Chapter 2 Flashcards

1
Q

When is it advisable to self-perform work?

A
  • When the project is small in scope, simple in character, and ongoing in nature
  • When the owner has a trained and skilled labour force
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which projects are good candidates for a CM approach?

A
  • large or complex projects when construction expertise is needed during design phase
  • projects that require flexibility as design evolves
  • projects to be delivered quickly (fast-tracked)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are some benefits of the GC approach

A
  • gives an idea of final project cost prior to construction
  • clearly defined roles for each contracting party
  • minimizes owner liability for cost overruns and late project delivery
  • contractors skills may reduce cost of construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between the CM approach and CM at Risk approach

A
  • In CM approach, CM is agent of owner

- In CM At Risk, CM is independent contractor, responsible to complete project by set date and budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some ways in which design-build projects are awarded

A
  • If scope is well defined, competitive approach with target cost
  • Or cost plus fixed fee w. GMP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some disadvantages of design-bid contracts (ie. GC approach)

A
  • Owner is exposed to greater probability of claims
  • Tight bids can lead to small margins
  • Awarding contracts to lowest bidder may result in contract with incompetent contractor
  • Approach often extends the project duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who represents the owner in a GC method

A

The firm responsible for the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How many contracts has the owner on a GC method and with who

A

2 contracts:

  • with designer
  • with constructor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Explain the difference between public & private sector for the GC method

A
  • In public: each party’s role is defined, it’s a rigid process, lowest bidder gets the contract
  • In private: the owner can select whichever GC he wants & negotiate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When the GC subcontracts all the work what is that called

A

Brokerage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is the Separate contract method appropriate

A

If the owner has the necessary in-house capabilities to manage the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Pro’s and con’s of separate contract method

A

pro’s: good for projects that require specialty work

con’s: owner assumes greater risk than the GC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is fast tracking and what method of construction uses it

A

Delivery of project to the owner before waiting that the design is complete. Design-Build and CM uses it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The CM is not responsible for what in the professional CM method

A
  • means and method of the construction
  • construction cost
  • Time & Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly