inform the Contractor of my rejection to their extension of time claim.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the different Relevant Events?

A
  • Employers Instructions
  • Deferment of possession of the site
  • Exceptionally adverse weather
  • Force Majeur
  • Strike or local combination of workmen affecting any trade on site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What should be considered when assessing a Contractors claim for EOT?

A
  • Contract / Contract Amendments
  • That the Contractor has used their best endeavours to prevent delay
  • That the Contractor has given notice when reasonable and apparent
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you name 5 docs an EA/CA would issue?

A

1) Payment Certificate
2) Pay less notice
3) Practical Completion certificate
4) Notice of non completion
5) Certificate of making good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

On what basis would you issue a PC cert?

A

On the basis the Contractor has fulfilled their obligations under the Contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What needs to be on a payment certificate?

A
  • Date
  • Project
  • Employer
  • Contractor’s Company
  • Gross value
  • Amount of retention
  • Amount on this certificate
  • Signature
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What would you do in the instance a contractor disagrees with the amount on a payment cert?

A

I would liaise with the Contractor to understand why they had disagreed with my payment cert, if I had included the incorrect values or if they disagree with the QS.

If it was my mistake, I would look to rectify this issue by issuing a revised payment notice which supersedes the previous issue.

If the Contractor disagreed with the QS, I would look tounderstand the basis of the disagreement. If the QS has made a fair and reasonable assessment, then I would issue my payment certificate and it would be for the Contractor to dispute.

However, if the Contractor was correct, I would look to liaise with the QS to see if they would revise their assessment and I would update my payment certificate accordingly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should be on a change control register?

A
  • Reference
  • Description
  • Action owner
  • Comments
  • Cost / Programme impact
  • Status (open / closed)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What sections of the contract would you check to ensure you are not instructing works already included?

A

Drawings and specification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly