What following project management tools will display the project workflow from start to completion and in the order in which the activities should happen?

A

A project network diagram (PND) visualizes the activities within the project from start to completion. It illustrates activities’ successors and predecessors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Clowchart, Pareto chart, or control chart are most often used in what?

A

quality control