CMPM_L3_PERT CPM and PDM Flashcards

1
Q

What is PERT?

A

Program Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

It was developed independently in the later part of 1950’s. These two are networks. A
techniques, used for planning and coordinating large scale projects.

A

PERT and CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is CPM?

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It is a control tool for defining the parts of construction job and then putting them together in a network form.

A

PERT and CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Section_________________ requires the application of PERT/CPM technique to all projects with an estimated cost of ₽100,000 or more.

A

Section 6 R.A. 5979

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Three Phases of PERT/CPM:

A

Planning

Scheduling

Control-Monitor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

It is determining the relationship between the work operation and the sequence in which they are to be performed.

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It is the process of translating the arrow diagram into time table of calendar days.

A

Scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Five inputs that can be obtained in Planning phase:

A
  1. A network diagram defining the activities in the project
  2. The duration of activities
  3. Cost estimates of the activities for monitoring cost, cash flow requirements
  4. Resources estimates
  5. Trade indicators (responsibility) for activity grouping
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

From the Schedule Phase, there are four output that can be obtained:

A
  1. The schedule of activities in the network
  2. A Bar Chart or a Time Scaled Network
  3. A Resource Analysis
  4. A Cash Requirement prediction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 6 schedule of activities in the network?

A
  1. The Critical Activities
  2. The Earliest Start date for each activity
  3. The Earliest Finish date for each activity
  4. The Latest Start date for each activity
  5. The Latest Finish date for each activity
  6. The Float which refers to the amount of extra time available for an activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

It uses actual data which includes:

  1. Addition to the project – this refers to the
    new activities
  2. Deletion from the project
  3. Changes as to duration, description, trade
    indicators, cost estimates or resource
    estimates
  4. Actual starting dates
  5. Actual finishing dates
A

Control Monitor Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The Output Phase consist of the following:

A
  1. Time status report
  2. Revised schedules
  3. Revised Bar Charts/ Arrow Diagram or Network
  4. Revised resource analysis
  5. Revised cash flow predictions
  6. Cost status reports
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the three major reasons for construction failure?

A
  1. Unbalanced organization due to lack of planning and
    scheduling.
  2. Lack of financial planning.
  3. Poor cost control.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

This method calculates the longest path of planned activities to
logical end points or to the end of the project.

It also computes the earliest and latest time that each activity can
start and finish without making the project longer.

This process determines which activities are “critical” (i.e., on the
longest path) and which have “total float” (i.e., can be delayed
without making the project longer)

A

CRITICAL PATH METHOD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It shows the inter-dependencies among various project activities.
It has largely replaced Arrow on Node diagramming.
It represents activities as boxes that are assigned properties of the
activities they represent.

A

PRECEDENCE DIAGRAM METHOD

15
Q

Developed in the early 1960s by H.B. Zachry in cooperation with IBM.

A

PRECEDENCE DIAGRAM METHOD

16
Q

Developed in the late 1950s by Morgan R. Walker of Du Pont and
James E. Kelley, Jr. of Remington Rand

A

CRITICAL PATH METHOD

17
Q

The earliest point in time an activity can begin.

A

Early Start Time (EST)

18
Q

The earliest point in time an activity can finish.

A

Early Finish Time (EFT)

19
Q

The latest point in time the activity can begin.

A

Late Start Time (LST)

20
Q

The latest point in time an activity can finish.

A

Late Finish Time (LFT)

21
Q

The period by which an activity can shift in its timing without affecting the Early Start of any succeeding activity.

A

Free Float (FF)

22
Q

The period by which an activity can shift in its timing without affecting the relevant schedule of completion.

A

Total Float (TF)

22
Q

The longest sequence of activities from commencement to completion.

A

Critical Path

23
Q

Activities A and B can start at the same time.

A

Start-to-Start

24
Q

Activity B can finish 3 days after Activity A has finished.

A

Finish-to-Finish

25
Q

Activity B can be finished 2 days after Activity A starts.

A

Start-to-Finish

25
Q

Activity B can only start 3 days after Activity A has finished.

A

Finish-to-Start

26
Q

It is an overlap between the first and second activity. When an activity is still running and
the next activity starts.

A

Lead Time (-)

27
Q

It is defined as the delay between two activities. When one activity completes and
there is a waiting period before the second activity can start.

A

Lag Time (+)

28
Q

Activity B must start 3 days after Activity A has finished.

A

LAG TIME

29
Q

A ________________ through the network determines the earliest time each activity can
start and finish.

It also determines the Total Duration of the
Project

A

Forward Pass

29
Q

Activity B can already start 5 days before Activity A finishes.

A

LEAD TIME

30
Q

A ___________________ through the network
determines the latest time each activity can
start and finish without delaying completion of
the project.

It also helps determine the activities that can
be delayed or not.

A

Backward Pass

31
Q

DISADVANTAGES OF PDM:

A

Manual Calculation is more complicated

May produce different dates on different software

Updating and Managing change can be challenging