Conflict Avoidance, Management and Dispute Resolution Procedures - L1 Flashcards

1
Q

Conflict avoidance, management and dispute resolution procedures - Extract from Candidate Guide - Aug 2018 (updated Feb 2022)

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you avoid conflict?

A

The best way is to keep communication clear and constant so that all parties understand what it is that is going on and when there is a dispute, it can be effectively addressed in a fair way.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name some conflict avoidance processes?

A
  • Good Management
  • Clear Contract Documentation
  • Partnering and Alliancing
  • Good Payment Practice
  • Record Keeping
  • Regular reporting and proactivity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Partnering & Alliancing:

A

Partnering and alliancing are collaborative project management approaches in construction and other industries. Partnering promotes open communication and cooperation among project stakeholders, emphasizing trust, shared goals, and early involvement. Alliancing goes further, forming a formal partnership where risks and rewards are shared, fostering innovation and cost savings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the different techniques of conflict avoidance?

A
  • Confronting collaborative, confront the issue rather than each other
  • Compromising give and take
  • Smoothing more accommodating, involves sacrifice.
  • Forcing force your view to complete disregard of the other view
  • Avoiding postponing.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the types of Dispute Resolution?

A
  • Negotiation
  • Mediation and Conciliation
  • Expert Determination
  • Adjudication
  • Arbitration
  • Litigation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are ADR techniques?

A

This stands for Alternative Dispute Resolution and refers to any technique that is not litigation or arbitration.
Advantages of ADR:
• Speed takes less time than court proceedings following the CPR.
• Informality - outside of court.
• Greater opportunity for negotiation.
• Cost less money on professional fees that litigation.
• Quality of decision making “ as its made by experts in the field not judges.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is “JCT”?

A

JCT” refers to the “Joint Contracts Tribunal.” JCT develops standard construction contracts in the UK, outlining project terms and dispute resolution procedures. RICS professionals use these contracts as the basis for resolving construction disputes through arbitration or mediation, ensuring adherence to agreed-upon terms and industry standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does JCT recommend for ADR?

A

The methods of dispute resolution are referenced in the Articles:
• Mediation
• Adjudication (adjudicator can be named in Contract Particulars)
• Arbitration (Appointing body can be named in Contract Particulars)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a dispute/conflict?

A

When two or more parties have a difference of opinion. It can be positive or negative and lead to:
* Arguments
* Negotiation
* Dispute resolution
* Innovation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Dispute Board

A

Dispute Adjudication Board (DAB), is a specialized panel of experts in construction and dispute resolution. Its primary role is to swiftly and impartially resolve disputes that emerge during construction projects. Typically comprising three members – one appointed by the project owner, another by the contractor, and a neutral chairperson – the board reviews disputes, assesses evidence, and issues binding or non-binding decisions as per the contract terms. This process enhances transparency and fairness in conflict resolution, minimizing the need for lengthy and expensive legal proceedings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you name some of the RICS approved ADR / Ombudsman bodies ? Where would you find this information ?

A
  • Centre for Effective Dispute Resolution
  • The property Ombudsman
  • The property Redress Scheme
  • Financial Ombudsman Service
  • Local Government Ombudsman
  • Adjudicators Office
    *The New Homes Ombudsman Service: NHOS
    Contained within the RICS Guidance Note - ‘Complaints Handling’ 1st Edition 2016

RICS Conflict Avoidance and Dispute Resolution in Construction Guidance Note (2012)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you understand by Statutory?

A

Statutory Law (Statue Law) is set down by legislate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the conflict avoidance pledge CAP?

A

Five of the UKs leading professional bodies joined together to form a commitment in the construction and infrastructure sectors to prevent disputes through early communication, collaboration, and dispute avoidance mechanisms. It aims to reduce project delays and costs by fostering a cooperative environment, enhancing project success, and maintaining positive stakeholder relationships.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What statute does Arbitration sit under?

A

The Arbitration Act 1996

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who set up the property ombudsman ?

A

The scheme was underpinned by statue in 2007 (estate agents) and 2014 (letting and managing agents) and approved by the UK government to help consumers settle their disputes with property businesses such as estate agents, letting agents and property management agents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What does without prejudice mean ?

A

That it cannot be used as evidence in court proceeding or criminal proceedings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the meaning of disclosure ?

A

Relating to a mechanism allowing a party in arbitration to see a file of the other party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What if the contract doesn’t have ADR Procedures?

A

If the contract qualifies under the The Housing Grants, Construction and Regeneration Act 1996 (The Construction Act), both parties have a statutory right to adjudication. If it does not qualify, then the Scheme for Construction Contracts applies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the Scheme for Construction Contracts 2011?

A

It is a secondary piece of legislation put into contracts upon failure of compliance of the construction act. It sets out a procedure for the appointment of the adjudicator and conduct of adjudication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the responsibility of an expert witness ?

A

To provide independent, impartial, and unbiased evidence to the court or tribunal. They should have specialist skills, knowledge, or experience

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What does this Act (The Housing Grants, Construction and Regeneration Act 1996 (The Construction Act) ) require in terms of certifying contractor’s requests for payment and invoices etc?

A

There must be a “due date” for each payment; there must be a “final date” for each payment; the contract must require a “payment notice” to be given within 5 days of the due date, stating what is to be paid and the basis on which it is calculated – this can be a duty of the payer or the payee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What enforces the requirement for a building contract to contain provisions for adjudication?

A

The HGCRA Housing grants, Construction and Regeneration Act 1996. (so called Construction Act)

This act also requires the following:
* The right to be paid in interim, periodic or stage payments
* The right to be informed of the amount due, or any amounts to be withheld
* The right to suspend performance for non-payment
* The right to adjudication
* Disallowing pay when paid clauses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What changes did the Construction Act 2009 provide in terms of adjudication?

A

It allowed for verbal contracts to be protected by the same rights to adjudication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What would you consider to select a form of dispute resolution?

A
  • The cost in proportion to the claim
  • The timescales involved
  • The impact on business relationships and reputation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What court are construction disputes heard ?

A

The Technology and Construction Court (TCC) is a specialized UK court handling complex disputes in technology, construction, engineering, and infrastructure, renowned for its technical expertise. Nothing less than £250,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What does the abbreviation HGCRA strand for ?

A

Housing Grants Construction Regeneration Act 1996.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is included in the RICS Conflict Avoidance and Dispute Resolution Guidance Note (Part of the ‘Black Book’)?

A
  • Conflict avoidance processes
  • Three pillars of dispute resolution
  • Dispute resolution techniques
  • ADR
  • Standard form contracts
  • Conflict Avoidance
  • Dispute Resolution Procedures
  • Dispute Escalation Clauses
  • Interim Valuations and Claims
29
Q

What are the 3 Pillars of Dispute Resolution

A

Adjudication, mediation, and arbitration. Adjudication involves a formal third-party decision. Mediation is an informal, collaborative process facilitated by a neutral mediator. Arbitration is a semi-formal process where arbitrators render a binding decision. These methods offer varying levels of formality and control in conflict resolution.

30
Q

What Guidance do the RICS provide on Conflict of Interest?

A

RICS - Conflict of Interest Professional Standard

This document was reissued in July 2023 as a professional standard. It had previously been published in March 2017 as a Professional Statement.

Inlcudes:
Conflicts of Interest
COnfidential Information
Firm Systems and controls
Record Keeping
Informed Consent
Information Barriers
Competing bidders
Agency

31
Q

What is informed consent ?

A

When an conflict of interest has been highlighted to a client who understand and still wants to progress .

32
Q

What is a conflict of interest?

A

When a duty to act on behalf of one party is compromised or potentially compromised by the duty to act on behalf of another party which having competing interests

33
Q

What are the types of conflicts of interest?

A
  • Party Conflict – working on the same project/instruction but for two separate clients
  • Own Interest – when the duty to act on behalf of a client is compromised by your own personal interests.
  • Confidential information conflict – when you have a duty to present information to one client but have a duty to another client to keep that information confidential.
34
Q

What is a information barrier ?

