Chapter 6 - Time Flashcards
What happens in the Define Activities process group?
We identify the specific actions necessary to produce the project deliverables
What are activities?
They are the project work packages that are decomposed into smaller components
What are the inputs to Define Activities?
Scope baseline
What are the tools and techniques of Define Activities?
- Decomposition
- Rolling wave planning
- Templates
What is decomposition?
Subdividing the project work packages into smaller packages called activities.
What is rolling wave planning?
A form of progressive elaboration whereby the work to be accomplished in the near term is planned while future work is planned in less detail
What are outputs of Define Activities?
- Activity list
- Activity attributes
- Milestone list
What is the activity list that is an output of Define Activities?
A list of all of the scheduled activities required for the project
What is the activity attributes that is an output of Define Activities?
It extends the description of the activity by identifying more information (can include things like activity description, resource requirements, etc.)
What is the Sequence Activities process group?
It identifies and documents the relationship between project activities. The focus is to arrange the activities in an order.
What are the inputs to Sequence Activities?
- Schedule Management Plan
- Activity list
- Activity attributes
- Milestone list
- Project scope statement
What are the tools and techniques to Sequence Activities?
- Precedence Diagramming Method (PDM)
- Dependency determination
- Leads and lags
What are the 4 types of dependencies (AKA logical relationships) in the PDM and what do they represent?
- Finish to Start
- Finish to Finish
- Start to Start
- Start to Finish
What are the 3 dependency determinations?
- Mandatory
- Discretionary
- External
Explain the difference between the 3 dependency determinations?
Mandatory (AKA hard logic) – required constraint, often involve physical limitations (i.e. foundation before the walls)
Discretionary (AKA soft logic, preferred logic) – constraint based on lessons learned or best practices, but not required. Project Manager or Project Team determines this dependency. (i.e. need plumbing and electrical work finished before the dry wall is installed (a mandatory dependency between the first two activities and the dry wall installation). But, it is not necessary to do the plumbing first and the electrical second, or at the same time. They can be done in any order as long as they are completed before the dry wall installation. The project team decides the order while developing the schedule.
External – constraint involving something out of your control. (i.e. government regulations, suppliers)
Explain the difference between the 3 dependency determinations?
What is a lead? (coding might start before design finished)
An accelerant that allows one activity to begin before its successor is complete
What is a lag? (wait 3 days after pouring concrete)
A delay between activities (Lag is a drag)
What are the outputs of Sequence Activities?
What are the outputs of Sequence Activities?
Project schedule network diagrams
What is a network diagram and when is it used?
It’s a schematic showing how project activities are connected and how the project flows
Used to evaluate schedule compressions
What are the 2 network diagramming methods?
- Precedence Diagramming Method (PDM) – activity on nodes (AON)
- Arrow Diagramming Method (ADM) – activity on arrow (AOA), dummy activities
What is GERT?
Graphic Evaluation Review Technique (GERT) – allows loops
What happens in the Estimate Activity Resources process group?
Estimate the type and quantities of resources to perform each activity
What are the inputs to Estimate Activity Resources?
- Schedule Management Plan
- Activity list
- Activity attributes
- Resource calendars
- Risk Register
- Activity Cost Estimates
What are resource calendars?
They define what resources are available and when
What are the tools and techniques to Estimate Activity Resources?
- Expert Judgment
- Alternatives analysis
- Publishing estimating data
- Bottom up estimating
- Project management software
What is bottom up estimating?
Estimates are prepared at the lower, more detailed level and then aggregated up to complete all of the activities