Chapter 7 - Project Cost Management Flashcards

1
Q

Cost?

A

A resource sacrificed to achieve specific objective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Cost Management Processes

A
  • Planning cost management
  • Estimating costs
  • Determining the budget
  • Controlling costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Management Basic Principles

A
  • Profits (revenue minus expenditure)
  • Profit margin (ratio of revenue to profits)
  • Life cycle costing (total cost of ownership)
  • Cash flow analysis (estimated annual costs and benefits -> annual cash flow)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Types of Costs and Benefits

A
  • Tangible
  • Intangible
  • Direct costs
  • Indirect costs
  • Sunk cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Reserves

A
  • contingency
    future situations partially planned for
  • management
    unpredictable future situations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Management Plan (includes)

A
  • level of accuracy and units of measure
  • organisational procedure links
  • control thresholds
  • rules of performance measurement
  • reporting formats
  • process descriptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Types of Cost Estimates

A

ROM (rough order of magnitude)
- 3-5 yrs before project completion, -50% to +100%

Budgetary
- 1-2 yrs out, -10% to +25%

Definitive
- >1 yr out, -5% to +10% accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Estimates Tools and Techniques

A
  • Analogous/top-down estimates
  • Bottom-up estimates
  • parametric modelling
  • 3-point
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project Cost Control

A
  • monitoring cost performance
  • ensure only appropriate changes are included in baseline
  • inform stakeholders of cost affecting changes to project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EVM

A
  • project performance measurement technique; scope, time, cost data
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EVM calculations

A
cv = ev - ac 
sv = ev - pv 
cpi = ev/ac 
spi = ev/pv 
eac (estimate at completion) = bac/cpi 
estimated time to complate = original time / SPI
How well did you know this?
1
Not at all
2
3
4
5
Perfectly