A

A measure put in place as a result of a conflict on interest, to reduce the passing or access of information from within an organisation.

35
Q

How would you carry out a conflict of interest check?

A

Collate all the job details and check with colleagues and the system files if there are any competing clients. If there is a conflict, it should be disclosed to the clients and get their approval before proceeding.

36
Q

What is conflict avoidance and conflict management?

A
  • Conflict avoidance is a person’s method of reacting to conflict, which attempts to avoid directly confronting the issue at hand.
  • Conflict management is the process of limiting the negative aspects of conflict while increasing the positive aspects of conflict
37
Q

What is Mediation ?

A

Negotiations carried out with the assistance of an impartial 3rd party person who has no power to impose an outcome. The mediators role is to facilitate a decision. When an agreement has been found, the parties can sign a document to the agreement.

Advantages
* Similar to negotiation but benefit of an impartial member
* Non adversarial
* Voluntary
* Quick
* Usually inexpensive
* Flexible as parties retain control
* Mediator can make the decision if parties agree

  • Mediator does not state specialist advice
  • Can be subject to delaying tactics
  • Costs may not be recoverable if no settlement is reached.
38
Q

What is Arbitration ?

A

Private contractual from of dispute resolution. A 3rd party arbitrator or panel selected by the parties in dispute forms a decision based on material facts, documents and principles of law. The decision is legally binding and has limited rights of appeal. Legal costs are normally awarded to the successful party. It commences with a notice to concur which provides for agreement of appointment failing which, an arbitrator is appointed by a nominating body. Three procedures: Documents only – 30 days, short hearing – 30 days, full procedure – no time limit.

Advantages
• Governed by Arbitration Act 1996
• Private
• Arbitrator is usually experienced in the field
• Consensual in that the parties can decide timings etc.
• Can call on witnesses
• Outcome can amend the contract

Disadvantages
• Expensive
• Can only be appealed on point of law/jurisdiction

39
Q

Who can be an Arbitrator?

A

An expert in their own right, who acts fairly and impartially to reach a decision.

40
Q

What is Adjudication?

A
  • (Parties agree by contract to appoint a 3rd party adjudicator)(JCT)
  • Party issues notice of dispute
  • Adjudicator appointed in 7 days
  • Adjudicator has 28 days to issue decision
  • Introduced under ‘Housing Grants, Construction & Regeneration Act 1996
  • Can be overturned by Arbitration of Litigation
  • Binding and enforceable in the TCC (Technology and Construction Court)
41
Q

What are the time frames of Adjudication?

A

Can take up to 28 days to complete, this can be extended to 42 days with agreement from both parties.

42
Q

Is Adjudication binding?

A
  • Adjudication decisions are binding unless and until they are revised by subsequent arbitration or litigation after practical completion, or by agreement between the parties (hence the term ‘pay now argue later’).
  • There is no right of appeal and limited right to resist enforcement.
  • Generally, adjudicators do not have the power to award costs (other than their own fees and expenses).
  • Adjudication must adhere to strict timescales and typically takes up to 28 days.
43
Q

Under JCT how long does an adjudicator have to make his award?

A

28 days from issue of the referral notice, but this can be extended to 42 if both parties agree.

44
Q

What are the time frames of Adjudication?

A

Can take up to 28 days to complete.

45
Q

What is Litigation?

A

Lawsuit within a court of law.

