Construction Design & Management (Health & Safety) Regulations 2015 Flashcards
1
Q
When is a Principle Designer required in a project?
A
- A principle designer is required when there is more than 1 contractor expected to be involved in the project.
2
Q
When does it become necessary to submit an F10 notification?
A
When a project matches any one of the following 3 criteria:
- Project will last more than 30 days.
- More than 20 workers on-site at any point.
- The project will exceed 500 person days.