Chapter 6 Project Schedule Management Flashcards

1
Q

Project Schedule Model Maintenace

A

Process used to update the status and record progress of the project in the schedule model during the execution of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Activities

A

Process of identifying and documenting the specific actions to be performed to produce deliverables.

Decomposes work packages into scheduled activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Control Thresholds

A

Variance thresholds for monitoring schedule performance may be specified to indicate an agreed upon variation before action is needed

Expressed as a percentage. Deviations from the parameters estimated in the baseline plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level.

Progressive elaboration applicable to work packages, planning packages, and release planning when using Agile or Waterfall.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activity List

A

The schedule of activities required on a project

Includes an activity identifier and scope of work description for each activity in detail to ensure the team understands the work required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity Attributes

A

Extend the description of the activity by identifying multiple components associated with each activity.

Used to identify where the work is to be performed, project calendar, and type of effort involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sequence of Activities

A

The process of identifying and documenting relationships among the project activities

Key benefit is it defines the logical sequence of work to obtain the greatest efficiency given the

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project Scheduling

A

A detailed plan that requests how and when the project will deliver the products, services, results defined in the project scope and serves as a tool for communication, managing stakeholders expectations and as a basis for performance reporting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Iterative Scheduling

with Backlog

A

A form of rolling wave planning based on adaptive life cycles such as the approach for product development

Requirements documented as user stories that are refined and prioritized prior to construction

Delivers incremental value to the customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

On Demand Scheduling

A

Used in the Kanban System, based on the pull-based scheduling to limit a teams work in progress in order to balance demand against the teams delivery.

Does not rely on a schedule pulls work from backlog - a queue of work to be done ASAP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Plan Schedule Management

A

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing and controlling the project schedule.

Provides guidance on how the project schedule will be managed throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Time Boxed Periods

A

Durations during which the team works steadily towards completion of a goal.

Helps minimize scope creep.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Lags & Leads

A

Lead - Amount of time a successor activity can be advanced with respect to predecessor activity.

Lag- Amount of time a successor activity will be delayed with respect to a predecessor activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate Activity Durations

A

Process of estimating the number of work periods needed to complete individual activities w/ estimated resources.

Provides the amount of time each activity will take to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity using historical data from a previous similar project or activity

Used when there is a limited amount of info.

Not accurate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PDM

Precedence Diagramming Method

A

Technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by 1 or more logical relationships to show the sequences in which the activities are performed.

17
Q

Parametric Testing

A

Technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters

Multiplying the quantity of work by the number of labor hours per unit of work

18
Q

Three Point Estimating

A

Most Likely (tM)- Based on previous project data

Optimistic (tO) - Best case scenario

Pessimistic (tP) - Worse case scenario

19
Q

Duration Estimate

A

Quantitive assessments of the likely number of time periods that are required to complete an activity, phase or project.

20
Q

Schedule Network Analysis

A

Overarching technique used to generate the project schedule model

21
Q

Critical Path Method

A

Used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical networks path within the schedule model

22
Q

Total Float

A

The schedule flexability or amount of time that a schedule activity can be delayed or extended without delaying the project finish date

23
Q

Free Float

A

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor.

24
Q

Critical Chain

A

The critical chain method is a technique that modifies the project schedule to account for limited resources by adding duration buffers that are non-work schedule activities to maintain focus on the planned activity durations.

25
Q

Pareto Chart

A

A specific type of histogram that ranks causes or issues by their overall influence.

It assists in prioritizing corrective actions as the issues with the greatest impact are displayed in order. In addition, the Pareto chart includes an arc representing the cumulative percentage of the causes.

26
Q

Resource Leveling

A

Start and finish dates are adjusted based on resource constraints with the goal of balancing the demand.

27
Q

Resource Smoothing

A

Adjusts the activities of a schedule model so that the requirements for resources on a project do not exceed certain predefined resource limits

28
Q

What if Scenario Analysis

A

The process of evaluating scenarios to predict their effect, positive or negative on project objectives.

29
Q

Simulation

A

Models the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives.

30
Q

Schedule Compression

A

Techniques used to shorten or accelerate the schedule duration without reducing the project scope in order to meet schedule constraints.

31
Q

Crashing

A

Used to shorten the schedule duration for the least incremental cost by adding resources

32
Q

Fast Tracking

A

Schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

33
Q

Agile Release Planning

A

Provides a high level summary timeline of the release schedule (usually 3-6months) based on the product road map and the product vision for the products evolution.

34
Q

Schedule Data

A

A collection of info for describing and controlling the schedule. Milestones, activities, activity attributes

35
Q

Project Calendars

A

Identifies working days and shifts that are available for scheduled activities