Advantages
* Binding but can be appealed
* Can deal with several claims at once

~~~
Disadvantages
* Adversarial and formal
* Publicly exposed
* Expensive
* No influence over choice of judge or hearing details

46
Q

What is Litigation?

A

The courts have inherent jurisdiction to hear a dispute in respect of just about anything. Ianthe absence of any other procedure, the parties will have a right to refer their matter to an appropriate court. The procedure is governed by the Civil Procedure Rules, and the nature, complexity and value of the dispute will determine which court will hear a particular dispute. Courts have the widest jurisdiction and in addition to determining disputes and declarations, they can also issue Charging Orders, summon witnesses and involve the third parties in the dispute as necessary

47
Q

Why would you go for litigation?

A

Litigation allows you to bring multiple disputes to the table to be heard and can bring unwilling parties in.

48
Q

What are the differences between arbitration and litigation?

A

Litigation is more adversarial but allows you to address multiple disputes whereas arbitration only allows you to handle one dispute at a time. Litigation also only requires one parties consent to proceed. Litigation does not have a maximum time frame to resolve the issue. The Arbitrator is also predetermined in the contract whereas you do not get a choice of the judge assigned.

49
Q

What is the difference between Mediation and Conciliation?

A
  • Mediation is a voluntary procedure, which involves the appointment of a third party mediator, who will help to facilitate negotiations between parties. Them aim of mediation is to help the parties reach an amicable agreement.
  • Conciliation is also a voluntary procedure, which involves the appointment of a third party Conciliator. The role of the conciliator is to also facilitate negations, however the Conciliator will create a settlement proposal.
50
Q

What is the difference between arbitration and adjudication?

A
  • Arbitration is a procedure in which both sides agree to let an impartial third party, the arbitrator, decide the case
  • The arbitrator may be a lawyer, or may be an expert in the field of the dispute, or in some cases, an arbitration panel
  • The arbitrators decision, known as an award, is legally binding and can be enforced through the courts
  • Normally, there is no appeal, however there are exceptions in which appeals may be accepted
  • In adjudication, the decision is the responsibility of a third party adjudicator selected by the parties to the dispute
  • Adjudication decisions are binding unless and until they are revised by subsequent arbitration or litigation after practical completion, or by agreement between the parties (hence the term ‘pay now argue later’)
  • There is no right of appeal and limited right to resist enforcement
  • Generally, adjudicators do not have the power to award costs (other than their own fees and expenses)
  • Adjudication must adhere to strict timescales and typically takes up to 28 days
51
Q

What is the different between mediation and conciliation?

A
  • The mediator is a neutral party who help parties to rebuild business relationships and help them to work out a solution that is mutually agreeable
  • There parties are directly engaged in the discussions
  • It is non-binding and parties can revert to arbitration or litigation at any time
  • Conciliation has the same aims than mediation but the processes are different
  • The conciliator is usually a figure of authority that the parties have turned to for guidance
  • The conciliator makes suggestions and the parties make the final decisions.
52
Q

Why might you choose Arbitration over Litigation?

A
  • Arbitration is more private
  • You get control over the arbitrator and the duration.
  • The arbitrator can amend the contract
  • Arbitration deals with any disputes arising out of or in connection with the contract.
53
Q

Why Might you choose Litigation over Arbitration?

A
  • Multiple but separate disputes can be heard under the same case.
  • On a statutory basis, can bring unwilling parties into litigation
54
Q

What are the ADR measures ?

A
55
Q

What is Merrett v Babb ?

A
  • Court case in 2001
  • Babb had carried out a valuation as an employee of a company for a house purchased by Merrett
  • Valuation later found to be negligent
  • The original company no longer existed
  • Court ruled Merrett could pursue the individual – Babb – for the losses
  • Big shock in the industry
56
Q

What are the main forms of dispute resolution in order ?

A

• Mediation
Mediation involves an independent trained mediator who facilitates communication between the two parties having the dispute, with the aim of achieving a settlement or resolution. The mediator will discuss the issues and try to help the parties reach an agreement, but will generally not offer their own opinions or assessment.
• Conciliation
Conciliation is generally used for employment situations rather than commercial disputes. Conciliation is a compulsory process before an individual wishes to bring a claim to the Employment Tribunal. The conciliator will discuss the issues and try to help the parties reach an agreement, often providing their own opinion after assessing the situation and the different arguments. Their opinion may help to form a settlement or achieve a conclusion to the dispute.
