What is a boilerplate?
A
Also known as the general conditions, the boiler plate augments the construction contract and outline the rules under which the project will be built
2
Q
What are some benefits of using standard conditions
A
-they are familiar to all parties
-the wording is clearly understood
they have often been court-tested so that the legal interpretation is known
3
Q
What are some of the topics addressed in supplementary conditions?
A
Anything that is specific to the job being constructed, ie:
- specific information about material substitutions
- which materials the owner will provide
- the type of surveying information to be provided by the owner
- examination of the site
- cost reporting requirements