Construction Technology Flashcards

1
Q

Explain the basic construction process of a concrete frame structure. What are the primary advantages and disadvantages of using concrete frame construction compared to other methods?

A

Answer: Concrete frame construction typically involves the erection of a framework consisting of columns, beams, and slabs made from reinforced concrete. The process begins with the construction of foundations, followed by the casting of columns and beams which form the skeleton of the building. Slabs are then cast on the framework to create floors. Can be either cast in situ or pre cast.
- Advantages: Concrete frame structures offer high strength and durability, fire resistance, and flexibility in design, allowing for large open spaces without columns. They also provide good thermal mass, which contributes to energy efficiency.
- Disadvantages: The main drawbacks include the longer construction time due to curing requirements, the weight of the structure requiring strong foundations, and potential for cracking or shrinkage if not properly managed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What considerations should be taken into account when choosing concrete frame construction for a project?

A

Answer: Key considerations include the load-bearing requirements, fire resistance needs, and the design flexibility required for the building. The time constraints of the project should also be considered due to the curing times needed for concrete. Additionally, the availability of skilled labour for concrete construction and the potential environmental impact due to cement production should be evaluated. Good load bearing, so good for high rise and multiple floors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key benefits of steel frame construction, particularly in relation to speed of construction and flexibility of design?

A

Answer: Steel frame construction is known for its rapid assembly, as pre-fabricated steel components can be quickly erected on-site. This speed can significantly reduce the overall construction timeline. Steel also allows for more design flexibility, enabling longer spans without intermediate supports, and is adaptable for future modifications. Its high strength-to-weight ratio makes it suitable for high-rise buildings and structures requiring large open spaces.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does steel frame construction impact the overall sustainability of a building project?

A

Answer: Steel is highly recyclable, which can reduce the environmental impact of a building project. Additionally, steel frame buildings can be designed for deconstruction, further enhancing their sustainability. However, the production of steel is energy-intensive, which must be balanced by its long-term durability and potential for reuse.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you describe the main steps involved in traditional masonry construction?

A

Answer: Traditional masonry construction typically involves the laying of bricks or stones in a pattern, bonded together with mortar. The process begins with setting out the building’s footprint, followed by the construction of a solid foundation. The walls are then built-up layer by layer, with careful attention to alignment, plumb, and level. Openings for doors and windows are incorporated as the walls rise. Finally, the walls are capped with a lintel or beam to support the structure above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the long-term maintenance considerations for buildings constructed using traditional masonry?

A

Answer: Masonry buildings require regular maintenance to prevent moisture ingress, which can lead to deterioration of mortar joints and the masonry units themselves. Repointing of mortar, repairing cracks, and ensuring proper drainage away from the building are essential tasks. Additionally, maintaining the roof and managing vegetation around the building helps to protect the masonry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you outline the key stages of the RIBA Plan of Work and how they contribute to the overall management of a construction project?

A

Answer: The RIBA Plan of Work is divided into eight stages:
Stage 0 – Strategic Definition: Project objectives and feasibility are assessed.
Stage 1 – Preparation and Brief: Detailed project brief is developed.
Stage 2 – Concept Design: Initial design ideas are proposed and developed.
Stage 3 – Spatial Coordination: The design is refined and coordinated with structural and building services.
Stage 4 – Technical Design: Detailed design information is prepared for construction.
Stage 5 – Manufacturing and Construction: The project is constructed.
Stage 6 – Handover: The building is handed over to the client and users.
Stage 7 – Use: Post-occupancy evaluation and feedback are conducted.
These stages ensure that a project is carefully planned, designed, and executed, with clear milestones for review and decision-making.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What challenges might arise during the foundation installation phase, and how would you address them?

A

Answer: Challenges during foundation installation can include unexpected ground conditions, such as poor soil quality or the presence of underground obstacles. These can be addressed by conducting thorough site investigations beforehand and having contingency plans, such as modifying foundation design or employing ground improvement techniques. Weather conditions can also impact foundation work, which requires careful scheduling and protective measures to ensure the integrity of the foundations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do the different stages of the RIBA Plan of Work align with your experience in monitoring construction progress?

A

Answer: My experience aligns with several stages of the RIBA Plan of Work, particularly during the construction phase (Stage 5), where I have monitored foundation installation, steel frame erection, and modular building installation. My role has involved ensuring that the construction aligns with the technical design (Stage 4) and overseeing progress to meet the project’s requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Could you describe any specific issues you encountered when monitoring foundation installation, and how were they resolved?

