CJM Flashcards

1
Q

Who is responsible to make sure the site is ready to build?

A

The owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where are project warranties shown?

A

CSI division one, general conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When do addenda occur?

A

During the bid process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three types of submittals?

A

Shop drawings, material data, and samples

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who prepares the shop drawings?

A

Fabricator/manufacturer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where to document justification for rain delays?

A

In the daily report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Items to consider when having materials delivered to the job site?

A

Labor force to unload, equipment to unload, and compliance with purchase orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Jobsite space allocation identify areas for…

A

Materials delivery and storage, temporary offices, and facilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Submittals effect…

A

The project’s schedule and quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Delivery materials delivered…

A

As closest possible to installation location

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the laydown area?

A

Storage area on job site. Majority of the laydown area is used to store rebar during the first third of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the most unpredictable expense of a project?

A

The labor cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who is responsible for as built drawings?

A

The superintendent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who approves subcontractor payments?

A

The contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What might an inspector do if he discovers work being performed outside the permit?

A

He may issue a stop work notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Technical specifications effect…

A

Quality of work

17
Q

Building information modeling-efficient method…

A

To transfer info from architect to builder

18
Q

Cash flow projections relate…

A

Schedule of values to construction schedule

19
Q

Who gives payment draw request approval to the owner?

A

The architect

20
Q

During close out, the punch list is completed prior to notification of…

A

Architect and engineer

21
Q

Date of installation not included…

A

With as-builts

22
Q

Requirement for warranty listed…

A

In specifications

23
Q

Who is most likely to work with as-built drawings?

A

Project manager

24
Q

Define finish to finish relationship?

A

Used when two activities should be completed at the same time despite the fact that they might have different durations

25
Operations and maintenance training done by?
Manufacturer representative
26
How are manuals organized?
Per construction specifications institute format