Chapter 5 Project Control Flashcards
1
Q
What is BCWP & ACWP stand for?
A
Budgeted cost of work performed
Actual costs of work performed
2
Q
What is the process of front loading? Why is it done?
A
front loading is achieved by assigning higher costs to early activities, and lower costs to late activities, but keeping the total project cost unchanged. It is a common practice since the GC tends to have a lot of expenditures at the beginning of the project.