A

In a project the client installed the wrong foundation not as designed by the engineer. i took measures and photos and requested details of the build up from the contractor and sent to the SE who produced the design. The engineer confirmed that the raft foundation was suitable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In your experience, what are the critical factors to monitor during the erection of a steel frame building?

A

Answer: Critical factors include ensuring the accuracy of the steel frame alignment and connections, maintaining site safety protocols, and coordinating with other trades to avoid clashes. Monitoring the delivery and storage of steel components to prevent damage or distortion is also important. Additionally, it’s essential to verify that all components are installed as per the design specifications, especially bolted and welded connections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you ensure quality control and safety during the steel frame erection process?

A

Answer: Quality control is maintained by conducting regular inspections and cross-checking with the design drawings to ensure that each component is installed correctly. Safety is ensured through rigorous adherence to health and safety regulations, providing appropriate training to workers, and using personal protective equipment (PPE).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the advantages of modular construction, particularly in terms of project timelines and cost management?

A

Answer: Modular construction offers significant advantages in terms of reduced project timelines because modules are prefabricated off-site while site preparation is underway. This parallel construction process can lead to earlier project completion. Cost management benefits arise from reduced on-site labour, lower material waste, and minimized weather-related delays. Additionally, modular buildings can be more easily disassembled and relocated if necessary, adding flexibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How has your understanding of construction technology and the RIBA Plan of Work influenced your approach to managing or assisting in construction projects?

A

Answer: My understanding of construction technology and the RIBA Plan of Work has enabled me to approach projects systematically, ensuring that each stage of construction is carefully planned and executed. This knowledge helps me anticipate potential issues and coordinate effectively with different teams to maintain project timelines and quality standards. By understanding the interdependencies of different construction phases, I can contribute to more efficient project management and problem-solving.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Can you discuss any potential drawbacks of modular building installations that you’ve observed in your experience?

A

Answer: Potential drawbacks of modular building installations include limitations in design flexibility, as modules must conform to transportable sizes and shapes. There can also be challenges in aligning and integrating modules on-site, particularly if there are discrepancies between site conditions and the prefabricated components. Additionally, achieving seamless integration of building services across modules may require careful coordination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Can you explain the rationale behind recommending stone mastic asphalt (SMA) over permeable surfacing for the hardstanding design?

A

Answer: I recommended SMA over permeable surfacing because SMA provides a durable and cost-effective solution. While permeable surfaces offer drainage benefits, they often require a more expensive sub-base to manage water infiltration effectively. SMA, combined with a water attenuation tank, allows us to manage surface water runoff efficiently while also reducing the costs associated with the sub-base and top coat. This approach met the client’s budget constraints while ensuring compliance with SuDS requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How did you ensure compliance with Sustainable Drainage Systems (SuDS) when advising on the use of a water attenuation tank?

A

engineer designed, done based on the catchment area, rainfall volumes. DEsigned to accomodate 1 in 100 year storm event for extreme rainfall.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What factors did you consider when balancing cost savings against performance and regulatory compliance in this project?

A

Answer: I considered several factors, including the initial cost of materials and construction, long-term maintenance requirements, and the need to meet SuDS regulations. I also evaluated the lifespan and durability of the proposed materials. The goal was to provide a solution that was not only cost-effective upfront but also performed well over time and complied with all relevant regulations. The choice of SMA and the incorporation of a water attenuation tank struck the right balance between these considerations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How did you communicate your recommendation to the engineer and other stakeholders involved in the project?

A

Answer: Initially the LPA requested that we included some form of SUDS design, so I knew that either permeable surfacing or water attenuation would be required. With that in mind, I discussed with the engineer on site and requested two options to present to the client. Both of the engineers’ designs were suitably designed so either option could be chosen. I based my recommendations mainly on the longevity of the permeable surfacing and that I didn’t think it was necessary suitable in the long run. Based on costs from other projects the cost to install permeable would be more than SMA even with the excavation and install of the attenuation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Did you consider any alternative solutions or materials before proposing SMA? If so, what were they, and why were they not selected?

A

Answer: Other permeable option such as permeable block paving was considered. However, I advised against this mainly due to cost, as the paving is specialised and it requires skills to properly install the block paving to ensure it is level. Requires regular weeding at joints to maintain aesthetic appearance. Prone to inking underweight if the sub base is not correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are SUDS?

A

Answer: SUDS stands for Sustainable Drainage Systems. Primary goal is to reduce the surface water run-off in urban areas. The primary goals are to prevent flooring, improve water quality. Ways include permeable paving, rainwater harvesting and storage/attenuation. The Flood and Water Management Act 2010 in the UK provided a legal framework for managing flood risks and promoting the use of SUDS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What considerations led you to propose the reuse of an existing concrete slab as the foundation for the modular building?