• Arbitration
This is more formal than mediation, and involves a process in which the dispute is resolved by the decision of an arbitrator (a nominated third party who is qualified to handle arbitration). The arbitration process can be particularly useful in disputes which require an understanding of technical knowledge and where privacy is important (eg to avoid disclosure of commercially sensitive information) or if there is an international element (i.e. to avoid multiple legal jurisdictions). It runs as a tribunal process and decisions are binding. Many contracts will contain an arbitration clause, which requires arbitration to be used in the case of a dispute.
• Adjudication
This form of ADR is generally reserved for disputes which arise out of construction contracts. It is a relatively formal process which involves: providing a written Notice of Adjudication which sets out the brief details of the dispute; appointment of an agreed adjudicator; serving a referral notice which sets out the dispute in detail by the aggrieved party; a response to this referral notice (essentially the defence); and finally a decision being reached by the adjudicator within 28 days of the referral notice. This decision is final and binding.

57
Q

Why might you want to keep disputes out of the courts ?

A

For costs and reputational damage

58
Q

Give me some examples of the requirements of the Housing Grants and Construction Regeneration Act.

A
  • The right to adjudication
  • The right to staged payments and dates
  • The right to suspension for non-payment
59
Q

Tell me about a conflict of interest check you have carried out.

A

N/A

60
Q

What is the practice of dual agency/double dipping?

A

Dual agency, also known as double dipping in real estate, occurs when one agent or brokerage represents both the buyer and the seller in a single transaction. This can lead to conflicts of interest, as the agent must serve the best interests of both parties, potentially compromising advocacy and transparency.

61
Q

Explain the role of the Civil Procedure Rules (CPRs).

A

The Civil Procedure Rules (CPR) in the UK, established by the Royal Institution of Chartered Surveyors (RICS), govern the resolution of civil disputes related to property and land matters. These rules provide a structured framework for the conduct of litigation involving property disputes, surveys, valuations, and related issues.

62
Q

What does CPR Practice Direction 35 relate to?

A

Practice Direction 35 covers various aspects related to expert witnesses, including their appointment, duties, and the content of their reports. It also outlines the process for challenging the evidence provided by expert witnesses and the court’s role in managing and facilitating the expert witness process during litigation.

63
Q

What tribunals are you aware of and when do they get involved?

A

Lands Tribunal
An expert tribunal established by the Lands Tribunal & Compensation Act (NI) 1964. Although it is a court, it includes valuer as well as legal members. The Tribunal deals both with appeals from some other bodies and also disputes referred directly to it. Lands Tribunal examples: compensation for the compulsory purchase of land. discharge or modification of land affected by a ‘restrictive covenant’ compensation for the effect on land affected by public works.

The RICS’ Regulatory Tribunal is independently led by its Presiding Chair, Alexandra Marks CBE (Independent Member). It consists of both Independent Members and RICS Members, who form the Panels and Single Member which independently determine regulatory cases including disciplinary cases against RICS Members and Firms.

64
Q

What is a Scott Schedule and when would one be used?

A

A Scott Schedule is a document commonly used in construction and building disputes to provide a structured breakdown of the various elements of a construction project, associated costs, and the parties’ positions in a dispute. It is typically used during arbitration, litigation, or other forms of dispute resolution.

65
Q

Explain the proposed provisions of the Commercial Rent (Coronavirus) Bill.

A

Enabling relief from payment of certain rent debts under business tenancies adversely affected by coronavirus to be available through arbitration; and for connected purposes.

66
Q

What form of ADR will be used to recover commercial rent arrears due to Covid?

A

Disputes about Covid rent arrears may now be determined by arbitration. The Commercial Rent (Coronavirus) Act 2022 sets out a binding arbitration procedure for the resolution of rental disputes.

67
Q

What is the Technology & Construction Court and what is its role?

A

A specialist court, which deals principally with technology and construction disputes

68
Q

Explain what the role of the RICS Low Value Dispute Adjudication service is.

A

A simple and cost effective procedure.

The service is aimed at disputes where the amounts claimed are for £50,000 or less, and the issues in dispute are relatively uncomplicated.