Chapter 18: Managing Product Delivery Flashcards

1
Q

What is the purpose of managing product delivery

A

Purpose is control the link between the PM and the team manager(s), by agreeing the requirements for acceptance, execution and delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Objectives if managing product delivery process

A
  • work on products allocated to the team is authorised and agreed
  • team managers, team members and suppliers are clear as to what is to be produced
  • planned products are delivered to expectations and within tolerance
  • accurate progress information is provided to PM at an agreed frequency to ensure expectations are managed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Managing Product Delivery - Context

A

Views the project from team managers perspective, whereas the controlling a stage process views it from the PM’s perspective

Team manager ensures products are created and delivered by the team to the project by:
- accepting and checking authorised work packages from PM
- ensuring interfaces identified in work package are maintained
- create a team plan for work packages being assigned
- ensure that products are developed in accordance with any development methods
- obtaining approval for completed products from the authorities identified in the product description
- delivering the products to the PM in accordance with any procedures specified in the work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the activities within the managing product delivery process?

A

Accepts a work package

Execute a work package

Deliver a work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Accept a work package - context

A

Before a work package is allocated to a team, there should be an agreement between the PM and the team manager as to what is to be delivered.

This should cover the reporting requirements, what constraints apply, procedures to be applied and whether requirements for work package are reasonable/can be achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Prince2 recommends the following actions regarding accepting a work package

A

Review the work package:
- obtain any referenced documentation
- clarify with PM what is to be delivered
- negotiate with the PM, on behalf of the team,the constraints within which the work is to be done
- agree tolerances for the work package

Produce a team plan to show which products can be completed within constraints

Consult with supplier that team plan is viable

Seek necessary approval for team plan

Undertake a review of the risks against the team plan and advise the PM of any additional/ modified risks

Consult with project assurance as to whether any extra reviewers are required and ensure that quality register is updated accordingly

Agree to deliver the work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Execute a work package - context

A

The work has to be executed and monitored to the requirements in the authorised work package

Team manager can only proceed with work package or take corrective action whilst work package is forecast to be completed within tolerances set by PM. As soon as work package tolerances are forecast to be exceeded, the team manager should raise an issue to PM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Prince2 recommends the following actions regarding executing a work package

A

Manage the development if the required products

Notify the PM of any new issues and risks associated with the work package and advise the PM of their status

Take the action required by the PM

Obtain approvals for completed products

Review and report the status of the work package to the PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Deliver a work package - context

A

Just as the work package was accepted from the PM, notification of its completion must be returned to the PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Prince2 recommends the following actions regarding delivery of a work package

A

Review quality register to verify that all quality activities associated with work package are complete

Review the approval records to verify that all the products to be delivered by the work package are approved

Update the team plan to show that the work package is complete

Check the work package and follow the procedure to deliver the completed products

Notify the PM that the work package is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Tailoring products in managing product delivery

A

Team plan
- team plan may be subset of the stage plan, and may be informal or formal
- team plan may include components in any format commensurate with the complexity of the work package, with views ranging from a simple list of accountabilities, products and activities
- team plan should be developed at same time as stage plan, not waiting for work package

Checkpoint report
- checkpoint reports may be informal or formal, depending on the context
- if PM meets with the team members regularly, then a verbal update, captured by the project manager in a daily log need to be used to create highlight report, may be sufficient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Tailoring roles in managing product delivery

A

Team ma aged is responsible for all activities but may be supported by team members but may be supported by team members

Although prince2 processes define who creates and approves a work package, responsibilities may be changed provided the PM and Team manager are in agreement on what the work package comprises.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Product delivery using agile approach

A

In agile working, delivery is done iteratively

Progress information would be visible on an information radiator which is frequently updated by the way of daily activities if working in an agile way. This provides the information for the project manager to manage the project at the stage level by having clear and regular information across all the teams at the delivery level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly