Construction Design & Management (Health & Safety) Regulations 2015 Flashcards

1
Q

When is a Principle Designer required in a project?

A
  • A principle designer is required when there is more than 1 contractor expected to be involved in the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When does it become necessary to submit an F10 notification?

A

When a project matches any one of the following 3 criteria:

  • Project will last more than 30 days.
  • More than 20 workers on-site at any point.
  • The project will exceed 500 person days.