Chapter 7: Bidding and estimating Flashcards

1
Q

When deciding whether to bid on a project, an estimator must consider all of the following EXCEPT?

Can the company breakeven on this project?

radio_off.png radio_off.png
How will project risks be managed?

radio_off.png radio_off.png
Does this project match our expertise?

radio_off.png radio_off.png
Special site conditions

A

Can the company break even on the project?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which is NOT a common phase of construction?

Punch list

radio_on.png radio_off.png
Post-construction

radio_off.png radio_off.png
Construction

radio_off.png radio_off.png
Pre-construction

A

punch list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When preparing an accurate cost estimate, if there is a conflict between the specifications and applicable codes, the contractor must follow:

A

The stricter of the two

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The document in a bid package that describes how the bid should be completed and submitted is the:

A

bid instructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If changes are made to a bid package before the bids are due, the change is referred to as:

A

an addendum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An unresponsive (or non-responsive) bid means:

A

the bid is rejected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If a general contractor approaches another subcontractor (other than the subcontractor ‘s bid he used to win the bid), discloses the bid to the new subcontractor and asks the new sub to submit a lower bid after the project has been awarded, the general contractor’s action is technically referred to as:

A

bid shopping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly