Chapter 21 - Project Administration and Execution Flashcards

1
Q

An ICT infrastructure needs to be able to support new applications and technologies for ___ years

a. 1 to 3
b. 3 to 5
c. 5 to 7
d. 10 to 15

A

d. 10 to 15

p 21-2

An ICT infrastructure needs to be able to support new applications and technologies for 10-15 years. Therefore, this foundation needs to be carefully planned to ensure that the investment in infrastructure will support new technologies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

___ includes detailed review of the design documentation throughout the project where the ICT distribution designer is responsible for the workmanship and test results.

a. Quality management
b. Risk management
c. Integration management
d. Scope management

A

a. Quality management

p 21-7

Each project should have a quality management plan that includes detailed review of the design documentation throughout the project.

In the event that the ICT distribution designer is also responsible for the build portion of the project, then physical quality (i.e., workmanship) and test results would be part of this area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

___ of a project covers the breakup of a large project into multiple small projects

a. Risk management
b. Communications management
c. Scope management
d. Integration management

A

d. Integration management

p 21-7

Integration management of a project covers the breakup of a large project into multiple small projects or conversely, running several small projects as one large one.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

___ covers personnel issues, which involves engaging the right people to do the job and ensuring that they are properly trained, equipped, and motivated.

a. Scope management
b. Human resources management
c. Risk management
d. Stakeholder management

A

b. Human resources management

p 21-6

The human resources area of TPM covers personnel issues, which involves engaging the right people to do the job and ensuring that they are properly trained, equipped, and motivated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A(n) ___ describes the work to be performed or the services to be provided.

a. RFP
b. Execution plan
c. SoW
d. Construction documents

A

c. SoW

p 21-9

An SoW describes the work to be performed or the services to be provided. It describes tasks, directs methodologies to be used, and establishes the period of performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Specifications must be included in the contract documents to provide a clear and accurate description of the technical requirements for the materials used.

a. True
b. False

A

a. True

p 21-10

Specifications must be included in the contract documents to provide a clear and accurate description of the technical requirements for the materials used and the installation of those materials, including the procedures for commissioning the final product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The ___ is the contractual vehicle for expressing the specific agreement between the contractor and the owner of the project

a. RFP
b. Execution plan
c. SoW
d. Construction documents

A

c. SOW

p 21-10

The SoW is the contractual vehicle for expressing the specific agreement between the contractor and the owner of the project. Because the SoW defines the actual work to be performed, its accuracy has a direct impact on effective contract administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

It is recommended to include in the SoW requirements for legal, financial, or contract administration matters.

a. True
b. False

A

b. False

p 21-11

The SoW is only one part of the procurement process and contract development. Do NOT include in the SoW requirements for legal, financial, or contract administration matters. These requirements more appropriately belong in the RFP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The United States National Computer-Aided Design (CAD) Standard is developed and administered by the:

a. National Institute of Standards and Technology (NIST)
b. Construction Specifications Institute (CSI)
c. American Institute of Architects (AIA)
d. National Institute of Building Services (NIBS)

A

d. National Institute of Building Services (NIBS)

p 21-48

The NIBS wrote the introduction and is responsible for the administration and development of the standard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In project management, when using a PERT estimate, if there is a greater than _____ percent difference between the most likely and pessimistic estimates, the project is considered to be high-risk.

a. 20
b. 15
c. 10
d. 5

A

c. 10

p 21-24

If there is greater than a 10 percent difference between the most likely and pessimistic estimates, it is a high-risk project or activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In the MasterFormat 2012 numbering system, Division _____ is titled “Electrical.”

a. 27
b. 26
c. 17
d. 16

A

b. 26

p 21-45 Table 21.1

Telecom or Communications is Division 27

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A work breakdown structure (WBS) can be diagrammed as a ___ or a(n) ___.

a. Calendar chart; text report
b. Logic diagram; milestone chart
c. PERT chart; Gantt chart
d. Tree structure; outline

A

d. Tree structure; outline

p 21-18

The content of a WBS should be as specific as possible. A WBS can be diagrammed as a tree structure or an outline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A ___ type of specification allows contractors to choose the materials and installation methods to provide the desired results.

a. Reference
b. Design-build
c. Descriptive
d. Performance

A

d. Performance

p 21-43

Specifications are one of the elements produced during the design phase of a construction project. Performance— The focus is on results. Contractors can choose the materials and installation methods to provide the desired results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In project estimation, a cost performance index (CPI) of less than 1 indicates that the project is _____ budget.

a. Under
b. Over

A

b. Over

p 21-24

By determining the actual cost of work performed (ACWP) for each task that is completed and then accumulated similar to the budgeted cost of work performed (BCWP), the CPI can be calculated by using the following equation:

CPI = BCWP / ACWP

A CPI value less than 1 indicates the project is over budget, while a value greater than 1 is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In project estimation, if the budgeted cost of work performed (BCWP) is higher at a given time than the corresponding budgeted cost of work scheduled (BCWS), the project is considered to be _____ schedule.

a. Behind
b. Ahead of

A

b. Ahead of

p21-24

By comparing the BCWP with the initial BCWS, one can visually determine if the project is behind or ahead of schedule. If the BCWP is higher than the corresponding BCWS, the project is ahead of schedule. If the BCWP is below the BCWS, then the project is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In a _____ bid, bids and contracts for the mechanical, plumbing, and electrical portions of the project must be separate from the general construction contract.

a. Negotiated
b. Segregated
c. Syndicated
d. Multiple prime

A

d. Multiple prime

p 21-38

in the United States, bidding laws often require the mechanical, plumbing, and electrical portions of the work to be bid and contracted separately from the general construction contract. This is called a multiple prime bid or filed sub bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

___ estimates are based on the time or cost it took to perform similar work in the past.

a. Analogous
b. Parametric
c. Engineering
d. Subcontractor
e. PERT

A

a. Analogous

p 21-23

Analogous estimates are based on the time or cost it took to perform similar work in the past. The better the current costs are tracked, the more accurate the future
estimates will be. Analogous estimates must be adjusted for current job conditions (e.g., building size, construction type).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A(n) ___ estimates is handy for developing a rough order of magnitude estimate.

a. Analogous
b. Parametric
c. Engineering
d. Subcontractor
e. PERT

A

b. Parametric

p 21-23

Parametric estimates are based on dollar/foot, dollar/drop time, and cost. A parametric estimate is handy for developing a rough order of magnitude estimate and is used to check an analogy estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A PERT estimate usually falls between the ___ and ___ estimates.

a. Pessimistic, most likely
b. Most likey, Optimistic

A

a. Pessimistic, most likely

p 21-23

A PERT estimate usually falls between the pessimistic and most likely estimates. The greater the difference between the estimates, the greater the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A SPI values less than 1 indicates a project is ___

a. Behind schedule
b. Ahead of schedule

A

a. Behind schedule

p 21-24

SPI = BCWP / BCWS

An SPI value of 1 indicates a project is on schedule, whereas SPI values less than 1 indicate being behind schedule with values greater than 1 being ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A ___ is an accepted collection of requirements and recommendations for the defining, construction, evaluation, application, or comparison of materials, equipment, products, and services.

a. Code
b. Standard
c. Directive
d. Regulation

A

b. Standard

p 21-31

Standards may define processes, procedures, practices, or methods and are developed to improve the quality, function, performance, repeatability, or some other facet of the item being defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Compliance to a standard is an optional act

a. True
b. False

A

a. True

p 21-31

Compliance to a standard is a voluntary act unless otherwise specified by law, contract, or other legally binding article.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

___ may reference numerous ___ to ensure the minimum functional requirements of a given material or component.

a. Codes, standards
b. Standards, codes

A

a. Codes, standards

p 21-32

24
Q

Which one of the following is not a key member of the construction team.

a. Construction manager
b. Subcontractor
c. ICT designer
d. General contractor

A

c. ICT designer

p 21-34

25
Q

Once bids are received from the contractors, this type of delivery method ___, is where the owner and design professional will review these bids to award the contract.

a. Design-bid-build (DBB)
b. Design-build (DB)
c. Construction manager (CM) at risk
d. Integrated project delivery (IPD)

A

a. Design-bid-build (DBB)

p 21-37

The final phase is the construction phase, which consists of construction of the facility. The design professional typically will also have a role in overseeing the contraction at the owner’s request.

26
Q

In this delivery process ___, the construction typically is overlapping the design phase. This allows for an expedited schedule while minimizing any potential risk for the owner.

a. Design-bid-build (DBB)
b. Design-build (DB)
c. Construction manager (CM) at risk
d. Integrated project delivery (IPD)

A

b. Design-build (DB)

p 21-37

Unlike the DBB scenario, the design professionals generally work directly for the contractor.

27
Q

This approach ___ integrates all aspects of the design and construction process into a single team effort. This includes design professionals, CMs, and contractors.

a. Design-bid-build (DBB)
b. Design-build (DB)
c. Construction manager (CM) at risk
d. Integrated project delivery (IPD)

A

d. Integrated project delivery (IPD)

p 21-37

IPD uses a three-pronged platform with the owner as one entity, the design professionals as the second, and the contractors as the third.

28
Q

With this form of contract, ___ , there can be a shared savings clause or incentives for early completion.

a. Stipulated sum
b. Cost plus fee
c. Unit price

A

b. Cost plus fee

p 21-41

This form of contract often leads to value engineering that can generate savings during the construction phase of the building.

29
Q

In the design phases of a project, pricing for the required work is obtained using documents developed in the _____ phase.

a. Programming
b. Schematic design
c. Design development
d. Construction document

A

d. Construction document

p 21-25

Upon the owner’s approval of DD documents, the design team prepares the CDs. These are used to obtain pricing for the required work. CDs communicate the owner’s detailed requirements, coordination, and quality requirements in a set of CD drawings and specifications.

30
Q

Within the nine telecommunications project management (TPM) knowledge areas, project safety is covered in the area titled ___ management.

a. Quality
b. Risk
c. Scope
d. Human resources

A

d. Human resources

p 21-6

The human resources area of TPM covers personnel issues, which involves engaging the right people to do the job and ensuring that they are properly trained, equipped, and motivated.

Project safety, an issue where the telecommunications PM may have the greatest personal liability, can be managed by the human resources, risk management, and safety management departments. Any of these departments may have a responsibility to ensure that training for safety is provided to all project team members.

31
Q

In the design-build (DB) project delivery method, the design professionals generally work directly for the:

a. Architect
b. Consultant
c. Contractor
d. Owner

A

c. Contractor

p 21-37

Unlike the DBB scenario, the design professionals generally work directly for the contractor.

32
Q

The _____ document is the baseline standard for evaluating all proposals submitted by contractors for a project.

a. Organization breakdown structure (OBS)
b. Work breakdown structure (WBS)
c. Request for proposal (RFP)
d. Scope of work (SoW)

A

d. Scope of work (SoW)

p 21-10

The difficult and sometimes controversial function of proposal evaluation and contractor selection is based largely on the SoW, which is the baseline standard for evaluating all proposals

33
Q

In a _____, bids and contracts for the mechanical, plumbing, and electrical portions of the project must be separate from the general construction contract.

a. Trades prime bid
b. Segregated bid
c. Multi-bid
d. Filed sub bid

A

d. Filed sub bid

p 21-28

Additionally, in the United States, bidding laws often require the mechanical, plumbing, and electrical portions of the work to be bid and contracted separately from the general construction contract. This is called a multiple prime bid or filed sub bid.

34
Q

Before the 2004 edition, the MasterFormat included _____ divisions, with the telecommunications scope of work (SoW) included in Division _____.

a. 20; 19
b. 20; 16
c. 19; 19
d. 16; 16

A

d. 16; 16

p 21-44

Before the 2004 edition, the MasterFormat included 16 divisions as well as a summary of the front-end requirements. Telecommunications SoW was included within the electrical scope of Division 16.

35
Q

Periodic progress reports _____ classified as deliverables in the scope of work (SoW) document for a project.

a. Are not
b. Are

A

a. Are not

p 21-14

Periodic progress reports are not considered deliverables because they are not the final result of the task; rather, they are a management tool for monitoring progress toward the completion of a deliverable.

36
Q

In project estimation, if the budgeted cost of work performed (BCWP) is lower at a given time than the corresponding budgeted cost of work scheduled (BCWS), the project is considered to be _____ schedule.

a. Behind
b. Ahead of

A

a. Behind

p 21-24

By comparing the BCWP with the initial BCWS, one can visually determine if the project is behind or ahead of schedule. For example, if the BCWP is higher at Week 3 than the corresponding BCWS, the project is ahead of schedule. Similarly, if the BCWP is below the BCWS, then the project is behind schedule.

37
Q

In project estimation, another term for a budgeted cost of work scheduled (BCWS) is _____ value.

a. Budgeted
b. Earned
c. Estimated
d. Planned

A

d. Planned

p 21-24

BCWS is also known as planned value.

38
Q

A ___ type of specification allows contractors to choose the materials and installation methods to provide the desired results.

a. Reference
b. Design-build
c. Descriptive
d. Performance

A

d. Performance

p 21-43

Performance—The focus is on results. Contractors can choose the materials and installation methods to provide the desired results.

39
Q

A ___ type of specification requirements are based on an established standard.

a. Reference
b. Design-build
c. Descriptive
d. Performance

A

a. Reference

p 21-43

40
Q

A _____ type scope of work (SoW) tells the contractor the objectives and parameters to be accomplished and the end goal or desired achievement.

a. Specification
b. Quality
c. Design
d. Performance

A

d. Performance

p 21-11

The performance type tells the contractor the objectives and parameters to be accomplished and the end goal or desired achievement. The contractor proposes how these objectives will be accomplished.

41
Q

In project management, _____ bids are used to develop cost and time estimates for work that requires special tools or skills.

a. Specialty
b. Parametric
c. Engineering
d. Subcontractor

A

d. Subcontractor

p 21-23

Subcontractor bids—Subcontractor bids are used to develop cost and time estimates for work that requires special tools or skills. The subcontractor will provide the client a price that will not be exceeded. This provides an option to use the subcontract or to perform the work.

