Chapter 3 - Termination of contract Flashcards
What are the three main ways a contract can be discharged?
- Performance: Complete or substantial performance discharges the contract. Damages may be payable. Partial performance – but only if contract is severable.
- Frustration: The contract is impossible to perform due to unforeseen circumstances. No fault of either party.
- Breach: Failure to perform contractual obligations leads to remedies for the breach.
What is substantial performance?
When most obligations are completed, allowing the party to claim payment, although damages may still apply for incomplete parts.
What happens if a contract is discharged due to frustration?
Neither party is liable for failure to perform, provided the frustration was due to circumstances beyond their control, such as destruction of the subject matter or government intervention.
Can a contract be frustrated if alternative modes of performance are possible?
No, a contract is not frustrated if performance is still possible, even if it is more difficult or expensive.
What happens if one party prevents the other from performing their obligations under a contract?
The party prevented from performing is discharged from their obligations and may:
- Sue for damages for breach of contract.
- Bring a quantum meruit claim to recover payment for the work already completed (‘as much as they deserve’).
What is a quantum meruit?
Literal Meaning: ‘As much as he deserves’ in Latin.
Purpose: To prevent unjust enrichment by ensuring that a party who has provided a benefit is compensated fairly.
When It Applies:
- A contract is incomplete or frustrated.
- One party prevents the other from completing their obligations.
- There is no pre-agreed price for the work performed.
Example Scenarios:
A contractor starts work on a project but is prevented from completing it by the client. The contractor can claim quantum meruit for the value of the work already completed.
A service provider performs work without a finalized price, and the other party benefits from it. Quantum meruit allows the service provider to recover fair compensation.
It’s an equitable remedy to ensure fairness in situations where a contract fails or does not specify payment terms.
Example Scenarios:
- A contractor starts work on a project but is prevented from completing it by the client. The contractor can claim quantum meruit for the value of the work already completed.
- A service provider performs work without a finalized price, and the other party benefits from it. Quantum meruit allows the service provider to recover fair compensation.
What is frustration in contract law?
A contract is frustrated when it becomes impossible to perform due to circumstances beyond the parties’ control, such as destruction of the subject matter or government intervention.
Under what circumstances will a contract NOT be frustrated?
- If an alternative mode of performance is possible, even if it is more expensive or difficult.
- If a force majeure clause covers the situation – ‘what will you do in certain situations’.
Give examples of frustration scenarios.
- Destruction of subject matter (e.g., a venue burns down).
- Personal incapacity (e.g., a musician unable to perform due to illness).
- Government intervention (e.g., new laws prohibiting performance).
- Non-occurrence of a key event (e.g., cancellation of a planned event central to the contract).
What does the Law Reform (Frustrated Contracts) Act 1943 provide for frustrated contracts?
Recovery of money paid before frustration.
Payment of reasonable expenses incurred.
Compensation for any valuable benefit gained by one party before frustration.
What constitutes a breach of contract?
Failure to perform obligations under the contract without a lawful excuse.
What is a lawful excuse for non-performance of a contract?
- The other party has rejected performance.
- The other party has made performance impossible.
- The parties have agreed to non-performance.
What is a repudiatory breach?
A significant breach that deprives the injured party of the main benefit of the contract, allowing them to terminate and claim damages.
AT DATE
Agree to do something and its not done on the date of performance
What is an anticipatory breach? What can the injured party do?
When one party indicates before performance is due that they will not perform their contractual obligations, giving the other party the right to terminate or sue immediately.
PRIOR WARNING
Said I will not be turning up on day of performance between date of agreement and performance
Where the breach is sufficiently serious, the injured party may choose (at the time of the breach)
either to:
Treat the contract as discharged immediately and sue for damages
Allow the contract to continue until there is an actual breach and take action at that time.
If the innocent party elects to treat the contract as still in force, he may continue with his preparations for performance and recover the agreed price for his services. The duty to mitigate his losses does not arise until he accepts the breach.
What are the options for the injured party in the event of an anticipatory breach?
A. Treat the contract as discharged immediately and sue for damages.
B. Wait until there is an actual breach and take action then.
C. Both A and B.
D. Continue with the contract without any legal action.
C. Both A and B.
Correct Answer: C. Both A and B.
In an anticipatory breach, what is the injured party’s duty regarding mitigation of losses?
A. The duty arises immediately upon the breach.
B. The duty arises only when the breach is accepted by the injured party.
C. The injured party has no duty to mitigate losses.
D. The duty arises after legal proceedings commence.
B. The duty arises only when the breach is accepted by the injured party.
What remedies are available for a repudiatory breach of contract?
