Chapter 6 - Time Flashcards

1
Q

What happens in the Define Activities process group?

A

We identify the specific actions necessary to produce the project deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are activities?

A

They are the project work packages that are decomposed into smaller components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the inputs to Define Activities?

A

Scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the tools and techniques of Define Activities?

A
  1. Decomposition
  2. Rolling wave planning
  3. Templates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is decomposition?

A

Subdividing the project work packages into smaller packages called activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is rolling wave planning?

A

A form of progressive elaboration whereby the work to be accomplished in the near term is planned while future work is planned in less detail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are outputs of Define Activities?

A
  1. Activity list
  2. Activity attributes
  3. Milestone list
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the activity list that is an output of Define Activities?

A

A list of all of the scheduled activities required for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the activity attributes that is an output of Define Activities?

A

It extends the description of the activity by identifying more information (can include things like activity description, resource requirements, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Sequence Activities process group?

A

It identifies and documents the relationship between project activities. The focus is to arrange the activities in an order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the inputs to Sequence Activities?

A
  1. Schedule Management Plan
  2. Activity list
  3. Activity attributes
  4. Milestone list
  5. Project scope statement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the tools and techniques to Sequence Activities?

A
  1. Precedence Diagramming Method (PDM)
  2. Dependency determination
  3. Leads and lags
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the 4 types of dependencies (AKA logical relationships) in the PDM and what do they represent?

A
  1. Finish to Start
  2. Finish to Finish
  3. Start to Start
  4. Start to Finish
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the 3 dependency determinations?

A
  1. Mandatory
  2. Discretionary
  3. External
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Explain the difference between the 3 dependency determinations?

A

Mandatory (AKA hard logic) – required constraint, often involve physical limitations (i.e. foundation before the walls)
Discretionary (AKA soft logic, preferred logic) – constraint based on lessons learned or best practices, but not required. Project Manager or Project Team determines this dependency. (i.e. need plumbing and electrical work finished before the dry wall is installed (a mandatory dependency between the first two activities and the dry wall installation). But, it is not necessary to do the plumbing first and the electrical second, or at the same time. They can be done in any order as long as they are completed before the dry wall installation. The project team decides the order while developing the schedule.
External – constraint involving something out of your control. (i.e. government regulations, suppliers)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Explain the difference between the 3 dependency determinations?
What is a lead? (coding might start before design finished)

A

An accelerant that allows one activity to begin before its successor is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a lag? (wait 3 days after pouring concrete)

A

A delay between activities (Lag is a drag)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the outputs of Sequence Activities?

A

What are the outputs of Sequence Activities?

Project schedule network diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a network diagram and when is it used?

A

It’s a schematic showing how project activities are connected and how the project flows

Used to evaluate schedule compressions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the 2 network diagramming methods?

A
  1. Precedence Diagramming Method (PDM) – activity on nodes (AON)
  2. Arrow Diagramming Method (ADM) – activity on arrow (AOA), dummy activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is GERT?

A

Graphic Evaluation Review Technique (GERT) – allows loops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What happens in the Estimate Activity Resources process group?

A

Estimate the type and quantities of resources to perform each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the inputs to Estimate Activity Resources?

A
  1. Schedule Management Plan
  2. Activity list
  3. Activity attributes
  4. Resource calendars
  5. Risk Register
  6. Activity Cost Estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are resource calendars?

A

They define what resources are available and when

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the tools and techniques to Estimate Activity Resources?

A
  1. Expert Judgment
  2. Alternatives analysis
  3. Publishing estimating data
  4. Bottom up estimating
  5. Project management software
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is bottom up estimating?

A

Estimates are prepared at the lower, more detailed level and then aggregated up to complete all of the activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are the outputs to Estimate Activity Resources?

A

What are the outputs to Estimate Activity Resources?

  1. Activity resource requirements
  2. Resource breakdown structure – shows the resources to be used, organized by their category type.
  3. Project document updates.
28
Q

What happens in Estimate Activity Durations?

A

Estimate the number of work periods needed to complete the activities

29
Q

What are the inputs to Estimate Activity Durations?

A
  1. Schedule Management Plan
  2. Activity list
  3. Activity attributes
  4. Activity resource requirements
  5. Resource calendars
  6. Project scope statement
  7. Risk Register
  8. Resource Breakdown Structure
30
Q

What are the tools and techniques to Estimate Activity Durations?

A
  1. Expert Judgment
  2. Analogous estimating
    3 Parametric estimating
  3. 3-point estimating
  4. Group decision making techniques
  5. Reserve analysis
31
Q

What is analogous estimating?

