Who is responsible to make sure the site is ready to build?
The owner
Where are project warranties shown?
CSI division one, general conditions
When do addenda occur?
During the bid process
What are the three types of submittals?
Shop drawings, material data, and samples
Who prepares the shop drawings?
Fabricator/manufacturer
Where to document justification for rain delays?
In the daily report
Items to consider when having materials delivered to the job site?
Labor force to unload, equipment to unload, and compliance with purchase orders
Jobsite space allocation identify areas for…
Materials delivery and storage, temporary offices, and facilities
Submittals effect…
The project’s schedule and quality
Delivery materials delivered…
As closest possible to installation location
What is the laydown area?
Storage area on job site. Majority of the laydown area is used to store rebar during the first third of a project
What is the most unpredictable expense of a project?
The labor cost
Who is responsible for as built drawings?
The superintendent
Who approves subcontractor payments?
The contractor
What might an inspector do if he discovers work being performed outside the permit?
He may issue a stop work notice