A

Answer: The existing concrete slab presented an opportunity for cost savings by eliminating the need for new foundations. However, its suitability for reuse depended on several factors, including its structural integrity and alignment with the modular building design. I considered the potential cost benefits against the need for raised pads to achieve level access, ultimately determining that the economic advantages outweighed the challenges. The existing slab also reduced construction time and minimized site disturbance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How did you assess the structural integrity of the existing slab and what steps did you take to confirm its suitability?

A

Answer: I instructed core testing of the slab to assess its compressive strength, thickness, and condition. The test results were reviewed by a structural engineer, who confirmed that the slab was suitable for reuse as the foundation for the modular building, provided that certain adjustments were made, such as adding raised pads and accounting for the existing finished floor level. This thorough assessment ensured that the slab could safely support the new structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Could you elaborate on the challenges associated with ensuring level access and the design of the ramp and cloaking for the modular building?

A

Answer: The main challenge was achieving level access given the existing slab’s height. To address this, I recommended installing a ramp, which had to be designed to comply with accessibility standards while integrating aesthetically with the overall site design, 1:20 ramp gradient, suitable width and handrail height and landing. The cloaking presented another challenge, as it needed to both conceal the underside of the building and provide proper ventilation. I proposed brickwork cloaking that matched the boundary wall, ensuring a cohesive look while allowing for the installation of airbricks to maintain sub-floor ventilation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Why was sub floor ventilation suggested?

A

Answer: The bottom of the cabin is timber. When lowered onto a slab and built around with a ramp or and cloaking wall there would be little to no ventilation (there would be a small amount because of the very small gaps between the copings and the cabins. Air bricks allow for air to flow beneath the building controlling moisture levels. If this wasn’t the case the timber sub floor could rot and invite a termite infestation leading to further deterioration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is core testing?

A

Answer: Core testing involves extracting a core of concrete from the slab. The purpose is to assess the concrete strength, evaluate the quality of the concrete mix and identify any deterioration. Can be cored right through to determine the thickness of the slab.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

If the slab contained no mesh, what are some potential Issues?

A

No reinforcement would mean limited tensile strength, thus affecting load bearing capacity. Could be used, depending on thickness and the spread of load, should not be concentrated.

28
Q

What specific information or parameters are typically assessed during core testing of a concrete slab?

A

Answer: The purpose is to assess the concrete strength, evaluate the quality of the concrete mix and identify any deterioration.

29
Q

Who advised on these testing locations?

A

Answer: An engineer advised on the locations, ensuring that the structural ability of the slab was not compromised. The engineer ensured that none of the pads would be where a sample was taken. After cores were filled with high strength none shrink grout.

30
Q

How many Cores were taken?

A

Answer: 5, one to each corner and one to the centre, core tests are usually in a grid formation to establish depths at all areas.

31
Q

Did you need to confirm the thickness of the slab? Why was this?

A

Answer: Yes, the thickness of a slab affects its load bearing capacity. Thicker slabs can support heavier weight with less deflection. Thicker slabs tend to go down to deeper to more solid ground. In a geotechnical report it stated that the ground had variable soil conditions, which is likely why a raft was used in the first instance for the previous building.

32
Q

What other tests could you have done?

A

Ground penetrating radar (GPR) test, which omits electromagnetic waves into the material and analyses reflection from embedded objects. The results can be effected by rebar.

33
Q

Can you describe the process of commissioning an asbestos R&D survey and how the findings influenced the project’s execution?

A

Answer: The R&D survey was commissioned by contacting a certified asbestos surveyor, who conducted a thorough inspection of the property, including areas not immediately visible. The survey findings revealed asbestos-containing materials that required careful handling. Based on these results, I adjusted the project timeline to accommodate safe removal and disposal of asbestos by licensed contractors. The findings also led to the implementation of stringent safety measures during the refurbishment, including air monitoring to ensure that the site was safe for occupancy post-removal.

34
Q

When you suspected the presence of asbestos in the roof and walls, how did you proceed to confirm your suspicions and manage the risk?

A

Answer: Upon suspecting asbestos due to the age and appearance of the building materials, I immediately instructed an asbestos R&D (Refurbishment and Demolition) survey to confirm the presence and extent of asbestos-containing materials. Once the survey results identified asbestos cement sheets in the roof and asbestos insulation board in the walls, I ensured that all works were planned and executed with strict adherence to health and safety regulations, including the use of licensed asbestos removal contractors.

35
Q

What precautions were necessary during the re-roofing and wall cladding replacement to ensure safety and regulatory compliance?

