Chapter 3 - Planning and Scheduling Flashcards
1
Q
Dividing problems into small subparts is a common technique to understand and organize complex construction projects. This is applicable to both scheduling and cost estimating. Describe the steps:
A
1) Identify all tasks (aka Activities) necessary to accomplish a project
2) Identify the relationships and dependencies between these tasks
3) Define critical success factors and key milestone dates for each activity
2
Q
What are the 5 main characteristics of construction activities?
A
- Activities consume time
- Activities usually consume physical resources
- Activities have definable start and finish points.
- Activities are assignable.
- Activities are measurable