Commercial Flashcards
What are Y clauses in the NEC contract?
There are three optional Y clauses:
• Option Y(UK)1: Project Bank Account
• Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
• Option Y(UK)3: Contracts (Rights of Third Parties) Act 1999. This Option should be used only in the UK. If used it limits third parties rights under the Contracts (Rights of Third Parties) Act 1999 to only those parties and rights stated in the Contract Data Part 1.
What does the first clause (10.1) in the NEC3 contract state?
‘The Employer, the Contractor, the Project Manager and the Supervisor have an obligation, not only to comply with the contract but to act in a sprit of mutual trust and co-operation.
Note: in NEC4 this has been broken into two different clauses. The first (10.1) clause states the requirements to comply with the contract. The second (10.2) requires the parties to act in a spirit of mutual trust and co-operation.
Related article: https://www.clydeco.com/blog/projects-construction/article/the-meaning-of-mutual-trust-and-cooperation-in-nec
What is the role of the Supervisor in the NEC contract?
- Responsible for quality control. This is covered by core clause 4, name ‘Testing and Defects’ in NEC3 and ‘Quality Control’ in NEC4.
- Does NOT supervise the Contractor.
- Required to keep good site diaries.
- Independent of the Project Manager.
- Has the right to instruct a search for a Defect, and the responsibility to issue the Defects Certificate.
What are the 6 main options in the NEC Engineering and Construction Contract suite?
A – Lump Sum with Activity Schedule
B – Lump Sum with Bill of Quantities
C – Target Cost with Activity Schedule
D – Target Cost with Bill of Quantities
E – Cost Reimbursable
F – Management Contract
What is a Early Warning (EWN) in the NEC contract?
‘Early warning notices, referred to in clause 16.1 of the NEC contract, are to be issued for potential problems. Both the Contractor and the Project Manager must issue an early warning as soon as either becomes aware of any matter that could possibly (not definitely):
• increase the total of the Prices.
• delay Completion.
• delay meeting a Key Date.
• impair the performance of the works in use.
• adversely affect the work of Others.
A risk reduction meetings follows the issuing of an EWN so all parties can agree the best way forward to eliminate or reduce the risk. The Project Manager revises the Risk Register to record the decisions made at each risk reduction meeting and issues the revised Risk Register to the Contractor.
EWNs are one example of how NEC embeds good project management practice in the contract in a way that makes it advantageous for parties to comply. In this instance, the impact of a compensation events can be assessed as if an EWN had been raised and the other party had mitigated accordingly (63.5).
What is the NEC Professional Services Contract used for? What are the main options?
The Professional Services Contract is tailored to providing a service, rather than doing physical construction works. The main option clauses are:
• A Priced subcontract with activity schedule
• C Target contract
• E Time based contract
• G Term contract Option
What is Defined Cost in the NEC contract?
Defined Cost includes “only amounts calculated using rates and percentages in the Contract Data (Schedules of Cost Components) and other amounts at open market or competitively tendered prices with deductions for all discounts, rebates and taxes which can be recovered”. In target costs contracts, the Contractor is only paid for defined costs incurred, minus disallowed costs and plus a fee. The fee covers overheads and profit. This would be the Price for Works Done to Date (PWDD) for NEC Option C to F contracts.
What forms the documentation of a NEC ECC contract?
The components of an NEC ECC contract are as follows:
• The form of agreement.
• The conditions of contract. This includes the main Option, any secondary option clauses (X clauses), the dispute resolution option (W clause) and any amended or additional clauses (Z clauses).
• Contract data (parts 1 and 2).
• Prices (including a schedule of cost components), activities schedules, bill of quantities.
• Works information.
• Site information.
What are the requirements for correspondence under NEC?
All communications must be in a form whereby there can be read, copied and recorded (i.e. verbal doesn’t hold any contractual weight). A notification must be communicated separately from other communications.
What is the Price for Work Done to Date (PWDD) in the NEC contract?
The price for work done to date (PWDD) varies by main option:
• Option A – The sum of the completed tasks on the Activity Schedule
• Option B – The sum of the actual measurement of items on the BoQ
• Option C to F – The sum of Defined Cost less Disallowed Cost plus Fee to date
What does the fee include in the NEC contract??
' • Profit / Head Office Overheads • Insurance Premiums • Corporation Tax • Advertising and Recruitment Costs • Sureties and Guarantees • Indirect Payments.
Why was the NEC Contract introduced? What were the aims?
- Greater flexibility, allowing the contract to be used across all engineering and construction projects.
- Numerous primary and secondary option clauses to suite the projects needs.
- Written in plain, present tense English to make it clear and simple.
- Stimulates good project management through various mechanisms.
What are the three main financial statements?
- Cash flow statement - this shows cash inflow and outflow, effectively showing the bank balance of a company.
- Profit and loss account (also known as the income statement) - this shows income generated and expenses occurred, showing the profit or loss of a company.
- Balance sheet - this shows the values of assets and liabilities, showing the net worth of a company.
What types of insurance are required under NEC?
- Insurance against loss of or damage to the works, plant or materials
- Public liability insurance
- Professional indemnity Insurance
- Contractor’s equipment loss insurance
What is in Contract Data Part 1 in the NEC contract?
’ • Details of the employer and key personnel.
• The location of the works information and site information.
• The language and law to be adopted.
• The period for reply.
• Options for adjudication / arbitration.
• Starting date / defects date / defects correction period.
• Payment details.
• Options for compensation events.
• Risk and insurance.
• Confidentiality.
• Construction operations.
• Employees.
• Intellectual property.
• Novation.
• Termination.
• Data protection.
• Force majeure (unforeseeable circumstances that prevent someone from fulfilling a contract).
• Early warning / compensation events.
• Disallowable expenses.
• The split in regards to pain/gain for target cost contracts, as well as any thresholds.
What is a Schedules of Cost Components in the NEC contract?
These provide division between reimbursable items of cost, and items deemed to be included in the Fee. The schedule does not actually constitute a schedule of costs, simply a list of cost components that the Contractor can recover directly, which are • People, • Equipment (non-permanent), • Plant & Materials (permanent), • Charges, • Manufacture & Fabrication, • Design, • Insurance.
What are the different schedules of cost components in the NEC contract?
- Schedule of Cost Components (SCC) – used with Options C, D, E and F for payment of Defined Cost and assessment of compensation events.
- Shorter Schedule of Cost Components (SSCS) – only used for assessing compensation events. This is always used for Options A and B, but also for Options C and D if the PM and Contractor agree.
What is the role of the Project Manager in NEC?
’ • Contract administrator
• Employer’s representative but acts independently
• Must be very familiar with the Contract, Works and Site Information
What are the 9 core sections of the NEC contract?
- General
- Contractor’s main responsibilities
- Time
- Testing and Defects
- Payment
- Compensation events
- Title
- Risks and insurance
- Termination