Chapter 6-7 Flashcards
Activity
an element of the project that consumes time such as work or waiting (waiting for approval, contracts to be signed, parts or materials to arrive). It may or may not require resources.
Merge Activity
an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it-aka it’s an important activity)
Parallel Activities
Activities that can occur at the same time
Path vs. Critical Path
Path- a sequence of connected, dependent activities
Critical Path- the path with the longest duration through the network, is something is delayed the project still requires the same time just has a different order
Burst Activity
this activity has one or more activity immediately following it (other activities can be done till after this one is completed)
Sensitivity
the likelihood the original critical paths will change once the project is initiated (non critical activities are labeled insensitive)
Laddering
working on anything that can be done at one time during the same time period to complete more activities faster. (this is also called concurrent engineering)
Free Slack or Float
Free Slack is the amount of time an activity can be delayed without affecting any activities following it. OR free slack can be the amount of time an activity can exceed its early finish date without affecting the early start date of following activities.
Lag
A Lag is the minimum amount of time a dependent activity must be delayed to begin or end.
Finish to Start Relationship
There are situations in which the next activity in a sequence must be delayed even when the preceding activity is complete. For example when you’ve made a YouTube video for a sponsor even though the video is complete you have to wait for the sponsors approval before posting.
Start to Start Relationship
Activity Q cannot begin until 5 time units after activity P begins, therefore you assign a lag of five time units to activity Q.
Finish to Finish Relationship
The completion of one activity depends on the when another activity is done.
Start to Finish Relationship
this relationship represents situations in which the finish of an activity depends on the start of another activity
Hammock Activities
This type of activity derives its name because it spans over a segment of a project. Examples of hammock activities are Inspection Services, Consultants, or construction Management Services.
The Risk Management Process
- Risk Identification- analyze the project to identify sources of risk
- Risk Assessment- access the risks in terms of severity of impact, likelihood of occurring, and controllability
- Risk Response Development- develop a strategy to reduce possible damage, develop contingency plans
- Risk Response Control- implement risk strategy, monitor and adjust plan for new risks, change management