City and Guilds LvL 3 Mock paper A Flashcards
Infrastructure?
Infrastructure is that apparatus whose sole purpose is to support signal transmission, whether electric, electronic, optical or radio, from one place to another
Carrier Network?
Carrier network is used to describe a network that carries collected high density communication signals, which have originated a various locations, between two points
WAN?
Wide Area Network is a network designed to serve customers by linking remote sites together without utilising a public switched telephone network
List four classes of infrastructure that could be found in an underground environment?
CCTV, CATV, WAN, LAN
List four classes of infrastructure that could be found in an overhead environment?
CCTV, CATV, WAN, LAN
What is the role of infrastructure planning in a telecom business?
To determine and enable an assured pathway through survey, liaison and organisation for the cost effective provision or alteration of telecoms plant facilitating an estimate of costs, construction drawings and programming having taken into account the necessary drivers
Identify three reasons for planning?
- Assuring the route
- Accurate costing
- Accurate programming
- Supporting the tendering process
- Resource/contract control
- Budget control
- Third party assurance
- Meeting customer needs
- Highlight and liaison with 3rd parties
- Customer orders
- Strategic planning policies
- Effective use of maintenance budgets
- Property/highway development schemes
Identify three drivers for planning?
- Maintenance
- Highway Development
- Annual Charges
- Estimates used in budgetary control
Briefly describe three important reasons why estimates are used in budgetary control?
A company may need to know in advance what a project will cost to budget for it to know whether undertaking the project will benefit the business and in what timescales
Cost, Benefit & Timescale
Give one example of cost effective planning specific to an overhead network?
- Calculation of pull on pole to determine whether a stay is necessary.
- Pole siting and spacing to avoid additional poles or support techniques.
- Pole siting to reduce disruption, signing, and guarding and enable maintenance.
- Pole siting to enable the maximum number of houses to be served
- Correct sizing of aerial cables to meet forecast growth over the specific period as dictated by the strategic planning policy.
- Avoidance of private wayleaves.
Give one example of cost effective planning specific to an internal network?
- Minimum tray size to meet initial demand with allowance for flux and reasonable growth.
- Shortest route lengths achievable.
- Sufficient outlets to meet the design specification.
- Minimal fleeting
Give two specific uses for each of the following types of survey Preliminary?
- A preliminary survey is used generally as a feasibility study which may be used for:
- Assessing broad costs to enable a company to develop a business case for a project, this may be used to give a company an indication of costs for its strategic planning policy
- Costs for inclusion in an invitation to tender
- A customer to budget for a future project
- Identification of potential assured routes
Give two specific uses for each of the following types of survey Detailed?
will provide sufficient information to determine the optimum route for construction and will identify all engineering and 3rd party issues, allow sufficiently accurate estimate of time, quantities and work disciplines to be produced from which costs and programming can be calculated
Describe three ways in which third party issues can affect a project?
- Private Wayleaves will need negotiation between the relevant parties; frequently these parties now include legal representation. Failure to recognise a private wayleave issue will inevitably result in a delay to project completion.
- Additional funds are required for the legal representation of both parties, and the actual cost of the wayleave.
- A wayleave is not transferable in ownership and a new owner may wish to renegotiate the terms for more money.
- A private wayleave across land for instance may not be secure in so much that the owner may decide to develop the land and decide to terminate the wayleave agreement requiring that plant is removed
- A wayleave for placing plant etc within a building will require a detailed method statement to satisfy the building owner or his/her agents
- Frequently owners are only prepared to negotiate wayleaves for an initial cable installation and every subsequent installation is subject to additional negotiation and associated costs
- Parish councils like to know of any potential disruptions in their parish and they have very strong contacts with the Local Authority and dignitaries such as MPs. To ignore their presence may result in delay whilst enquiries are made by their contacts
- The new Roads and Street Works act 1991 requires that all works in the public highway are noticed and co-ordinated. Under this procedure previously noticed utility works could take priority over the project requiring deferment or route change
- The Local Authority’s resurfacing schedule may take priority over the project especially towards the end of that Authority’s financial year, requiring deferment or route change
- A public event may be scheduled which conflict with the project programme and the police could require deferment or route change
- The police and the Highway Authority will have an input into the negotiation of critical junctions, which will affect costs and timescales.
Give three Acts of Parliament that need to be considered at the planning stage of an infrastructure project?
- The Communications Act 2003
- The Telecommunications Act 1984
- The Interconnection Regulations 1997
- Highways Act 1980
- New Roads and Street Works Act 1991, (NRSWA)
- Health and Safety at Work Act 1974
- Environmental Health Act
- Traffic management Act 2006
- Town and County Planning Act
- Compulsory purchase of land in England and Wales for Telecommunications Operators
- The Telecommunications Act 1984 (para 34)
- Describes the function of OFCOM
- The Telecommunications Act 2003 Part 1
- Improper use of public telecommunications systems
- The Telecommunications Act 1984 (para 43)