Chapter 7 - Project Cost Management Flashcards
1
Q
Cost?
A
A resource sacrificed to achieve specific objective
2
Q
Project Cost Management Processes
A
- Planning cost management
- Estimating costs
- Determining the budget
- Controlling costs
3
Q
Cost Management Basic Principles
A
- Profits (revenue minus expenditure)
- Profit margin (ratio of revenue to profits)
- Life cycle costing (total cost of ownership)
- Cash flow analysis (estimated annual costs and benefits -> annual cash flow)
4
Q
Types of Costs and Benefits
A
- Tangible
- Intangible
- Direct costs
- Indirect costs
- Sunk cost
5
Q
Reserves
A
- contingency
future situations partially planned for - management
unpredictable future situations
6
Q
Cost Management Plan (includes)
A
- level of accuracy and units of measure
- organisational procedure links
- control thresholds
- rules of performance measurement
- reporting formats
- process descriptions
7
Q
Types of Cost Estimates
A
ROM (rough order of magnitude)
- 3-5 yrs before project completion, -50% to +100%
Budgetary
- 1-2 yrs out, -10% to +25%
Definitive
- >1 yr out, -5% to +10% accurate
8
Q
Cost Estimates Tools and Techniques
A
- Analogous/top-down estimates
- Bottom-up estimates
- parametric modelling
- 3-point
9
Q
Project Cost Control
A
- monitoring cost performance
- ensure only appropriate changes are included in baseline
- inform stakeholders of cost affecting changes to project
10
Q
EVM
A
- project performance measurement technique; scope, time, cost data
11
Q
EVM calculations
A
cv = ev - ac sv = ev - pv cpi = ev/ac spi = ev/pv eac (estimate at completion) = bac/cpi estimated time to complate = original time / SPI