In which organizational form is it most difficult to integrate project activities?
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A

A. Classical/ Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
In which organizational form would the project manager possess the greatest amount of authority? 
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A

B. Projected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
In which organizational form does the project manager often have the least amount of authority?
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A

D. Weak Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
In which organizational form is the project manager least likely to share resources with other projects?
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A

B. Projected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
In which organizational form do project managers have the greatest likelihood of possessing reward power and have a wage-and -salary administration function? (the project and line manager are the same)
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A

A. Classical/ Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
In which organizational form is the worker in the greatest jeopardy of losing his or her job if the project gets canceled?
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A

B. Projected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
In which type of matrix structure would a project manager most likely have a command of technology?
A. Classical/ Traditional
B. Projected
C. Strong Matrix
D. Weak Matrix
A