City and Guilds LvL 3 Mock paper A Flashcards

1
Q

Infrastructure?

A

Infrastructure is that apparatus whose sole purpose is to support signal transmission, whether electric, electronic, optical or radio, from one place to another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Carrier Network?

A

Carrier network is used to describe a network that carries collected high density communication signals, which have originated a various locations, between two points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

WAN?

A

Wide Area Network is a network designed to serve customers by linking remote sites together without utilising a public switched telephone network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List four classes of infrastructure that could be found in an underground environment?

A

CCTV, CATV, WAN, LAN

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List four classes of infrastructure that could be found in an overhead environment?

A

CCTV, CATV, WAN, LAN

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the role of infrastructure planning in a telecom business?

A

To determine and enable an assured pathway through survey, liaison and organisation for the cost effective provision or alteration of telecoms plant facilitating an estimate of costs, construction drawings and programming having taken into account the necessary drivers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Identify three reasons for planning?

A
  • Assuring the route
  • Accurate costing
  • Accurate programming
  • Supporting the tendering process
  • Resource/contract control
  • Budget control
  • Third party assurance
  • Meeting customer needs
  • Highlight and liaison with 3rd parties
  • Customer orders
  • Strategic planning policies
  • Effective use of maintenance budgets
  • Property/highway development schemes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Identify three drivers for planning?

A
  • Maintenance
  • Highway Development
  • Annual Charges
  • Estimates used in budgetary control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Briefly describe three important reasons why estimates are used in budgetary control?

A

A company may need to know in advance what a project will cost to budget for it to know whether undertaking the project will benefit the business and in what timescales

Cost, Benefit & Timescale

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Give one example of cost effective planning specific to an overhead network?

A
  • Calculation of pull on pole to determine whether a stay is necessary.
  • Pole siting and spacing to avoid additional poles or support techniques.
  • Pole siting to reduce disruption, signing, and guarding and enable maintenance.
  • Pole siting to enable the maximum number of houses to be served
  • Correct sizing of aerial cables to meet forecast growth over the specific period as dictated by the strategic planning policy.
  • Avoidance of private wayleaves.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Give one example of cost effective planning specific to an internal network?

A
  • Minimum tray size to meet initial demand with allowance for flux and reasonable growth.
  • Shortest route lengths achievable.
  • Sufficient outlets to meet the design specification.
  • Minimal fleeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Give two specific uses for each of the following types of survey Preliminary?

A
  • A preliminary survey is used generally as a feasibility study which may be used for:
  • Assessing broad costs to enable a company to develop a business case for a project, this may be used to give a company an indication of costs for its strategic planning policy
  • Costs for inclusion in an invitation to tender
  • A customer to budget for a future project
  • Identification of potential assured routes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Give two specific uses for each of the following types of survey Detailed?

A

will provide sufficient information to determine the optimum route for construction and will identify all engineering and 3rd party issues, allow sufficiently accurate estimate of time, quantities and work disciplines to be produced from which costs and programming can be calculated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe three ways in which third party issues can affect a project?

A
  • Private Wayleaves will need negotiation between the relevant parties; frequently these parties now include legal representation. Failure to recognise a private wayleave issue will inevitably result in a delay to project completion.
  • Additional funds are required for the legal representation of both parties, and the actual cost of the wayleave.
  • A wayleave is not transferable in ownership and a new owner may wish to renegotiate the terms for more money.
  • A private wayleave across land for instance may not be secure in so much that the owner may decide to develop the land and decide to terminate the wayleave agreement requiring that plant is removed
  • A wayleave for placing plant etc within a building will require a detailed method statement to satisfy the building owner or his/her agents
  • Frequently owners are only prepared to negotiate wayleaves for an initial cable installation and every subsequent installation is subject to additional negotiation and associated costs
  • Parish councils like to know of any potential disruptions in their parish and they have very strong contacts with the Local Authority and dignitaries such as MPs. To ignore their presence may result in delay whilst enquiries are made by their contacts
  • The new Roads and Street Works act 1991 requires that all works in the public highway are noticed and co-ordinated. Under this procedure previously noticed utility works could take priority over the project requiring deferment or route change
  • The Local Authority’s resurfacing schedule may take priority over the project especially towards the end of that Authority’s financial year, requiring deferment or route change
  • A public event may be scheduled which conflict with the project programme and the police could require deferment or route change
  • The police and the Highway Authority will have an input into the negotiation of critical junctions, which will affect costs and timescales.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Give three Acts of Parliament that need to be considered at the planning stage of an infrastructure project?

