Chapter 7 Project Cost Management Flashcards
EVM
Earned Value Measurement
(PV-EV)
ES
Earned Schedule
If greater than 0 project is ahead of schedule
SPI
Schedule Performance Index - ES/AT. It indicates the efficiency with which work is being accomplished.
Plan Cost Management
The process of defining how the project costs will be estimated, budgeted, managed, monitored or controlled.
Occurs early in the project to create framework for cost management processes
Cost management plan - tools, techniques, and processes to manage costs
Cost Management Plan
Component of the Project Management Plan that describes how project costs will be planned, structured and controlled. Units of measure, precision, control thresholds
Cost Estimate
Quantitative assessment of the likely costs for resources required to complete the activity. It’s accuracy will increase as the project progresses.
Bottoms Up Estimating
The cost of individual work packages or activities is estimated to the greatest level of specific detail.
Three Point Estimating
Factoring in uncertainty and risk to define an estimate range.
Triangular Distribution
CE= (cO + cM + cP)/3
Beta Distribution
CE = (cO + cM + cP)/6
Determine Budget
The process of aggregating the estimated costs of individual activities or work packages to estimate an authorized baseline.
Includes all funds authorized to execute the project.
Cost Quality
Evaluating the cost impact of additional investment in conformance vs. the cost of non-conformance
Cost Baseline
Approved version of the time-phased project budget that includes contingency reserves but excludes management reserve.
Summation of the Control Accounts = Work Packages and Contingency Reserves
Cost Aggregation
Cost estimates are aggregated by work packages in accordance with the WBS. Work package estimates are then aggregated for the higher component levels of the WBS and then ultimately the entire package.
Reserve Analysis
One of the techniques used to determine a project budget. During Reserve Analysis, a project is analyzed from a cost overruns point of view and buffers are placed in appropriate place. These buffers are called Contingency and Management Reserves