Chapter 7 Project Cost Management Flashcards

1
Q

EVM

Earned Value Measurement

A

(PV-EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

ES

Earned Schedule

A

If greater than 0 project is ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

SPI

A

Schedule Performance Index - ES/AT. It indicates the efficiency with which work is being accomplished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Plan Cost Management

A

The process of defining how the project costs will be estimated, budgeted, managed, monitored or controlled.

Occurs early in the project to create framework for cost management processes

Cost management plan - tools, techniques, and processes to manage costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Management Plan

A

Component of the Project Management Plan that describes how project costs will be planned, structured and controlled. Units of measure, precision, control thresholds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Estimate

A

Quantitative assessment of the likely costs for resources required to complete the activity. It’s accuracy will increase as the project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Bottoms Up Estimating

A

The cost of individual work packages or activities is estimated to the greatest level of specific detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Three Point Estimating

A

Factoring in uncertainty and risk to define an estimate range.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Triangular Distribution

A

CE= (cO + cM + cP)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Beta Distribution

A

CE = (cO + cM + cP)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Determine Budget

A

The process of aggregating the estimated costs of individual activities or work packages to estimate an authorized baseline.

Includes all funds authorized to execute the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Quality

A

Evaluating the cost impact of additional investment in conformance vs. the cost of non-conformance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Baseline

A

Approved version of the time-phased project budget that includes contingency reserves but excludes management reserve.

Summation of the Control Accounts = Work Packages and Contingency Reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Aggregation

A

Cost estimates are aggregated by work packages in accordance with the WBS. Work package estimates are then aggregated for the higher component levels of the WBS and then ultimately the entire package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Reserve Analysis

A

One of the techniques used to determine a project budget. During Reserve Analysis, a project is analyzed from a cost overruns point of view and buffers are placed in appropriate place. These buffers are called Contingency and Management Reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Management Reserves

A

An amount of the budget withheld for management control purposes and reserved for unforeseen work that is within the scope. It’s not included in the baseline.

17
Q

Contingency Reserve

A

Used to manage identified risks, or “known-unknown” (known = identified, unknown = risks). This reserve can be measured in either cost or time.

Not a random reserve; it is an estimated reserve based on various risk management techniques.

18
Q

Funding Limit Reconcilliation

A

The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project.

19
Q

Control Costs

A

Monitoring the status of the project to update project costs + managing changes to the baseline.

Any increase in budget must go through integrated change control.

Analyzing the relationship between the consumption of project funds and the work being accomplished

20
Q

EVA

Earned Value Analysis

A

Compares the performance measurement baseline to the actual schedule and cost performance.

21
Q

EVM

Earned Value Measurement

A

Integrates the scope baseline with cost baseline and schedule baseline to form the performance measurement baseline.

22
Q

PV

Planned Value

A

The authorized budget assigned to scheduled work. Defines the physical work that should be accomplished.

23
Q

Performance Measurement Baseline

A

Total planned value for the project

24
Q

BAC

Budget at Completion

A

The total amount budgeted for the project

25
Q

EV

Earned Value

A

The measure of work performed expressed in terms of the budget authorized for the work.

Cannot be more than Planned Value

Used to calculate % complete on a project

26
Q

AC

Actual Cost

A

The realized cost incurred for the work performed on an activity during a specific time period. Total cost incurred in accomplishing the work.

27
Q

SV

Schedule Variance

A

The measure of schedule performance expressed as the difference between Earned Value and Planned Value.

28
Q

CV

Cost Variance

A

The amount of budget deficit or surplus at a point in time. The difference b/w Earned Value and Actual Cost. Cost Variance at the end of a project is BAC-AC.

Indicates the relationship of the physical performance to costs spent.

29
Q

SPI

Schedule Performance Index

A

Measure of schedule efficiency expressed as the ratio of EV/PV.

Less than 1 = less work done
More than 1 = more work completed than planned

30
Q

CPI

Cost Performance Index

A

Measure of the cost efficiency of the budgeted resources, expressed as a ratio of EV/AC

Less than 1 = cost over-run
More than 1 = cost under-run