Chapter 7: Project Cost Management Flashcards

1
Q

The Project Cost Management processes are:

A

Plan Cost Management, Estimate Costs, Determine Budget, and Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define the process “Plan Cost Management”

A

The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define the process “Estimate Costs”

A

The process of developing an approximation of the monetary resources needed to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define the process “Determine Budget”

A

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define the process “Control Costs”

A

The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

True or false: On some projects, especially those of smaller scope, cost estimating and cost budgeting are tightly linked and can be viewed as a single process that can be performed by a single person over a relatively short period of time

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

True or false: One aspect of cost management is recognizing that different stakeholders measure project costs in different ways and at different times

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define “earned value management (EVM)”

A

EVM is a project management technique for measuring project performance and progress in an objective manner. It integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define “earned schedule (ES)”

A

ES is an extension to the theory and practice of EVM. Earned schedule theory replaces the schedule variance measures used in traditional EVM (earned value − planned value) with ES and actual time (AT). Using the alternate equation for calculating schedule variance ES − AT, if the amount of earned schedule is greater than 0, then the project is considered ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The schedule performance index (SPI) using earned schedule metrics is ____. This indicates the efficiency with which work is being accomplished

A

ES/AT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Projects with high degrees of uncertainty or those where the scope is not yet fully defined will always still benefit from detailed cost calculations due to frequent changes

A

False. They may not benefit from detailed cost calculations due to frequent changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The cost management plan can establish the following:

A

Units of measurement, Level of precision, Level of accuracy (tolerance), Organizational procedures links, Control thresholds, Rules of performance measurement, Reporting formats, and Additional details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A cost ______ is a quantitative assessment of the likely costs for resources required to complete the activity. It is a prediction that is based on the information known at a given point in time

A

Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Considering options like make versus buy, buy versus lease, and the sharing of resources in order to achieve optimal costs for the project, are all part of creating what?

A

Cost Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

True or false: Cost estimates should be solidified at the beginning of a project, and then reflected upon and recorded after project completion

A

False. Cost estimates should be reviewed and refined during the course of the project to reflect additional detail as it becomes available and assumptions are tested

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define “Analogous cost estimating”

A

Analogous cost estimating uses values, or attributes, of a previous project that are similar to the current project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Define “Parametric estimating”

A

Parametric estimating uses a statistical relationship between relevant historical data and other variables (e.g., square footage in construction) to calculate a cost estimate for project work. This technique can produce higher levels of accuracy depending on the sophistication and underlying data built into the model

18
Q

Define “Bottom-up estimating”

A

Bottom-up estimating is a method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes

19
Q

Using Triangular Distribution while Three-Point Estimating, what would that formula look like?

A

cE = (cO + cM + cP) / 3

20
Q

Using Beta Distribution while Three-Point Estimating, what would that formula look like?

A

cE = (cO + 4cM + cP) / 6

21
Q

Supporting detail for cost estimates may include:

A

Documentation of the basis of the estimate (i.e., how it was developed), Documentation of all assumptions made, Documentation of any known constraints, Documentation of identified risks included when estimating costs, Indication of the range of possible estimates (e.g., US$10,000 (±10%) to indicate that the item is expected to cost between a range of values), and Indication of the confidence level of the final estimate

22
Q

True or false: Cost estimates are aggregated by work packages in accordance with the WBS

A

True. Cost estimates are aggregated by work packages in accordance with the WBS. The work package cost estimates are then aggregated for the higher component levels of the WBS (such as control accounts) and, ultimately, for the entire project.

