Overhead absorption calculations

What is the calculation for Overhead Absorption Rate ?

A

OAR = Total budgeted cost centre overheads / Total planned work in the cost centre

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Overhead absorpiton calculations

What is the calculation for cost per direct labour hour ?

A

Cost per direct labour hour = Total cost centre overheads / Total direct labour hours (In cost centre)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Overhead absorpiton calculations

What is the calculation for cost per machine hour ?

A

Cost per direct labour hour = Total cost centre overheads / Total machine hours (In cost centre)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Overhead absorpiton calculations (Service sector)

What is the calculation for cost per hour of chargeable time ?

A

cost per hour of chargeable time = Total cost centre overheads / Total chargable hours (In cost centre)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Overhead absorpiton calculations (Service sector)

What is the calculation for cost per mile traveled ?

A

cost per mile traveled = Total cost centre overheads / Total miles traveled (In cost centre)