Chapter 7 - Plans Flashcards
Define a plan (in PRINCE2)
A proposal that outlines the what, where, when, how, and who of the project as a whole. In PRINCE2, there are the following types of plans: project plan, stage plan, team plan, and exception plan
What does the development of a plan enable the project management team to assess and understand?
Why (the user’s driving requirements and the benefits they expect to realise); what (the products to be delivered and their associated acceptance criteria and quality specifications); how (the delivery method and constraints); when (the sequence and estimated duration of delivery activities); where (the locations and facilities involved in delivery and acceptance); who (the required skills and responsibilities of the project team and how they will be organised); how much (the estimated costs of the agreed products and the associated delivery and management activities); risks (that may be encountered in the course of delivery); issues (the affect the accuracy of realism of the plan)
What happens if there is no plan?
There is no point of reference against which scope, benefits, quality, risks, issues and progress can be monitored and controlled.