A

Answer: The primary precaution was the safe removal of asbestos-containing materials before any further work commenced. This involved sealing off the affected areas, using proper personal protective equipment (PPE), and employing licensed asbestos removal specialists. The work was carried out under controlled conditions to prevent asbestos fibers from becoming airborne. Additionally, I ensured that all waste was disposed of at licensed facilities in compliance with environmental regulations. Continuous air monitoring was conducted to verify the safety of the work environment throughout the process.

36
Q

How did you ensure that the client was fully informed and compliant with asbestos management protocols before occupancy?

A

Answer: I kept the client informed throughout the process by providing regular updates and clear explanations of the risks and necessary precautions. After the asbestos removal was completed, I provided the client with the asbestos clearance certificate, which confirmed that the site was safe for occupancy. This document was crucial in demonstrating compliance with health and safety regulations. I also advised the client on the importance of maintaining an asbestos register and monitoring any remaining asbestos-containing materials in non-disturbed areas.

37
Q

Why was asbestos used historically?

A

Answer:
- Asbestos was widely used because it is high resistant to fire and heat.
- Insulating properties, thermal and acoustic.
- Affordability and availability.

38
Q

How did you communicate your concerns regarding asbestos to the client, and what actions did you recommend to address the issue?

A

Answer: I advised they get an asbestos R&D survey undertaken, which is a more intrusive version of a management survey, where samples are taken.

39
Q

How did you ensure compliance with relevant regulations and guidelines governing the handling and removal of asbestos-containing materials?

A

Answer: Works were licensable due to the time taken to remove the AIB. require a risk assessment and appropriate controls in place. Those carrying out the work must have the correct level of training to protect themselves and others. As defined by Control of asbestos regulations 2012

40
Q

What measures did the contractor put in place when removing the asbestos?

A

Answer:
- Isolate the work area using plastic sheets and clear signage.
- Ensured they were wearing suitable PPE.
- Use non-destructive methods of removal
- Used sealable containers for material and PPE.
- Taken to a licensed landfill.
- Provide air clearance cert following works.

41
Q

What is considered as licensable asbestos work?

A

Answer:
- Works on asbestos coatings, where exposure to workers is not sporadic, loose fill insulation. Works on AIB that is not a short duration.
- All licensable work must be notified via an ASB5 form at least 14 days before the work starts.

42
Q

In each of these projects, how did you prioritize client needs while ensuring adherence to safety, regulatory, and cost considerations?

A

Answer: I prioritized client needs by maintaining clear communication and understanding their goals, particularly regarding budget and timelines. Simultaneously, I ensured that all decisions complied with safety and regulatory requirements by consulting with relevant experts, such as structural engineers and asbestos specialists. I balanced these considerations by proposing cost-effective solutions, like reusing existing structures or selecting appropriate materials, while always keeping safety and compliance at the forefront of the decision-making process.

43
Q

Can you provide examples of how your recommendations directly impacted the project outcomes, particularly in terms of cost savings, safety, or compliance?

A

Answer: In the Grantham project, my recommendation to reuse the existing concrete slab resulted in significant cost savings by eliminating the need for new foundations. Similarly, in the Rotherham project, choosing SMA with a water attenuation tank provided a cost-effective yet compliant solution to the hardstanding design. For the Rugby refurbishment, my early identification of potential asbestos risk led to a safer work environment and ensured compliance with asbestos regulations, avoiding potential legal and health issues.

44
Q

How do you approach the balance between aesthetic design and practical considerations in your recommendations to clients?

A

Answer: I approach this balance by first understanding the client’s aesthetic preferences and practical needs. I then propose solutions that meet these requirements while considering factors such as budget, durability, and regulatory compliance. For example, in the Grantham project, I suggested brickwork cloaking that not only concealed the building’s underside but also matched the existing boundary wall, ensuring visual harmony while addressing practical concerns like ventilation and structural integrity.

45
Q

What lessons have you learned from these projects that you would apply to future situations involving site appraisals, material selection, or risk management?

A

Answer: One key lesson is the importance of thorough site appraisals and early identification of potential issues, such as existing structures or hazardous materials, which can significantly impact project planning and execution. I’ve also learned that clear communication with clients and consultants is crucial for making informed decisions that balance cost, safety, and design. Additionally, I’ve gained a deeper appreciation for the role of detailed planning in risk management, particularly when dealing with complex projects involving regulatory compliance.

46
Q

How do you stay up-to-date with technical standards and regulations relevant to your work, such as those concerning SuDS, modular construction, or asbestos management?

