Chapter 15: Directing A Project Flashcards

1
Q

What’s the purpose of the directing a project process

A

Enables the project board to be accountable for the projects success by making decisions and exercising overall controls while delegating day to day management of the project board to the project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When does the directing a project process start

A

The directing a project process starts on completion of the starting up a project process and is triggered by the request to initiate a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Info regarding directing a project process

A

The directing a project process covers the activities of the project board and isn’t concerned with the day to day activities of the project manager. (The project board manages by exception)

The project manager will inform the project board of any exception situation. It’s also important that levels of authority and decision making processes are clearly identified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How should info between project board & corporate, programme management or the customer flow

A

There must be a two way flow of info between project board & corporate, programme management or the customer during the project.

At all times, the project board must ensure that the project remains aligned with the strategy of corporate, programme management or the customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Info regarding project board communication

A

It’s a key role of the project board to act as a communication Channel

The requirement for the project board to act as a communication channel, and how it’s going to do it, should be documented in the communication management approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why should project board provide unified direction and guidance to the project manager

A

If the project board is unable to provide a single view, or if independent, possibly contradictory, advice is given and the risk of project failure significantly increases.

In such cases the project manager should refer to the executive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which 5 activities are involved in the directing a project process

A
  • authorise initiation
  • authorise the project
  • authorise a stage or exception plan
  • give ad hoc (for this) direction
  • authorise project closure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When request to initiate a project is received, the project board must decide whether to allow the prime time to proceed to initiation stage

What must be reviewed and verified in the authorise initiation stage?

A

Review and approve project brief
- confirm the project definition
- confirm the project approach
- formally confirm the appointments to the project management team, and confirm that all members have agreed their roles

Review and approve the project product description
- confirm the customers quality expectations
- confirm the acceptance criteria

Verify that outline business case demonstrates a viable project

Review and approve the stage plan for the initiation stage
- understand any risks to authorisation of initiation
- obtain or commit the resources needed by the stage plan
- ensure ghat adequate reporting and control mechanisms are in place for the initiation stage and set tolerances for it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What occurs in the authorising a project stage

A

Decision has to be made about whether to proceed with the rest if the project

The project board has to confirm that:
- an adequate and suitable business case exists and that it shows a viable project
- the project plan and the benefits management approach
- project plan approaches and controls support delivery of the project plan
- mechanisms for measuring and reviewing the projected benefits are established and planned

If project isn’t authorised by project board, it should be prematurely closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does prince2 recommend you do when project has been authorised

A

Review and approve the PID

Review and approve the benefits management approach. Confirm it addresses all the expected benefits and meets the needs of corporate, pm , c

Notify corporate, pm, c and other interested parties that the project is authorised

Authorise the project manager to deliver the project or instruct project manager to close the project prematurely if it has been decided to not proceed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Info regarding exception plans

A

If an exception plan has occurred during the management stage, project board may request that the project manager produces and exception plan for project board approval.

If approved, the exception plan will replace the plan that is in exception and will become the new baselines plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should occur in the authorise a stage or exception plan point

A

Review and approve end stage report:
- ascertain the performance of the project to date, asking the project manager to explain any deviations from the approved plans and to provide a forecast of project performance for reminder of project
- include lessons from lessons log
- check risk summary to ensure the exposure is still acceptable and that risk responses for both opportunities and threats are appropriate and planned

Review stage plan/ exception plan for which project manager is seeking approval:
- confirm validity and achievability of plan
- review and approve any new product descriptions
- confirm approaches and project controls in the PID are adequate for remainder of project

Make a decision
- approve the plan and authorise PM to proceed

Communicate the status of the project to corporate, programme management or the customer and keep other interested parties informed about project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which circumstances may prompt ad hoc direction

A
  • responding to requests
  • responding to reports
  • responding to external influences
  • project board members individual concerns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the two options for the project board if corporate, programme management or the customer decides to change the project mandate

A

Treat it as a request for change

Stop, and restart the project by triggering pre,suture closure - any result in additional costs compared with request for change option

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What occurs in the give ad hoc direction stage in response to informal requests for advice and guidance

A

Project board members may offer informal guidance or respond to requests for advice at any time during a project

In response to informal requests for advice and guidance:
- seek advice from corporate, programme management or customer if necessary
- assist the PM as required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What occurs in the give ad hoc direction stage in response to an escalated issue

A

seek advice from corporate, programme management or the customer if necessary

Make a decision within the project boards delegated limits of authority. This could be regarding:
- a problem/ concern
- a request for change
- an off specification

17
Q

What occurs in the give ad hoc direction stage in response to an exception report

A

Seek advice from corporate, programme management or the customer if necessary

Make a decision, within the project boards delegated limits of authority, to:
- increase tolerances that are forecast to be breached
- instruct the PM to produce an exception plan (stating what willbe acceptable)
- instruct the PM to close the project prematurely

18
Q

What occurs in the give ad hoc direction stage in response to the receipt of a highlight report

A

Review the highlight report to understand the status of the project

Ensure the management stage is progressing according to plan

Keep corporate, programme management or the customer informed about project progress, as defined by the communication management approach

19
Q

What occurs in the give ad hoc direction stage in response to advice and decisions from corporate, programme management or the customer

A

Ensure that the project management team is kept informed of external events that may affect it

Notify project manager team is kept informed of external events that may affect it

20
Q

What actions are recommended for the authorising project closure stage

A

Review original and current versions of PID to understand projects initial baseline, and current approaches and controls

Review and approve end project report to:
- understand the projects actual performance against its initial basis, including a summary of any deviations of approved plans
- assess the choice of project approach
- confirm who should receive which follow on action recommendation as summarised in the end project report

Ensure post project benefits reviews defined by the updated benefits management approach cover the performance of the project product in operational use in order to identify whether there have been any side effects

Confirm the updated business case

Review and issue a project closure notification in accordance with the communication management approach