42
Q

The Uniform Drawing System (UDS) specified in the United States National Computer-Aided Design (CAD) Standard is produced by the:

a. National Institute of Standards and Technology (NIST)
b. Construction Specifications Institute (CSI)
c. American Institute of Architects (AIA)
d. National Institute of Building Services (NIBS)

A

b. Construction Specifications Institute (CSI)

p 21-48

NIBS wrote with introduction and is responsible for the administration and development of the CAD standard. AIA produces the CAD Layer Guidelines. CSI produced the Uniform Drawing System (UDS).

43
Q

A scope of work (SoW) is _____ that is used to establish requirements for the performance of work to achieve the project objectives.

a. A stand-alone document
b. Part of a request for proposal (RFP)

A

b. Part of a request for proposal (RFP)

p 21-9

The SoW is part of a RFP or RFQ.

A SoW is developed as a response to a statement of work provided by the client and establishes requirements for the performance of work to achieve the project objectives

44
Q

In the MasterFormat 2012 numbering system, the Communications division is located in the ___ Subgroup.

a. Site Services
b. Infrastructure Services
c. Site and Infrastructure
d. Facility Services

A

d. Facility Services

p 21-45 Table 21.1

45
Q

Which one of the following types of symbols in the United States National CAD Standard (NCS) is scale dependent?

a. Reference
b. Line
c. Identity
d. Template

A

d. Template

p 21-54

Template—Resemble the actual objects being symbolized. These symbols are scale dependent.

46
Q

MasterFormat uses a ___-digit format to represent ___ levels of hierarchy.

a. Nine; five
b. Six; three
c. Three; four
d. Three; three

A

b. Six; three

p 21-46

MasterFormat uses a six-digit format to represent three levels of hierarchy. An additional two levels are provided; the fourth is reserved for assignment by MasterFormat, and the fifth is open for user definition. The full five-level format is typically represented as:
11 22 33.44.55555

47
Q

The UDS, included with Version 6 if the NCS, includes _____ interrelated modules consisting of standards, guidelines, and other tools.

a. Nine
b. Eight
c. Seven
d. Six

A

b. Eight

p 21-50

48
Q

A fifth-level identifier in MasterFormat can consist of one to _____ entries.

a. Five alphanumeric
b. Five numeric
c. Four alphanumeric
d. Four numeric

A

a. Five alphanumeric

p 21-46

Levels one through four are represented by a digit between 0 and 9, whereas level five can be a combination of one to five alphanumeric entries (a-z, 9-9)

49
Q

In the design-bid-build (DBB) project delivery method, the design professionals generally work directly for the:

a. Architect
b. Consultant
c. Contractor
d. Owner

A

d. Owner

p 21-37

50
Q

Within the ten telecommunications project management (TPM) knowledge areas, calculation of the critical path of events on the project is covered under _____ management.

a. Resource
b. Time
c. Scope
d. Integration

A

b. Time

p 21-7

Time management of a project covers time estimates and schedules. It includes the integration of time schedules from various subteams and calculation of the critical path of events on the project.

51
Q

Which one of the following project management tools uses network diagrams to identify the chain of events that take the longest time to complete on projects?

a. Gantt chart
b. Earned value (EV) method
c. Critical path method (CPM)
d. Program evaluation and review technique (PERT)

A

c. Critical path method (CPM)

p 21-21

CPM uses a similar network diagram by identifying the chain of events that take the longest time to complete on the project. The end date of the project is determined and identified as the critical path.

52
Q

Which is NOT true about conformance quality?

a. It focuses on physical quality.
b. It involves evaluating customer satisfaction.
c. It requires work force training.
d. It includes inspections of work

A

b. It involves evaluating customer satisfaction.

p 21-25

Conformance quality—The first step in the quality evolution was called conformance, which focused on physical quality (e.g., neatness, test results). This step is still important and requires workforce training and quality inspections of the work. It follows the principle of plan, do, check, and act.

53
Q

Which of the following does NOT describe one of the four main types of specifications?

a. Based on an established standard
b. Focused on exact properties and installation methods
c. Calling out brand names and models
d. Listing maximum acceptable performance

A

d. Listing maximum acceptable performance

p 21-43

54
Q

Which is NOT a type of contract?

a. Contractor submits a fixed price for the SOW
b. Contractor is reimbursed for actual costs plus a fee
c. Unit price is used because the SOW cannot be determined prior to bid
d. Mediation panel assigns a fair price based on work completed

A

d. Mediation panel assigns a fair price based on work completed

p 21-40

55
Q

In project estimation, another term for a budgeted cost of work performed (BCWP) is _____ value.

a. Budgeted
b. Earned
c. Estimated
d. Planned

A

b. Earned

p 21-24

Earned value occurs as work is performed. As each task is completed, the budgeted amount is accumulated similar to the BCWS, but is called the BCWP.