A. Refusal to accept further performance.
B. Reclaiming money already paid for defective performance.
C. Both A and B.
D. Continuing with the contract without recourse to damages.
C. Both A and B.
In the case of a repudiatory breach, what is the status of the injured party’s contractual obligations?
A. The party is discharged from all past and future obligations.
B. The party is discharged from future obligations but not past ones.
C. The party is still bound to all obligations.
D. The party must continue to perform until legal action is taken.
B. The party is discharged from future obligations but not past ones.
What is the purpose of awarding damages for breach of contract?
A. To punish the breaching party.
B. To put the injured party in the position they would have been in if the contract was performed.
C. To terminate the contract without compensation.
D. To ensure future performance of the contract.
B. To put the injured party in the position they would have been in if the contract was performed.
What are the two elements considered in awarding damages?
A. Value of the contract and moral culpability.
B. Remoteness of damage and measure of damages.
C. Severity of the breach and future implications.
D. Reasonableness of the clause and alternative options.
B. Remoteness of damage and measure of damages.
What are the key principles for awarding damages for breach of contract?
- Remoteness of damage: Damages must arise naturally or be within the parties’ contemplation.
- Measure of damages: Damages aim to put the claimant in the position they would have been in if the contract was performed.
Can abnormal losses be claimed as damages?
No, unless the breaching party was aware of the special circumstances causing the abnormal losses.
According to the rule of remoteness, when can damages be awarded?
A. When losses arise naturally or are reasonably foreseeable.
B. When the breach occurs, regardless of foreseeability.
C. Only if the contract explicitly provides for damages.
D. When the injured party can prove intent to harm by the breaching party.
A. When losses arise naturally or are reasonably foreseeable.
Louise runs a homemade cake business. Cook & Co contract to sell her a large industrial oven to enable her to expand her business by enabling her to increase cake production. Louise tells Cook & Co that she has also been awarded a contract to bake 100 jacket potatoes daily during November and December for a local street fair in the run up to Christmas and so needs the oven by 31 October. Cook & Co agree to deliver the oven by 28 October. Unknown to Cook & Co, Louise has also agreed to allow Bob the Baker to use the oven on Fridays (her day off) so that he can meet his extra customer demands over the weekends.
Owing to a dispute between the manufacturer and Cook & Co, the oven is not delivered to Louise until 12 November. Louise is therefore unable to fulfil the jacket potatoes contract and also is unable to increase cake production as planned. She has also lost the hire payment agreed by Bob in respect of two Fridays.
What is the legal position of Cook & Co?
Cook & Co were aware of the nature of her business and therefore will be liable to pay damages for her loss of normal profits arising from her inability to increase cake production between 28 October and 12 November. The losses on the baked potatoes contract are also recoverable from 1 – 12 November since, although they cannot be said to arise from the ordinary course of her business, Louise made Cook & Co aware of the contract. The agreement to let Bob hire the oven was not in the ordinary course of her business and the special circumstances were not known to Cook & Co, so they would not be liable for the loss of special profits on this contract.
When looking into the measure of damages, what 2 types of interest should we factor in?
Expectation and Reliance Interest.
Look at expectation first if not look at reliance to calculate
What is expectation interest?
To put the person in the position he would have been in if the contract had been performed.
What is reliance interest?
To put the claimant in the position he would have been in if he had not relied on the contract.
In what situation are damages for mental distress recoverable?
A. When financial loss is also claimed.
B. When the contract’s main purpose is enjoyment or pleasure.
C. When explicitly written into the contract.
D. When the breach involves gross negligence.
B. When the contract’s main purpose is enjoyment or pleasure.
Why were additional damages awarded in the holiday case?
Financial compensation alone did not address the disappointment and distress caused by the failure to provide the promised enjoyment, which was the contract’s principal purpose.
What is the claimant’s duty to mitigate loss in a breach of contract?
The claimant must take all reasonable steps to reduce their losses but is not required to take excessive or risky actions.
Can a claimant recover losses if they fail to mitigate them?
No, the claimant cannot recover avoidable losses. The defendant must prove that the claimant failed to take reasonable steps to reduce the losses.
Who bears the burden of proof to show that the claimant failed to mitigate their losses?
A. The claimant.
B. The breaching party.
C. The court.
D. An independent arbitrator.
B. The breaching party.
What are liquidated damages, and when are they enforceable?
Liquidated damages are a pre-agreed estimate of likely losses. They are enforceable if they represent a genuine attempt to predict actual damages rather than penalize the breaching party.
What is a penalty clause?
A penalty clause is a contractual term that imposes excessive liquidated damages and is not enforceable if it is disproportionate to the likely loss caused by a breach.