Chapter 5 Flashcards
Learning curves
each time the output quantity doubles, the unit labour hours are reduced at a constant rate; also called the improvement curve, experience curve, and industrial progress curve.
Delphi Method
A group decision process about the likelihood that current events will occur
Planning Horizon
estimates of current events are closer to 100% accuracy, the further away an event the the less accurate the estimate.
Factors influencing Quality of Estimates
- Planning Horizon
- Project Complexity
- People
- Project Structure and organization
- Padding Estimates
- Organization culture
- Other Factors (Non-project factors can influence time or cost estimates; example: equipment failure. Project priority can influence resource assignment and thus impact time and cost)
Tips for Estimating
- Responsibility (Estimates should be made by those most familiar with the task)
- use multiple people to estimate
- assume normal conditions
- time units (all estimates need to share a consistent time unit- days, hours, shifts)
- Independence (estimate each task, not a whole section)
- Contingencies (Work package estimates should not include allowances for contingencies.)
- Adding risk assessment to the estimate helps to avoid surprises to stakeholders
Top-Down Estimates
derived from someone who uses experience or information to determine the project duration and total cost.
sometimes these estimates made by top management who have very little knowledge of the component activities used to complete the project. (sometimes called Parametric)
Bottom-Up Estimates
project estimates come from people who have knowledge of the tasks
Bottom-Up Estimate Methods
- Template Methods
- Parametric Procedures
- Range Estimating
- Phase Estimating
Phase Estimating
A detailed estimate is developed for the immediate phase and a macro estimate is made for the remaining phases of the project. Once the first phase is coming to a close a detailed estimate of the next phase is developed, and so on until all the phases are complete
Range Estimating
Acquire 3 time estimates low, average and high. The low to high provides a range that the average estimate will fall between. Determining the low to high estimates for the activity is influenced by factors such as complexity, technology, newness, familiarity and typically done with a group of people.
Parametric Procedures
Same as parametric techniques such as cost per square foot, can be applied to specific tasks. Example: to estimate wallpaper costs, a contractor could guess based on past jobs that it would cost $5 per square yard at the store and $2 per yard to have it installed for a total of $7 per yard needed.
Template Methods
If the project is similar to past projects they can be used as a starting point for the new project. Differences in the new project can be noted and past times and costs can be adjusted to accommodate them.
Top-Down Estimate Approaches
- Consensus Methods
- Ratio Methods
- Apportion Methods
- Function Point Methods- for software or system projects
Consensus Methods
The uses the pooled experience of senior or middle managers to estimate the total project duration and cost.
Ratio Methods
Example: contractors frequently estimate using square feet, 2700 square feet might cost 160 per square foot