A

Answer: I stay up-to-date by regularly attending industry seminars, workshops, and webinars focused on the latest developments in construction standards and regulations. I also review updates from professional bodies like RICS, consult with experts in specific areas when needed, and participate in continuing professional development (CPD) courses. Additionally, I keep abreast of changes through industry publications and regulatory updates.

47
Q

Can you discuss how your technical knowledge influenced your decision-making process in any of the projects mentioned?

A

Answer: My technical knowledge played a crucial role in each project. For example, my understanding of SuDS informed my recommendation of a water attenuation tank in the Rotherham project, ensuring regulatory compliance while optimizing cost. In the Grantham project, my knowledge of modular construction and foundation requirements led to the innovative reuse of an existing slab

48
Q

What are weep holes

A

Weep holes in a cavity wall are small openings, typically located at the bottom of the outer leaf (the external layer) of a cavity wall, which allow water that has entered the wall cavity to escape. They are an essential feature in brick or masonry construction, designed to prevent moisture build-up within the wall and to promote proper drainage and ventilation.

49
Q

What is a cavity tray

A

A cavity tray is a waterproof barrier that directs water from the inner side of the cavity to the outer via weep holes. Generally you would find above openings.

50
Q

What is a cavity barrier

A

Cavity barriers are installed to stop fire and smoke from spreading through the cavity and into other areas of the building. They compartmentises the cavity to prevent fire spread horizontally or vertically.

51
Q

What are some different types of flat roof?

A
  • Warm flat roof.
  • Cold flat roof.
  • Inverted flat roof.
52
Q

Tell me about a warm flat roof.

A
  • Insulation above roof deck and below the waterproof membrane.
  • keeps roof deck warm, reducing risk of condensation.
53
Q

Advantages of Warm flat roof?

A

ADVANTAGES
- Continuous insulation (improved thermal efficiency).
- Reduces condensation risk.
- Continuous insulation reduces risk of cold bridging
- Flexibility to add insulation for U Values

54
Q

Disadvantages of warm flat roof?

A

DISADVANTAGES
- More expensive (more insulation)
- Can increase overall height of the roof, which may not always be suitable.

55
Q

Build up of warm flat roof?

A
  • Joists
  • Timber sub deck
  • Vapour control layer
  • Insulation
  • (optional timber deck)
  • Roof covering
56
Q

What is a cold flat roof?

A

Insulation is laid between the rafters. Not actually cold, but rafter make for cold bridging.

57
Q

Advantages of a cold flat roof?

A

ADVANTAGES
- Roofs are not as deep in height.
- Can mean higher floor to ceilings.
- Insulating between joists which would otherwise be voids.

58
Q

Disadvantages of cold flat roof?

A

DISADVANTAGES
- Prone to thermal bridging.
- Condensation risk, must be ventilated.
- Limited insulation thickness.

59
Q

Cold roof build up?

A
  • Ceiling.
  • Vapour barrier.
  • Insulation between joists.
  • Waterproofing membrane.
60
Q

What is an inverted flat roof?

A

Where the waterproofing layer is installed on top of the deck and the insulation is placed on top of this, rather than beneath it. Suitable for terrace or green roof.

61
Q

Advantages of an inverted flat roof?

A

ADVANTAGES
- Roof covering is protected.
- good thermal, entire roof deck warm.
- Flexibility, terrace, pavers, green roof.

62
Q

Disadvantages of inverted flat roof?

A

DISADVANTAGES
- Increased weight (gravel, pavers etc)
- Water resistant insulation expensive.
- Can degrade insulation if exposed to water for prolonged periods.

63
Q

Build up of inverted flat roof?

A
  • Ceiling.
  • Deck.
  • Waterproofing membrane.
  • Rigid insulation
  • Water flow reduction layer (minimise movement of water that could effect insulation)
  • Ballast or slabs etc
64
Q

Whta is a pot and beam floor?

A

Floor with clay or concrete blocks supported on parallel pre cast concrete beams.
- Good for strength and durability.
- Often high material and labour cost.
- Ventillated with telescopic vents.

65
Q

What is a timber floor?

A
  • Timber joists supported by load bearing walls.
  • Must be ventillated to prevent moisture build up.
  • Common in victorian houses.
66
Q

What is a concrete floor?

A
  • Hardcore
  • Sand binding
  • DPM
  • Concrete slab
  • Insulation
  • Vapour control layer
  • Screed
67
Q

What is the purpose of a vapour control layer and dpm in concrete floor?

A

DPM
- Prevent moisture rising through concrete slab.
- Protects the slab for damage.
- Polyethelene sheet beneath concrete.
Vapour control layer
- Prevents moisture from the building entering the structure of the floor.