23
Q

True or false: The management reserve is not included in the cost baseline

A

True. The management reserve is not included in the cost baseline but is part of the overall project budget and funding requirements

24
Q

Define “cost baseline”

A

The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures. It is used as a basis for comparison to actual results

25
Q

Management reserves are added to the cost baseline to produce the _______

A

project budget

26
Q

True or false: Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline

A

True. The cost baseline will include projected expenditures plus anticipated liabilities

27
Q

True or false: The key to effective cost control is the management of the risks associated with costs and funding

A

False. The key to effective cost control is the management of the approved cost baseline

28
Q

Define “Earned value analysis (EVA)”

A

Earned value analysis compares the performance measurement baseline to the actual schedule and cost performance. EVM develops and monitors three key dimensions for each work package and control account: Planned value, Earned value, and Actual cost

29
Q

Define “Planned value (PV)”

A

Planned value (PV) is the authorized budget assigned to scheduled work. It is the authorized budget planned for the work to be accomplished for an activity or work breakdown structure (WBS) component, not including management reserve. This budget is allocated by phase over the life of the project, but at a given point in time, planned value defines the physical work that should have been accomplished. The total of the PV is sometimes referred to as the performance measurement baseline (PMB). The total planned value for the project is also known as budget at completion (BAC)

30
Q

Define “Earned value (EV)”

A

Earned value (EV) is a measure of work performed expressed in terms of the budget authorized for that work. It is the budget associated with the authorized work that has been completed. The EV being measured needs to be related to the PMB, and the EV measured cannot be greater than the authorized PV budget for a component. The EV is often used to calculate the percent complete of a project. Progress measurement criteria should be established for each WBS component to measure work in progress. Project managers monitor EV, both incrementally to determine current status and cumulatively to determine the long- term performance trends

31
Q

Define “Actual cost (AC)”

A

Actual cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period. It is the total cost incurred in accomplishing the work that the EV measured. The AC needs to correspond in definition to what was budgeted in the PV and measured in the EV (e.g., direct hours only, direct costs only, or all costs including indirect costs). The AC will have no upper limit; whatever is spent to achieve the EV will be measured

32
Q

How could you use variance analysis to calculate cause, impact, and corrective actions for cost vs. schedule variances?

A

(CV = EV – AC), (SV = EV – PV)

33
Q

Define “Schedule variance (SV)”

A

Schedule variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value. It is the amount by which the project is ahead or behind the planned delivery date, at a given point in time

34
Q

Define “Cost variance (CV)”

A

Cost variance (CV) is the amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost. It is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual cost (AC)

35
Q

Define “schedule performance index (SPI)”

A

It is a measure of schedule efficiency expressed as the ratio of earned value to planned value. It measures how efficiently the project team is accomplishing the work. An SPI value less than 1.0 indicates less work was completed than was planned. An SPI greater than 1.0 indicates that more work was completed than was planned. Since the SPI measures all project work, the performance on the critical path also needs to be analyzed to determine whether the project will finish ahead of or behind its planned finish date. The SPI is equal to the ratio of the EV to the PV. Equation: SPI = EV/PV

36
Q

Define “cost performance index (CPI)”

A

is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. It is considered the most critical EVA metric and measures the cost efficiency for the work completed. A CPI value of less than 1.0 indicates a cost overrun for work completed. A CPI value greater than 1.0 indicates a cost underrun of performance to date. The CPI is equal to the ratio of the EV to the AC. Equation: CPI = EV/AC

37
Q

True or false: If it becomes obvious that the BAC (Budget at Completion) is no longer viable, the project manager should consider the forecasted EAC (Estimate at Completion)

A

True

38
Q

[in the context of forecasting budget] While EVM data quickly provide many statistical EACs, only three of the more common methods are described as follows

A

EAC forecast for ETC work performed at the budgeted rate, EAC forecast for ETC work performed at the present CPI, and EAC forecast for ETC work considering both SPI and CPI factors

39
Q

Define “to-complete performance index (TCPI)”

A

It is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget

40
Q

The equation for the TCPI based on the BAC:

A

(BAC – EV) / (BAC – AC)

41
Q

Quiz yourself on the Earned Value Analysis table on page 267

A

You did good job

42
Q

Either a calculated EAC value or a bottom-up EAC value is documented and communicated to _____

A

stakeholders