Chapter 4 Flashcards
1
Q
Defining Activities
A
- List of activities required to complete the project.
2
Q
Activity list
A
- Should include every activity needed to complete the work of the project.
3
Q
Activity Sequencing
A
- Process of identifying dependency relationships b/t project activities & sequencing them in proper order.
4
Q
Dependencies
A
- Relationships b/t activities
5
Q
Mandatory dependencies
A
- Type of work being performed
- one activity is dependent on another activity
6
Q
Discretionary dependencies
A
- Process or procedure-driven
- may include best-practice technics
7
Q
External dependencies
A
- Relationship b/t a project task & some factor outside the project that drives the scheduling of that task.
8
Q
Predecessor
A
- Activity is one that comes before another activity.
9
Q
Successor
A
- Activity is one that comes after the activity in question.
10
Q
Critical Path Method (CPM)
A
- longest full path on the project
11
Q
Forward Pass
A
- determining your critical path
- early start/early finish
12
Q
Backward Pass
A
- Start at the finish of your network diagram & work back through each path until you reach the start.
- late start/late finish
13
Q
Duration Compression
A
- used during planning to shorten the planned duration of the project or during project execution to help resolve schedule slippage.
14
Q
Crashing
A
- This is a schedule compression technique that adds resources to the project to reduce the time it takes to complete the project.
15
Q
Fast Tracking
A
- Performing two tasks in parallel that were previously scheduled to start sequentially.