A

Relies on historical information and expert judgment

32
Q

Relies on historical information and expert judgment

What is the advantage and disadvantage of using analogous estimating?

A

Advantages: less costly and time-consuming, can be used when you don’t have much details

Disadvantages: less accurate

33
Q

What is parametric estimating? (average to replace a muffler is 3 hours)

A

Uses statistical relationship between historical data and other variables

34
Q

What is 3-point estimating (AKA PERT)?

A

Factors in uncertainty and risk to improve estimates (most likely, optimistic, pessimistic)

35
Q

What is the PERT Estimate formula? (AKA beta distribution or weighted formula)

A

= (P+4M+O)/6

36
Q

What is the PERT standard deviation formula?

A

= (P-O)/6

37
Q

What is the triangular distribution formula?(AKA simple)

A

= (P+M+O)/3

38
Q

What does reserve analysis provide?

A

Contingency reserve

39
Q

What are the outputs to Estimate Activity Durations?

A
  1. Activity duration estimates

2. Project document updates

40
Q

What is the critical path?

A

The longest path in the project

41
Q

What is slack ? (same as float)

A

The amount of time the activity/project can be delayed without delaying the next activity or project

42
Q

What happens in Develop Schedule?

A

Create the project schedule

43
Q

What are the inputs to Develop Schedule?

A
  1. Schedule Management Plan
  2. Activity list
  3. Activity attributes
  4. Project schedule network diagrams
  5. Activity resource requirements
  6. Resource calendars
  7. Activity duration estimates
  8. Project scope statement
  9. Risk Register
  10. Project staff assignments
  11. Resource breakdown structure
44
Q

What are the tools and techniques to Develop Schedule?

A
  1. Schedule network analysis
  2. Critical path method
  3. Critical chain method
  4. Resource optimization techniques
  5. Modeling techniques
  6. Leads/lags
  7. Schedule compression
  8. Scheduling tools
45
Q

How much float does the critical path have?

A

Zero

46
Q

What does the critical path represent?

A

The greatest project risk

47
Q

What are the 3 types of slack?

A
  1. Free slack – the latest an activity can start without delaying its successor
  2. Total slack – the latest an activity can start without delaying the project
  3. Project slack – the amount of time the project can be delayed without delaying the customer’s completion date
48
Q

What are 2 schedule compression techniques?

A
  1. Crashing – more people on critical path

2. Fast tracking – adjusting sequential activities to run in parallel to accelerate completion

49
Q

What is the disadvantage of crashing?

A

Increases cost

50
Q

What is the disadvantage of fast tracking?

A

Increases risk

51
Q

Does schedule compression change the project scope?

A

No

52
Q

What is resource leveling?

A

Keeps resource usage at a constant level

53
Q

What is the disadvantage of resource leveling?

A

Usually pushes out the overall finish date

54
Q

The most common modeling technique (what-if scenario analysis) is …

A

Monte Carlo analysis

55
Q

What does modeling analysis (what-if scenario analyzing) do for a project?

A

Assesses the feasibility of a project schedule and helps prepare contingency plans

56
Q

What are the outputs to Develop Schedule?

A
  1. Schedule baseline
  2. Project schedule
  3. Schedule data
  4. Project calendars
  5. Project Management Plan updates
  6. Project documents updates
57
Q

What is the most common bar chart used in project management and why is it used?

A

The Gantt Chart used to track day-to-day details of the project

58
Q

When would you use a milestone chart?

A

For executive reporting

59
Q

What is the duration of a milestone?

A

Zero. It is only a significant point or date in the project.

60
Q

The Resource Breakdown Structure shows …

A

A hierarchical representation of resources by category and type.

61
Q

What is the Control Schedule process group?

A

It monitors the status of the schedule and manages changes to the schedule baseline

62
Q

What are the inputs to Control Schedule?

A
  1. Project Management Plan
  2. Project schedule
  3. Work performance data
  4. Project calendars
  5. Schedule data
  6. Organizational process assets
63
Q

What does the performance review of Control Schedule comprise?

A
  1. Trend analysis (Project slowing down or moving ahead of schedule).
  2. Critical path method (review CP).
  3. Critical chain method (buffer analysis).
  4. Earned Value Management (EVM)
  5. Schedule Performance Index (SPI)
  6. Schedule variance (SV)
64
Q

What is the formula for SPI?

A

= EV/PV

65
Q

What is the formula for SV?

A

= EV - PV

66
Q

What are the outputs to Control Schedule?

A
  1. Work Performance Information
  2. Schedule forecasts
  3. Change requests
  4. Updates – Project Management Plan, project documents, OPAs