Chapter 7 - Project Schedule Management Flashcards
Schedule Management
Includes the processes required to manage the timely completion of the project
Creating the schedule baseline, project schedule, and ensuring the project stays on schedule
Plan Schedule Management
Inputs: project management plan, project charter, enterprise environmental factors, organizations process assets
Tools & techniques: expert judgement, data analysis, meetings
Output: Schedule Management Plan
Schedule Management Plan
Document how the project defines the activities, sequences the activities, estimates the resources, developed the schedule, and controls the schedule to ensure the project stays on schedule
Measure the schedule and how to fix it if there are any variances from the schedule baseline
Part of the Project Management Plan
Define Activities
Taking the work packages on the WBS and breaking them down into activities
The specific work that will need to get done by the project team to create the deliverables
More detailed than work packages
Stored in the activities list
Define Activities Process
Inputs: project management plan (schedule management plan - list the steps to define the activities, how to decompose each work package into activities, scope baseline), enterprise environmental factors, organizational assets
Tools & techniques: decomposition (breaking down the work into activities), rolling wave planning (progressive elaboration), expert judgement (using SMEs to help decompose the work packages)
Outputs: activity list (list of all scheduled activities on the project), activity attributes (detailed information about each activity), milestones list (all project or phase milestones - major accomplishment or event), change request, Project Management Plan updates
Sequence Activities
Take the list of activities and put them in the order that you will perform them
Shows the relationship between each activity
Sequence Activities Process
Inputs: project management plan (schedule management plan), project documents (activity list, activity attributes, milestone list, assumption log), enterprise environmental factors, organizational process assets
Tools & techniques: precedence diagraming method (PDM), dependency determination, leads and lags, project management information system
Outputs: project schedule network diagrams, project documents updates
Precedence Diagraming Method (PDM)
Technique that is used to build a sequence using the activities
Activity-on-node (AON): boxes are activities, the numbers above them represent durations
Relationships
Finish-to-start (FS): most frequent, finish A then you can start B, Activity A is the predecessor and activity B is the successor
Finish-to-finish (FF): activities need to finish at the same time, activities A and B must be done simultaneously
Start-to-start (SS): activity A must start before Activity B can start
Start-to-finish (SF): activity B cannot finish until activity A has started - rarely used
Dependency Determination
Mandatory: hard logic or hard dependency, you have to finish one activity to start the next activity
Discretionary: soft logic, activities do not need to get done in a specific order
External: activities are dependent on activities outside the control of the project team (permits)
Internal: activities are dependent on activities within the control of the project team
Leads & Lags
Show an overlap or delay in schedule
Lead: an overlap between activities
Lags: delays between activities
Estimate Activity Duration Process
Inputs: project management plan (schedule management plan and scope baseline), project documents (activity list, activity attributes, assumption log, milestone list, resource calendars (availability of resources), risk register, resource break down structure (hierarchical break down of resources by their categories and types), lessons learned register, project team assignment, resource requirements), enterprise environmental factors, organizations process assets
Tools & techniques: expert judgement, analogous estimating, parametric estimating, three-point estimating, bottom-up estimating, data analysis, decision making, meetings
Outputs: duration estimates, basis of estimates
Analogous Estimating
Top-down
Relies on historical information to assign the current t duration to the activities
Quick to do, but less accurate
Parametric Estimating
Uses mathematical algorithm to calculate cost or duration
Based on historical data and variables
Can be very accurate if assumptions are correct
There-Point Estimating
Known as PERT (program evaluation and review techniques)
Optimistic: best case for the activity or least amount of time needed to complete the activity
Most likely (realistic): most likely or realistic case for the activity to be completed
Pessimistic: worst case for the activity or the longest time it would take to complete the activity
Beta Distribution
PERT
(Optimistic + 4 * realistic + pessimistic) / 6
Standard Deviation
Give a range for an estimate
(Pessimistic - optimistic) / 6