Chapter 7 Managing Project Impacts Flashcards
The EA process establishes the measures that are necessary to __________, __________, ___________, or __________potentially adverse impacts and, where appropriate, incorporate these into ______________________.
avoid, minimize, reduce, offset;
environmental management plans
Impact management is inherent in what stages of EA?
All of them
Impact mitigation
to make “less severe”
Strategy in EA to reduce the significance, risk, or severity of an anticipated, adverse effect.
a hierarchy of strategies from avoiding impacts to offsetting impacts that simply cannot be avoided, minimized, or restored
often by reducing the geographic extent of the impact, the magnitude of change in baseline condition, or the duration of the impact
For example, managing potentially adverse impacts to important species habitat should first consider options that ___________________________________, followed by options that ______________ habitat loss, ______________ habitat loss during project operations or at project completion, and finally, ______________ for unavoidable habitat loss. Each of these strategies is discussed below
avoid the loss of habitat;
minimize;
restoring;
compensating
Draw diagram for impact mitigation efforts
Fig 7.1 page 127
_______________ potentially adverse effects, and thus _____________ , is the most desirable approach to impact mitigation because it reduces the __________ and _________ needed to lower its severity. It also avoids potential conflict and concerns expressed by those who may ______________________.
Avoiding; preventing them from occurring.
time and financial resources
highly value the affected component .
Methods to avoid potentially adverse impacts include:
the consideration of alternative project locations to avoid impacts to sensitive habitat;
scheduling project construction activities so that they do not conflict with the timing of wildlife migration;
routing ancillary developments, such as access roads and other linear features, to avoid sensitive habitat, stream crossings, or cultural features;
construction of self-contained work camps to avoid potentially negative socio-economic effects caused by site worker–community interaction.
impact avoidance
A form of impact management whereby impacts are avoided at the outset by way of alternative project designs, timing, or location rather than managed or mitigated after they occur.
Impact Avoidance should enter the EA equation ____________.
should enter the EA equation early, since most impact avoidance opportunities are presented early in project design processes through alternative locations of project infrastructure or project design options.
Ecoducts for Avoiding Wildlife Collisions, Northern Sweden
The construction of ecoducts, also called wildlife bridges or wildlife overpasses, is an impact avoidance strategy in areas where wildlife collisions or disruptions to wildlife corridors or crossings are of concern. The image below shows an ecoduct near the LKAB iron ore mine in Kiruna, Norbotten County, northern Sweden. Operating for more than 100 years, the Kiruna mine is one of the world’s largest underground iron ore mines. The mine’s operations also have a significant surface footprint in an area that has traditionally been used by Sami Indigenous people for reindeer herding. Today, only about 10 per cent of Swedish Sami earn a living from reindeer husbandry, following the herd during its annual migration. The mine, coupled with other land uses, creates a bottleneck for herders when reindeer move between summer and winter pastures and poses high risk for collisions at road and railway crossings. This ecoduct and fence line were constructed at the mine site along the herding route to facilitate the movement of reindeer, minimize habitat fragmentation, and avoid collisions with railway traffic.
Buffer zones
An area of undisturbed environment, usually separating a project’s actions or disturbance from background conditions such as a riparian buffer zone.
a common mitigation strategy to minimize sediment loading in streams. While buffer zones and setbacks do not fully prevent erosion or surface runoff from occurring, they do reduce the severity of sediment loading or contamination to aquatic environments caused by runoff.
Restoration
An impact management action focused on restoring environmental quality, rehabilitating certain environmental features, repairing ecological functions, or restoring environmental components to varying degrees.
The objective is to return it to a more desirable condition compared to the state created by project actions. It won’t always be returned to the same pre-disturbance use.
Provide an example of restoration
For example, in cases where the construction of a project requires clearing the vegetated landscape and destruction of important species habitat, impact management efforts can focus on restoring the landscape during project operations or post-operation to resemble the pre-disturbed state or function.
Remediation
The process of post-industrial or post-development site cleanup, which typically involves the removal of contaminants or pollution from soil and water; a part of restoration
Reducing contamination levels of a site to safe levels within the ecosystem to protect human health and to restore certain land uses and hydrological functions
An emerging problem in Canada, and internationally, is the increasing amount of ______________project infrastructure and _______________ with no clear party responsible for __________________________.
abandoned project infrastructure and contaminated project sites with no clear party responsible for remediation or reclamation