Chapter 6 - Energy and Atmosphere Flashcards
Potential consequences of global climate change:
- rising sea levels leading to coastal floods
- severe droughts
- heat waves
- disease migration
Conventional fossil-based generation of electricity releases:
- Carbon dioxide
- Contributes to global climate change
Coal-fired electric utilities emit:
- Nitrogen oxide: key element in smog
- Sulfur dioxide: key element of acid rain
- Contributes to disruption of habitat and devastate landscapes
Natural gas is major source of:
Nitrogen oxides and greenhouse gas emissions
E&A credits focus on:
reducing energy use and demand and encouraging energy accountability and renewable energy
What is the Fundamental Commissioning and Verification intent?
To support the design, construction, and eventual operation of a project that meets the owner’s project requirements (OPR) for energy, water, indoor environmental quality, and durability
What is commissioning?
Is the process of verifying and documenting that a building and all of its systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the owner’s project requirements
What is an Owner’s project requirements (OPR)?
Is a written document that details the ideas, concepts, and criteria determined by owner to be important to the success of the project.
What does the OPR details?
It details the functional requirements of a project and the expectations of how it will be used and operated
What issues does the OPR addresses?
- Owner and User requirements: primary purpose, program, and use of the proposed project
- Goals: program needs, future expansion, flexibility, quality of materials, sustainability goals
Benefits of Commissioning:
- Reduced energy use
- Lower operating costs
- reduced contractor callbacks
- better building documentations
- improved occupant productivity
- verification of systems performance according to OPR
- improves energy efficiency by 5-10%
Cost of commissioning:
- may add 1% total project cost. Savings far outweigh this cost
- For existing buildings: $0.72/ft2, whole-building energy savings of 15% and payback time of 0.7 years
- For new constructions: $1.00 (0.6% of total construction costs), payback time of 4.8 years
Fundamental Commissioning and Verification prerequisites:
- Complete commissioning (Cx) process activities for MEP and renewable every systems and assemblies. According to ASHRAE Guideline
- Develop the OPR
- Develop a BOD
What is BOD?
Basis of Design is a written document that includes design information necessary to accomplish the OPR
What does the BOD include?
- Primary design assumptions: space use, climatic design conditions, space zoning, occupancy
- Standards: codes, guidelines, regulations
- Narrative descriptions: performance criteria of MEP and other systems that are to be commissioned
When should the BOD be completed?
By the Design team prior to the approval of contractor submittals of any commissioning equip. or system.
Commissioning plan is:
a document that outlines the organization, schedule, allocation of resources, and documentations requirements of the commissioning process. Plan to assign responsibilities and tasks
Commissioning authority (CxA) responsibilities:
- Review OPR, BOD, and project design
- Develop and implement a Cx plan
- Confirm incorporation of Cx requirements into the construction documents
- Develop construction checklist
- Develop system test procedure
- Verify system test execution
- Maintain issues and benefits log throughout the Cx process
- prepare final Cx process report
- Document all findings and recommendations and report directly to the owner
Current Facilities Requirements and Operations and Maintenance Plan must include:
- sequence of operation for the building
- building occupancy schedule
- equipment run-time schedule
- setpoints for all HVAC equip.
- set lighting level thruout the building
- minimum outside air requirement
- any change in schedules or setpoints for diff. seasons, days of the week, and times of day
- system narrative describing the mech. and elec. systems and equipment
- preventive maintenance plan
- commissioning program that includes periodic commissioning requirements, ongoing commissioning tasks, and continuous tasks for critical facilitites
CxA qualifications:
- Must have experience on 2+ building projects with similar scope.
- Must not be part of the project neither in the design or construction team
Enhanced commissioning (ECx) intent:
To further support the design, construction, and eventual operation of a project that meets the OPR for energy, water, indoor environmental quality, and durability
Additional CxA responsibilities in ECx:
- Gets involved early in the conceptual design and finishes late in the construction phase.
- review contractor submittals
- verify inclusion of systems manual requirements in CDs
- verify inclusion of operator and occupant training requirements in CDs
- verify systems manual updates and delivery
- verify operator and occupant training delivery and effectiveness
- verify seasonal testing
- review building operations 10 months after substantial completion. Warranty is still valid for many equip. and systems
- develop on-going commissioning plan
FCx vs ECx :
ECx covers all FCx plus:
- Review contractor submittals
- CxA participation in the design and construction phases
- CxA provides operational training
- Review building operations 10 months after completion
- Measurement and Verification of the commissioning plan
- Envelope Commissioning
Retro-commissioning is:
commissioning process that can be performed on existing buildings. Usually occurs at least one year after the building has been occupied