Chapter 8 - Project Cost Management Flashcards

1
Q

Cost Management

A

Creating the cost baseline and ensuring the project stays on budget

Includes the cost of ALL project resources: HR, materials, equipment, permits, and vendors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Variable Cost

A

Costs that change as the project proceeds
Gas prices or airline tickets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fixed Cost

A

Costs that stay the same throughout the project

Location rentals, management wages, utilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Direct Cost

A

Costs that are included in the baseline

This is a cost that the project will incur, such as materials, equipment rentals, or project team wages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Indirect Costs

A

Costs that are NOT included in the budget

Sponsor’s time spent helping with the project or ink for the printer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sunk Cost

A

Amount of money that has already been serpent on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Value Engineering

A

Value analysis: finding a less costly way of doing work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Traditional vs Agile

A

Traditional: the entire budget is calculated during planning

Agile: funded incrementally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Plan Cost Management

A

Create the Cost Management Plan

Inputs: common inputs
Tools & techniques: common tools
Output: Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost Management Plan

A

How to estimate the cost of each activity, create the project budget, and monitor and control the cost of the project

Can include how to determine the level of accuracy on the estimates, and how the EVM will be used to control the cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate Costs

A

Analyze each individual activity and assign a cost to each activity

Rough Order of Magnitude (ROM): most inaccurate, range -25% to +75%
Budget estimate: better, range -10% to +25%
Definitive estimate: very accurate and is done during the later parts of the planning process, range -5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate Costs Process

A

Inputs: project management plan (cost management plan, quality management plan, scope baseline), project documents (project schedule, risk register, lessons learned register, resource requirements)
Tools & techniques: expert judgement, analogous estimating, parametric estimating, bottom-up estimating, three-point estimating, data analysis
Outputs: cost estimates (cost of each individual activity), basis of estimates (how the estimates were developed and their ranges - assumptions and constraints), project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Management Plan

A

Gives the steps needed to estimate costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Quality Management Plan

A

Steps the project team will take to ensure the project meets its quality requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Scope Baseline

A

Includes the project scope, the WBS, and the WBS dictionary
Knowing the work that needs to be done and how it will be done will affect the cost of the project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project Schedule

A

Includes the network diagram, Gantt chart, and milestone chart
Knowing how long it will take to complete each activity will affect the cost

17
Q

Risk Register

A

Used to determine the amount of reserves needed for the activities

18
Q

Resource Requirements

A

The resources needed to complete each activity will affect the duration of each activity
Includes: people, equipment, and materials

19
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project.
Top-down estimating
Quick to perform but could be very inaccurate

20
Q

Parametric Estimating

A

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters

Something multiplied by something or something divided by something

21
Q

Bottom-up Estimating

A

A method of estimating project duration or costs by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)

Very accurate, can be very complex and time-consuming

22
Q

Reserve Analysis

A

Add reserve time to cover work risks

Contingency reserves: known unknowns
Included in the cost baseline and are within the control of the project manager

Management reserves: unknown unknowns
Added to the project by the organization’s management and are not included in the project cost baseline

23
Q

Cost of Quality

A

The amount of money you spend to ensure quality requirements are met on the project

24
Q

Cost Baseline

A

The approved version of the work package cost estimates and contingency reserves. Used to measure the performance of the project.

Known as the budget at completion (BAC)

25
Q

Cost Management Plan

A

A component of the project management plan that defines how the costs will be planned and controlled

States what inputs and tools to use to create the estimated cost of each activity

26
Q

Quality Management Plan

A

A component of the project management plan that describes how an organization’s quality policies will be implemented

Steps the project team will take to ensure the project meets it’s quality requirements

27
Q

Scope Baseline

A

Includes the project scope statement, WBS, WBS dictionary
Used as the basis for comparison to actual results
Part of the project management plan

28
Q

Cost Aggregation

A

Rolling up the activity costs into work packages and then the work packages into deliverables

29
Q

Funding Limit Reconciliation

A

When the organization limits the project funding
Might result in rescheduling of the project work

30
Q

Determine Budget Process

A

Inputs: project management plan, project documents, business documents, agreements
Tools & techniques: cost aggregation, expert judgment, historical information review, funding limit reconciliation, financing
Outputs: cost baseline funding requirements

31
Q

Control Costs

A

Part of monitoring and controlling
Try to keep the project on budget
Compare the planned work (project management plan) and the actual work (work performance data)