A
  • The Communications Act 2003
  • The Telecommunications Act 1984
  • The Interconnection Regulations 1997
  • Highways Act 1980
  • New Roads and Street Works Act 1991, (NRSWA)
  • Health and Safety at Work Act 1974
  • Environmental Health Act
  • Traffic management Act 2006
  • Town and County Planning Act
  • Compulsory purchase of land in England and Wales for Telecommunications Operators
  • The Telecommunications Act 1984 (para 34)
  • Describes the function of OFCOM
  • The Telecommunications Act 2003 Part 1
  • Improper use of public telecommunications systems
  • The Telecommunications Act 1984 (para 43)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give one standard that needs to be considered at the planning stage of an infrastructure project?

A
  • BS 7671:2001 Requirements for Electrical Installations (lEE Wiring Regulations 16th Edition)
  • BS 6701:2004 Telecommunications Equipment and Cabling Specification for Installation, Operation and Maintenance
  • BS EN 50174 — Parts 1, 2, & 3 — Information Technology — Cabling Installation
  • BS EN 50173-1:2002 Information Technology — Generic Cabling Systems Part 1: General Requirements and Office Areas
  • BS EN 50346 Information Technology. Cabling Installation. Testing of Installed Cabling
  • BS EN 60950-1 2002 Information Technology Equipment Safety Including Electrical Business Equipment
  • BS EN 62040-1 2003 Uninterruptible Power Systems (UPS). General Safety Requirements for UPS
  • BS EN 55022:1998 Information Technology Equipment. Radio Disturbance Characteristics
  • BS 5954-2:1985 Dimensions of Mechanical Structures of the 482.6mm (19”) Series. Specification for Cabinets and Pitches of Rack Structures
  • BS EN 5031 0:2000 Application of Equipotential Bonding and Earthing in Buildings with Information Technology Equipment
  • BS EN 50085 Cable Trunking and Cable Ducting
  • BS EN 50086 Conduit Systems
  • ISO/IEC 11801 Generic Cabling for Customer Premises
  • lSO/IEC 14763 Implementation and Operation of Customer Premises Cabling
  • BS EN 60825— BS 746-6 1989 — BS 5588-11 1997 — BS 7083 1996— BS 8888 2002— BS EN 124 1994— BS EN 12825 2001 etc.
17
Q

State how a planner interprets a Customers requirement in respect of an order from another company for additional services?

A

Many customers simply know what they would like to have, for example the number of outlets in a building, but not how to achieve the desired conclusion. It is the role of the planner to accurately translate a customer’s requirements whether internal or external, into an engineering scope of works that will meet the customer’s needs.

18
Q

State how a planner interprets a Customers requirement in respect of a highway widening scheme?

A

In the case of a highway scheme the planner must be able to fully understand the drawings especially where changes in elevation may be involved and the impact upon existing apparatus

19
Q

Give six different sources of information that a planner might use, three for each of the following infrastructure environments Internal?

A

Customer order — Customer detail — Building drawings — Equipment Specification — Customer Specification — CDM Building Manuals — As-built Records — Site Health & Safety File

20
Q

Give six different sources of information that a planner might use, three for each of the following infrastructure environments Underground?

A

Connection growth figures — Current sales activity — Maintenance fault rates — Circuit Penetration — Highway development schemes — Town or unitary development Plans — Planning applications and approvals — Local Authority resurfacing schemes — Local Authority structures list — Local Authority Co-ordination of Street Works Schedule — Traffic sensitivity street list — Public events list — Land Registry — Ordnance survey maps — Strategic Planning Policy — As-built records

21
Q

List three suitable Project Management tools that could be used to assist with the planning process?

A
  • Network diagrams
  • Work flow diagrams
  • Pert Charts
  • Planning Cycles
  • Gant Chart
22
Q

Identify one project management tool which would be most suited to planning infrastructure works and state a reason why?

A
  • Network diagrams, Work flow diagrams, Pert Charts
  • Each of the above gives a simple and effective illustration of dependent and independent elements of the work with timescales, which supports best use of resource
23
Q

Briefly explain Critical Path Analysis?

A

Critical Path Analysis highlights those tasks within a project that must be completed as programmed and gives project management an easily read picture of those elements that are flexible and which can be adjusted in the programme to transfer resources to support critical path elements delayed

24
Q

Figure 1 below shows a diagram of an Underground Duct Infrastructure. State what information is given by
(A)
136 56 467 483
0—————-0—————–0—————-0————
F6 o/s 228 2/110
Berwick avenue (B)
(C)

a) A
b) B
c) C

A

a) Centre to centre measurement
b) Number of ducts and dia
c) Chamber type and location