CMPM_L3_PERT CPM and PDM Flashcards
What is PERT?
Program Evaluation and Review Technique
It was developed independently in the later part of 1950’s. These two are networks. A
techniques, used for planning and coordinating large scale projects.
PERT and CPM
What is CPM?
Critical Path Method
It is a control tool for defining the parts of construction job and then putting them together in a network form.
PERT and CPM
Section_________________ requires the application of PERT/CPM technique to all projects with an estimated cost of ₽100,000 or more.
Section 6 R.A. 5979
Three Phases of PERT/CPM:
Planning
Scheduling
Control-Monitor
It is determining the relationship between the work operation and the sequence in which they are to be performed.
Planning
It is the process of translating the arrow diagram into time table of calendar days.
Scheduling
Five inputs that can be obtained in Planning phase:
- A network diagram defining the activities in the project
- The duration of activities
- Cost estimates of the activities for monitoring cost, cash flow requirements
- Resources estimates
- Trade indicators (responsibility) for activity grouping
From the Schedule Phase, there are four output that can be obtained:
- The schedule of activities in the network
- A Bar Chart or a Time Scaled Network
- A Resource Analysis
- A Cash Requirement prediction
What are the 6 schedule of activities in the network?
- The Critical Activities
- The Earliest Start date for each activity
- The Earliest Finish date for each activity
- The Latest Start date for each activity
- The Latest Finish date for each activity
- The Float which refers to the amount of extra time available for an activity
It uses actual data which includes:
- Addition to the project – this refers to the
new activities - Deletion from the project
- Changes as to duration, description, trade
indicators, cost estimates or resource
estimates - Actual starting dates
- Actual finishing dates
Control Monitor Phase
The Output Phase consist of the following:
- Time status report
- Revised schedules
- Revised Bar Charts/ Arrow Diagram or Network
- Revised resource analysis
- Revised cash flow predictions
- Cost status reports
What are the three major reasons for construction failure?
- Unbalanced organization due to lack of planning and
scheduling. - Lack of financial planning.
- Poor cost control.
This method calculates the longest path of planned activities to
logical end points or to the end of the project.
It also computes the earliest and latest time that each activity can
start and finish without making the project longer.
This process determines which activities are “critical” (i.e., on the
longest path) and which have “total float” (i.e., can be delayed
without making the project longer)
CRITICAL PATH METHOD