Chapter 5 Flashcards

1
Q

At the completion of a government project requiring security clearance, what document
would a vendor likely be asked to sign?
A. Nondisclosure agreement
B. Service-level agreement
C. Warranty
D. Request for proposal

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The EV for a project is 800, and the AC is 1200. The CPI for the project would be which one
of the following?
A. 1.5
B. 400
C. 2000
D. .667

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which document describes the goods or services an organization is interested in procuring
from outside the organization?
A. SOW
B. RFI
C. RFP
D. RFQ

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a software application that manages back-office activities such as accounting, human
resources, supply chain, operations, and procurement called?
A. Database management system (DBMS)
B. Enterprise resource planning (ERP)
C. Content management system (CMS)
D. Customer relationship management (CRM)

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The approved budget for given work to be completed within a specific timeframe is called
which one of the following?
A. Cost variance
B. Planned value
C. Earned value
D. Actual costs

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

All of the following are examples of deliverables EXCEPT:
A. Blueprints
B. User documentation
C. The finished product
D. Sign-off on the project charter

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly