Chapter 6-7 Flashcards

1
Q

Activity

A

an element of the project that consumes time such as work or waiting (waiting for approval, contracts to be signed, parts or materials to arrive). It may or may not require resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Merge Activity

A

an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it-aka it’s an important activity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Parallel Activities

A

Activities that can occur at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Path vs. Critical Path

A

Path- a sequence of connected, dependent activities

Critical Path- the path with the longest duration through the network, is something is delayed the project still requires the same time just has a different order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Burst Activity

A

this activity has one or more activity immediately following it (other activities can be done till after this one is completed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sensitivity

A

the likelihood the original critical paths will change once the project is initiated (non critical activities are labeled insensitive)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Laddering

A

working on anything that can be done at one time during the same time period to complete more activities faster. (this is also called concurrent engineering)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Free Slack or Float

A

Free Slack is the amount of time an activity can be delayed without affecting any activities following it. OR free slack can be the amount of time an activity can exceed its early finish date without affecting the early start date of following activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lag

A

A Lag is the minimum amount of time a dependent activity must be delayed to begin or end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Finish to Start Relationship

A

There are situations in which the next activity in a sequence must be delayed even when the preceding activity is complete. For example when you’ve made a YouTube video for a sponsor even though the video is complete you have to wait for the sponsors approval before posting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Start to Start Relationship

A

Activity Q cannot begin until 5 time units after activity P begins, therefore you assign a lag of five time units to activity Q.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Finish to Finish Relationship

A

The completion of one activity depends on the when another activity is done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Start to Finish Relationship

A

this relationship represents situations in which the finish of an activity depends on the start of another activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Hammock Activities

A

This type of activity derives its name because it spans over a segment of a project. Examples of hammock activities are Inspection Services, Consultants, or construction Management Services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The Risk Management Process

A
  1. Risk Identification- analyze the project to identify sources of risk
  2. Risk Assessment- access the risks in terms of severity of impact, likelihood of occurring, and controllability
  3. Risk Response Development- develop a strategy to reduce possible damage, develop contingency plans
  4. Risk Response Control- implement risk strategy, monitor and adjust plan for new risks, change management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Risk Breakdown Structures

A

Organizations use risk breakdown structures (RBS) in conjunction with work breakdown structure (WBS) to help management teams identify and eventually analyze risks.

17
Q

Risk Profile

A

a list of questions that address traditional areas of uncertainty on a project. These questions have been developed and refined from previous similar projects.

18
Q

Scenario analysis

A

The easiest and most commonly used technique for analyzing risk. Team members assess the significance of each risk event in terms of probability and impact.

19
Q

Failure Mode and Effects Analysis or FMEA

A

extends the risk severity matrix by including ease of detection in the equation

impact * probability * detection = risk value

20
Q

Two strategies for mitigating risk

A
  1. reduce the likelihood that the event will occur

2. reduce the impact the event would have on the project

21
Q

Risk avoidance

A

changing the project plan to eliminate the risk or condition.

22
Q

Risk Transfer

A

passes the risk onto another party, this transfer does not change the risk, and results in paying a premium for the exemption.

23
Q

Contingency plan

A

an alternative plan that will be used if a possible foreseen risk event becomes a reality. A contingency plan represents actions that will reduce or mitigate the negative impact of the risk of event.

24
Q

Types of Risks

A
  1. Technical
  2. Schedule
  3. Cost
  4. Funding
25
Q

Positive Risk or Opportunity

A

an event that can have a positive impact on project objectives (unusually favourable weather can speed up a construction project)

26
Q

Responses to Opportunities

A

Exploit- this task seeks to eliminate the uncertainty associated with an opportunity to ensure it happens.

Share- the strategy involves allocating some or all of the ownership of an opportunity to another party who is best able to capture the opportunity for the benefit of the project.

Enhance- the opposite of mitigation in that action is taken to increase the probability and/or the positive impact of an opportunity

Accept- accepting an opportunity is being willing to take advantage of it if it occurs, but not taking action to pursue it.

27
Q

Budget Reserves

A

set up to cover identified risks, these reserves are those allocated to specific segments or deliverables of the project

28
Q

Management Reserves

A

set up to cover unidentified risks and are allocated to risks associated with the total project

29
Q

Risk Register

A

details all identified risks, including descriptions, category, and probability of occurring, impact, responses, contingency plans, owners and current status.